MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY AND NAVAL NUCLEAR PROPULSION PROGRAM SUPPORT
Up for re-bid: ends 2028-09-30. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
2738 subawards totaling $2.65B (35.3% of what was obligated), as Fluor Marine Propulsion, LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Kiewit Power Constructors Co | $1.47B | 6 | KS | 2024-02-08 | 2025-11-24 |
| Amentum Joint Venture LP | $88.99M | 3 | SC | 2026-03-02 | 2026-03-12 |
| Mascaro Construction Co LP | $77.18M | 9 | PA | 2024-10-03 | 2026-07-27 |
| Fluor Corporation | $67.13M | 100 | SC | 2023-12-07 | 2026-06-29 |
| Colossal Contracting LLC | $64.92M | 202 | MD | 2022-10-24 | 2026-07-30 |
| Wainschaf Associates Inc | $37.12M | 1 | NY | 2025-08-26 | 2025-08-26 |
| CTG Federal, LLC | $36.39M | 41 | VA | 2022-12-13 | 2026-06-17 |
| Synergy Modular, Inc. | $30.61M | 1 | AZ | 2025-09-23 | 2025-09-23 |
| Goldbelt, Incorporated | $29.57M | 7 | PA | 2022-10-10 | 2023-12-20 |
| BWSR LLC | $25.00M | 1 | VA | 2023-07-06 | 2023-07-06 |
| Amentum Holdings Inc. | $24.96M | 2 | TN, VA | 2025-09-26 | 2025-11-07 |
| Bart & Associates, LLC | $22.16M | 1 | VA | 2025-09-18 | 2025-09-18 |
| Hexagon US Federal, Inc | $21.96M | 2 | AL | 2025-06-26 | 2026-02-18 |
| Minburn Technology Group, LLC | $19.41M | 1 | VA | 2024-05-16 | 2024-05-16 |
| GRM Kontracting LLC | $18.57M | 23 | PA | 2022-11-04 | 2026-04-28 |
| Westwind Computer Products, Inc. | $17.38M | 56 | NM | 2022-10-27 | 2026-07-06 |
| Multi-Phase Contracting Corp. | $16.63M | 8 | NY | 2023-03-01 | 2025-06-09 |
| Stanton Industrial Electric Supply, Inc | $15.77M | 5 | PA | 2024-01-17 | 2024-12-18 |
| Consigli Construction Co., Inc. | $14.23M | 2 | MA | 2024-10-01 | 2025-09-25 |
| Sterling Computers Corporation | $14.08M | 93 | SD | 2022-11-28 | 2026-07-31 |
| Battelle Memorial Institute | $12.72M | 21 | ID, WA | 2022-10-11 | 2026-03-24 |
| Information Management Group Incorporated | $11.72M | 8 | VA | 2024-02-08 | 2025-07-14 |
| Mirion Technologies (US), Inc. | $11.49M | 23 | CT | 2024-10-15 | 2026-07-16 |
| American Crane & Equipment Corp | $10.98M | 5 | PA | 2024-05-08 | 2024-12-04 |
| Dynamic Systems, Inc. | $10.27M | 16 | CA | 2022-10-27 | 2026-07-28 |
The 25 largest of 939; the rest are on USAspending.gov.
