EUROPA CLIPPER PROJECT THE CONTRACT IS THE SPONSORING AGREEMENT BETWEEN THE NATIONAL AERONAUTICS AND SPACE ADMINISTRATION NASA AND THE CALIFORNIA INSTITUTE OF TECHNOLOGY-CONTRACTOR, A PRIVATE NONPROFIT EDUCATIONAL INSTITUTION, WHICH ESTABLISHES THE RELATIONSHIP FOR THE OPERATION OF THE FEDERALLY FUNDED RESEARCH AND DEVELOPMENT CENTER-FFRDC KNOWN AS THE JET PROPULSION LABORATORY. THE CONTRACTOR, JPL, IS REQUIRED TO PERFORM WORK THAT IS DESIGNATED IN TASK ORDERS ISSUED BY THE NASA MANAGEMENT OFFICE-NMO CONTRACTING OFFICERS. NASA-SPONSORED WORK: JPLS PRIMARY MISSION IS TO SUPPORT THE NASA SCIENCE MISSION DIRECTORATE-SMD IN CARRYING OUT THE SPECIFIC OBJECTIVES IDENTIFIED IN THE SMD SCIENCE PLAN. THE FOUR BROAD SCIENTIFIC AREAS ARE: EARTH SCIENCE, PLANETARY SCIENCE, HELIOPHYSICS, AND ASTROPHYSICS. IN PERFORMANCE OF THIS CONTRACT, JPL SHALL: 1. SUPPLY A BROAD BASE OF SCIENTIFIC AND TECHNICAL CAPABILITIES RELEVANT TO NASA PROGRAM AND PROJECT RESPONSIBILITIES AND ASSIGNMENTS. 2. FOSTER ITS UNIQUE RELATIONSHIP WITH A TOP-TIER UNIVERSITY TO FACILITATE THE INVOLVEMENT OF SCIENTISTS, ENGINEERS, AND STUDENTS FROM THE UNIVERSITY AND RESEARCH COMMUNITIES IN NASA MISSION AND IN SUPPORTING OTHER GOVERNMENT AGENCIES. 3. SUPPORT NASA IN ENABLING PROGRAM AND INSTITUTIONAL CAPABILITIES. 4. DEVELOP SPACECRAFT AND INSTRUMENTS THAT ARE SENT TO VARIOUS DESTINATIONS WITH OUR SOLAR SYSTEM, INCLUDING EARTH ORBIT, PLANETS, PLANETARY SATELLITES, ASTEROIDS, AND COMETS. THESE MISSIONS MAY BE ORBITERS, LANDERS, OR ROVERS, AND TYPICALLY INCLUDE CUTTING-EDGE TECHNOLOGIES REQUIRED TO MEET SCIENTIFIC REQUIREMENTS. 5. PERFORM PROJECT TASKS INVOLVING: I-AUTONOMOUS DEEP-SPACE, INNER-SPACE AND EARTH-ORBITING SPACECRAFT OR MAJOR SUBSYSTEMS, II-EXPERIMENTS, INSTRUMENTS, OR OTHER DEVICES WHICH MAY BE CARRIED AS PAYLOAD ON SPACECRAFTS IN MISSIONS MANAGED BY OTHERS, AND-OR III-GROUND-BASED SYSTEMS. 6. BEYOND ITS PRIMARY MISSION, JPL MAY PERFORM WORK FOR OTHER NASA MISSION DIRECTORATES OR OFFICES. 7. JPL IS ALSO RESPONSIBLE FOR THE OPERATION, RESEARCH, TECHNOLOGY INSERTION, AND MANAGEMENT OF NASAS DEEP SPACE NETWORK TO PROVIDE TELECOMMUNICATION AND OPERATION SERVICES, INCLUDING DATA ACQUISITION AND DATA DELIVERY REQUIRED TO MEET ESTABLISHED AGENCY OBJECTIVES. 8. JPL IS ALSO REQUIRED TO MAINTAIN AND CONDUCT AN EDUCATION PROGRAM IN CLOSE COORDINATION WITH THE NASA HEADQUARTERS EDUCATION OFFICE, THE ACADEMIC COMMUNITY AT LARGE, AND IN SUPPORT TO NASA STRATEGIC OBJECTIVES TO IMPROVE STUDENT RETENTION IN THE SCIENCE, TECHNOLOGY, ENGINEERING, AND MATHEMATICS-STEM DISCIPLINES. WORK FOR NON-NASA SPONSORS: JPL MAY PERFORM WORK FOR NON-NASA SPONSORS. THIS WORK WILL BE DESIGNATED IN TASK ORDERS ISSUED BY NMO CONTRACTING OFFICERS BASED ON TASK PLANS INITIATED BY THE CONTRACTOR.