| Date | To | Amount | For |
|---|---|---|---|
| 2025-05-30 | Kiewit Power Constructors Co | $1.15B | CONSTRUCTION SUBCONTRACT (CS)-111G BUILDING OUTFITTING |
| 2025-05-09 | Kiewit Power Constructors Co | $96.96M | CS-111G |
| 2026-03-02 | Amentum Environment & Energy, Inc. | $85.07M | NEAP DETAILED DESIGN WITH OPTIONAL FOLLOW |
| 2024-10-31 | Kiewit Power Constructors Co | $66.04M | CONSTRUCTION SUBCONTRACT CS-108 MISCELLANEOUS METAL FABRICATION & ERECTION |
| 2025-05-04 | Mascaro Construction Co LP | $55.33M | COMPONENT TEST COMPLEX (CTC) DESIGN-BUILD CONSTRUCTION |
| 2025-11-24 | Kiewit Power Constructors Co | $52.15M | CS-107 |
| 2025-05-04 | Kiewit Power Constructors Co | $52.08M | CS-113 |
| 2024-02-08 | Kiewit Power Constructors Co | $52.00M | ROOFING AND SIDING FOR SFHP |
| 2025-08-26 | Wainschaf Associates, Inc. | $37.12M | KNOLLS SECURITY UPGRADES PROJECT |
| 2025-09-23 | Synergy Modular, Inc. | $30.61M | NRF MEDICAL SCIENCE COMPLEX |
| 2023-07-06 | BWSR LLC | $25.00M | TASK ORDER NO. 1, IDIQ 7019318 |
| 2025-11-07 | Amentum Technology, Inc. | $24.52M | SFHP ER RECAPITALIZATION PROJECT |
| 2025-09-18 | Bart & Associates, LLC | $22.16M | RECORDS DECLASSIFICATION REVIEW PROJECT |
| 2025-06-26 | Hexagon US Federal, Inc | $21.94M | RECORDS DECLASSIFICATION REVIEW PROJECT |
| 2025-06-26 | Fluor Marine Propulsion, LLC | $21.94M | RECORDS DECLASSIFICATION REVIEW PROJECT |
| 2023-03-30 | Facility Support Services LLC | $19.90M | SDL/BRES DESIGN-BUILD CONSTRUCTION CONTRACT, PER ATTACHED DOCUMENTS |
| 2024-05-16 | Minburn Technology Group, LLC | $19.41M | MICROSOFT ENTERPRISE AGREEMENT |
| 2024-02-15 | Stanton Industrial Electric Supply, Inc | $14.90M | CS-111E1 ELECTRICAL EQUIPMENT |
| 2025-09-25 | Fluor Marine Propulsion, LLC | $14.17M | CONSTRUCTION OF KS FIREHOUSE |
| 2025-09-25 | Consigli Construction Co., Inc. | $14.17M | CONSTRUCTION OF KS FIREHOUSE |
| 2024-05-09 | Multi-Phase Contracting Corp. | $11.41M | CONSTRUCTION CONTRACT FOR THE DATA CENTER POWER AND CAPACITY UPGRADE GPP |
| 2024-07-24 | Avantech, LLC | $9.67M | CS-111E3 POOL FILTRATION MECHANICAL SKIDS |
| 2024-12-04 | American Crane & Equipment Corp | $9.48M | CRANES E1 AND E4 REPLACEMENT PROJECT |
| 2026-04-30 | Eastern Heating & Cooling, Inc. | $9.45M | DDC SERVICE CONTRACT |
| 2025-09-24 | Quanta Government Solutions, LLC | $8.60M | TRANSPORTER TRANSFER PATH (TTP) |
81 actions since 2022-10-27. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-29 | P00150 | Funding only | $1.05M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $1,054,000.00 FROM $5,843,408,672.01 TO $5,844,462,672.01 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FROM $15 |
| 2026-08-31 | P00149 | Funding only | $4.88M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $4,885,000.00 FROM $5,838,523,672.01 TO $5,843,408,672.01 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FROM $15 |
| 2026-08-26 | P00148 | Funding only | -$4.40M | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $4,400,000.00 FROM $5,842,923,672.01 TO $5,838,523,672.01 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE A DECREASE FROM $15, |
| 2026-07-30 | P00147 | Funding only | $11.60M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $14,364,967.00 FROM $5,828,558,705.01 TO $5,842,923,672.01 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FROM $1 |
| 2026-07-30 | P00146 | Funding only | -$44.41M | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $44,410,000.00 FROM $5,872,968,705.01 TO $5,828,558,705.01 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE A DECREASE FROM $15 |
| 2026-07-07 | P00145 | Funding only | $4.85M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $4,852,700.15 FROM $5,868,116,004.86 TO $5,872,968,705.01 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FROM $15 |
| 2026-07-06 | P00144 | Funding only | -$500.0K | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $500,000.00 FROM $5,868,616,004.86 TO $5,868,116,004.86 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE A DECREASE FROM $15,20 |
| 2026-06-11 | P00143 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS ADMINISTRATIVE ACTION ONLY FOR THE OPTION TERM FOR CONTRACT 89233018CNR000004 WITH FLUOR: 1. REVISION SECTION C, DESCRIPTION AND SPECIFICATIONS, TO ADD RELATED SERVICES (F)(3). 2. REVISION DEPARTMENT OF ENERGY IM |
| 2026-05-29 | P00142 | Funding only | $37.33M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $37,330,907.67 FROM $5,831,285,097.19 TO $5,868,616,004.86 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FROM $1 |
| 2026-05-29 | P00141 | Funding only | -$30.85M | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $30,853,535.67 FROM $5,862,138,632.86 TO $5,831,285,097.19 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE A DECREASE FROM $15 |
| 2026-04-29 | P00140 | Funding only | $3.81M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $18,233,888.09 FROM $5,843,904,744.77 TO $5,862,138,632.86 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FROM $1 |
| 2026-04-29 | P00139 | Funding only | -$2.45M | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $2,450,000.00 FROM $5,846,354,744.77 TO $5,843,904,744.77 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE A DECREASE FROM $15, |
| 2026-03-31 | P00138 | Funding only | $16.45M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $68,993,659.94 FROM $5,777,439,124.83 TO $5,846,354,744.77 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FROM $1 |
| 2026-02-26 | P00137 | Funding only | $1.29B | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $1,287,198,510.52 FROM $4,490,162,574.31 TO $5,777,361,084.83 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FROM |
| 2026-01-29 | P00136 | Funding only | $67.50M | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE AND INCREASE DIFFERENT LINES OF ACCOUNT SUPPORTING THE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $67,495,000.00 FROM $4,422,667,574.31 TO $4,490,162,574.31 FOR THE OPTION TERM. THE TOTAL AMOU |
| 2025-12-11 | P00135 | Funding only | $432.0K | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $432,000.00 FROM $4,422,235,574.31 TO $4,422,667,574.31 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FROM $ |
| 2025-11-28 | P00134 | Funding only | $600.34M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $600,339,092.30 FROM $3,821,896,482.01 TO $4,422,235,574.31 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FR |
| 2025-11-12 | P00133 | Funding only | $40.62M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $72,963,423.51 FROM $3,748,933,058.50 TO $3,821,896,482.01 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FRO |
| 2025-11-06 | P00132 | Funding only | -$33.03M | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE THE CONTRACT FUNDING AND UPDATE LIST B FOR 89233018CNR000004 WITH FLUOR BY $33,035,000.00 FROM $3,781,968,058.50 TO $3,748,933,058.50 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD |
| 2025-10-29 | P00131 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE THIRD (3RD) YEAR OF THE OPTION TERM FEE AND FY26 SMALL BUSINESS GOALS FOR CONTRACT 89233018CNR000004 WITH FLUOR. |
| 2025-10-24 | P00130 | Funding only | -$18.20M | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE THE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $18,200,000.00 FROM $3,800,168,058.50 TO $3,781,968,058.50 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE A DECREASE FROM |
| 2025-09-23 | P00129 | Funding only | $14.40M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $14,395,020.97 FROM $3,785,773,037.53 TO $3,800,168,058.50 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FRO |
| 2025-09-22 | P00128 | Funding only | -$14.20M | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE THE CONTRACT FUNDING AND UPDATE SECTION J ATTACHMENT 3 (LIST B) FOR 89233018CNR000004 WITH FLUOR BY $14,200,000.00 FROM $3,799,973,037.53 TO $3,785,773,037.53 FOR THE OPTION TERM. THE TOTAL AMOUNT OF TH |
| 2025-08-28 | P00127 | Funding only | $13.60M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT FUNDING FOR 89233018CNR000004 WITH FLUOR BY $13,600,000.00 FROM $3,786,373,037.53 TO $3,799,973,037.53 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT FUNDING WOULD BE AN INCREASE FRO |