Delivery Order · National Aeronautics and Space Administration · to California Institute of Technology (UEI YC1YP79BFD19) · data as of 2026-09-30
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
44 actions since 2022-10-06. Each is a modification or amendment with the money it added or took back.
Date
Modification
Kind
Amount
What the agency wrote
2026-09-28
P00082
Funding only
$72.2K
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2026-09-01
P00081
Funding only
$6.09M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2026-08-20
P00080
Administrative change
$0
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2026-08-13
P00079
Funding only
$677.0K
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2026-07-14
P00078
Funding only
$3.0K
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2026-06-30
P00077
Supplemental agreement (work within scope)
$0
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2026-06-29
P00076
Funding only
$14.9K
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2026-06-09
P00075
Funding only
$20.19M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2026-05-20
P00074
Funding only
$1.53M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2026-03-23
P00073
Funding only
$21.00M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2025-12-03
P00072
Funding only
$24.63M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2025-09-25
P00071
Supplemental agreement (work within scope)
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
$23.99M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH PHASE E (40-19123)
2025-09-15
P00070
Funding only
$120.8K
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH E (40-19123)
2025-07-24
P00069
Funding only
$20.00M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH E (40-19123)
2025-05-14
P00068
Funding only
$1.34M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH E (40-19123)
2025-04-25
P00067
Funding only
$20.00M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH E (40-19123)
2025-04-07
P00066
Funding only
$5.00M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH E (40-19123)
2025-03-12
P00065
Supplemental agreement (work within scope)
$6.77M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH E (40-19123)
2025-03-10
P00064
Supplemental agreement (work within scope)
$0
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2025-03-03
P00063
Funding only
$13.83M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2025-01-07
P00062
Supplemental agreement (work within scope)
$500.0K
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-12-16
P00061
Funding only
$6.36M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-10-21
P00060
Funding only
$30.00M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-09-23
P00059
Supplemental agreement (work within scope)
$0
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-08-26
P00058
Funding only
$31.76M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-07-30
P00057
Funding only
$14.3K
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-07-15
P00056
Funding only
$31.5K
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-06-11
P00055
Funding only
$4.4K
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-06-03
P00054
Funding only
$62.73M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-05-10
P00053
Funding only
$1.36M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-05-08
P00052
Supplemental agreement (work within scope)
$0
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-04-03
P00051
Funding only
$54.50M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-02-21
P00050
Funding only
$25.61M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-01-24
P00049
Funding only
$20.50M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-01-05
P00048
Funding only
$39.67M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2024-01-03
P00047
Funding only
-$39.67M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2023-12-12
P00046
Funding only
$39.67M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2023-11-13
P00045
Funding only
$22.66M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2023-10-06
P00044
Funding only
$15.24M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2023-08-01
P00043
Funding only
$40.12M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2023-07-19
P00042
Administrative change
$0
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2023-03-13
P00041
Funding only
$147.90M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2022-12-28
P00040
Funding only
$50.00M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)
2022-10-06
P00039
Funding only
$45.00M
EUROPA CLIPPER PROJECT: PRE-PHASE A THROUGH C/D (40-19123)