| 2025-08-26 | P00126 | Funding only | -$13.82M | THE PURPOSE OF THIS MODIFICATION IS TO DECREASE CONTRACT 89233018CNR000004 WITH FLUOR BY $13,824,000.00 FROM $3,800,197,037.53 TO $3,786,373,037.53 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT WOULD BE A DECREASE FROM $13,134,592,148.11 TO $ |
| 2025-07-31 | P00125 | Funding only | $749.2K | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CONTRACT 89233018CNR000004 WITH FLUOR BY $749,249.02 FROM $3,799,447,788.51 TO $3,800,197,037.53 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT WOULD BE AN INCREASE FROM $13,133,842,899.09 TO $13 |
| 2025-07-30 | P00124 | Funding only | -$1.07M | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE LIST B, REMOVE DEAR CLAUSE 970.5226-1 PER EXECUTIVE ORDER 14151, SECTION G OF THE CONFORMED CONTRACT POINT OF CONTACT REVISED, AND DECREASE IN FUNDING. |
| 2025-06-25 | P00123 | Funding only | $2.16M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT 89233018CNR000004 WITH FLUOR BY $2,159,600.00 FROM $3,798,354,165.10 TO $3,800,513,765.10 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT WOULD BE AN INCREASE FROM $13,132,749,275.68 |
| 2025-06-24 | P00122 | Funding only | -$4.36M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) DECREASE OBLIGATED FUNDS BY $4,357,522.17 MODIFY SECTION J: BASELINE LIST OF APPLICABLE DIRECTIVES (LIST B) |
| 2025-06-11 | P00121 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXECUTE ADMINISTRATIVE CHANGES TO THE CONFORMED CONTRACT 89233018CNR000004 WITH FLUOR. 1. FAR CLAUSES 52.222-21, 52.222-26, AND 52.222-29 HAVE BEEN REMOVED. 2. FAR CLAUSE 52.244-6 HAS BEEN INCORPORATED IN TH |
| 2025-05-30 | P00120 | Funding only | $621.47M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT 89233018CNR000004 WITH FLUOR BY $621,471,268.08 FROM $3,181,240,419.19 TO $3,802,711,687.27 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT WOULD BE AN INCREASE FROM $12,515,635,529.7 |
| 2025-05-28 | P00119 | Funding only | -$3.66M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) INCREASE OBLIGATED FUNDS BY $621,471,268.08 |
| 2025-05-13 | P00118 | Funding only | $202.73M | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE BY $216,316,697.77 FROM $2,968,586,386.52 TO $3,184,903,084.29 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE CONTRACT WOULD BE INCREASE FROM $12,302,981,497.10 TO $12,519,298,194.87. THE PURPOSE OF TH |
| 2025-03-26 | P00117 | Funding only | $152.90M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO INCREASE BY $152,902,612.00 FROM $2,815,683,774.52 TO $ $2,968,586,386.52 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE |
| 2025-03-14 | P00116 | Funding only | $0 | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) INCREASE OBLIGATED FUNDS BY $59,529,893.03 MODIFY SECTION J: ATTACHMENT 3 AND BASELINE LIST OF APPLICABLE DIRECTIVES (LIST B) |
| 2025-01-24 | P00115 | Funding only | $368.64M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT AND MODIFY TWO (2) CLAUSES WITHIN SECTION H (1 AND 64) 89233018CNR000004 WITH FLUOR BY $368,638, |
| 2024-12-27 | P00114 | Funding only | $22.18M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT 89233018CNR000004 WITH FLUOR BY $22,183,207.02 FROM $2,365,332,508.47 TO $2,387,515,715.49 FOR T |
| 2024-12-23 | P00113 | Funding only | -$100.0K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO DECREASE THE CONTRACT 89233018CNR000004 WITH FLUOR BY $100,000.00 FROM $2,365,432,508.47 TO $2,365,332,508.47 FOR THE |
| 2024-11-22 | P00112 | Funding only | $1.14M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT 89233018CNR000004 WITH FLUOR BY $1,137,200.00 FROM $2,364,295,308.47 TO $2,365,432,508.47 FOR TH |
| 2024-10-30 | P00111 | Administrative change | $0 | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - REVISE TEXT TO BLOCK 14 FROM EXECUTED MODIFICATION 110. MODIFICATION 111 IS BEING ISSUED TO REVISE AN ERROR FROM MODIFICATION 110 IN BLOCK 14 - "2. REFER TO SECTION B, CLAUSE B. |
| 2024-10-30 | P00110 | Funding only | $361.80M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS, YEAR 7 FEE, LIST B ATTACHMENT, AND FY25 SMALL BUSINESS GOALS. THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT 89233018CNR000004 WITH FLUOR BY $ |
| 2024-09-30 | P00109 | Funding only | $1.11M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT 89233018CNR000004 WITH FLUOR BY $1,105,441.00 FROM $1,949,587,180.81 TO $1,950,692,621.81 FOR TH |
| 2024-08-28 | P00108 | Funding only | $1.00M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT 89233018CNR000004 WITH FLUOR BY $1,000,000.00 FROM $1,948,587,180.81 TO $1,949,587,180.81 FOR TH |
| 2024-08-27 | P00107 | Funding only | -$1.00M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO DECREASE CLIN 3 BY $1,000,000 FROM $1,949,587,180.81 TO $1,948,587,180.81 FOR THE OPTION TERM. THE TOTAL AMOUNT OF THE |
| 2024-08-06 | P00106 | Funding only | -$3.18M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO DECREASE CLIN 3 BY $3,176,000.00 FROM $1,952,763,180.81 TO $ $1,949,587,180.81 FOR THE OPTION TERM. THE TOTAL AMOUNT O |
| 2024-07-19 | P00105 | Funding only | $3.47M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CLIN 3 BY $3,471,846.99 FROM $1,949,291,333.82 TO $1,952,763,180.81 FOR THE OPTION TERM. THE TOTAL AMOUNT OF |
| 2024-07-19 | P00104 | Funding only | -$1.19M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS THE PURPOSE OF THIS MODIFICATION IS TO DECREASE CLIN 3 BY $1,191,060.00 FROM $1,950,482,393.82 TO $1,949,291,333.82 FOR THE OPTION TERM. THE TOTAL AMOUNT OF |
| 2024-06-28 | P00103 | Funding only | $51.08M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS |
| 2024-06-26 | P00102 | Funding only | -$7.68M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS |
| 2024-06-04 | P00101 | Funding only | -$1.85M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS |
| 2024-04-25 | P00100 | Funding only | $747.17M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE & INCREASE OBLIGATED FUNDS |
| 2024-03-28 | P00099 | Funding only | $192.83M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS |
| 2024-03-28 | P00098 | Funding only | -$105.8K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS |
| 2024-03-07 | P00097 | Funding only | $1.55M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS |
| 2024-02-13 | P00096 | Funding only | $188.00M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS |
| 2024-02-12 | P00095 | Funding only | -$38.8K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS |
| 2023-12-19 | P00094 | Funding only | $4.46M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS |
| 2023-12-15 | P00093 | Funding only | -$4.52M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS |
| 2023-11-30 | P00092 | Funding only | $316.48M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS |
| 2023-11-14 | P00091 | Funding only | $9.07M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS |
| 2023-11-09 | P00090 | Funding only | $60.0K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS |
| 2023-10-26 | P00089 | Supplemental agreement (work within scope) | $359.29M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS AND SMALL BUSINESS INCLUSION |
| 2023-10-24 | P00088 | Supplemental agreement (work within scope) | -$5.00M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS AND NEGO. FIXED FEE |
| 2023-09-22 | P00087 | Funding only | $650.0K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS. |
| 2023-09-21 | P00086 | Funding only | -$182.9K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS. |
| 2023-09-08 | P00085 | Option exercised | $0 | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - EXERCISING OPTION CLIN 0003. |
| 2023-08-31 | P00084 | Funding only | $7.25M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS. |
| 2023-08-31 | P00083 | Funding only | -$13.55M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS. |
| 2023-06-30 | P00082 | Funding only | $713.7K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE AND INCREASE OBLIGATED FUNDS. |
| 2023-05-24 | P00081 | Funding only | $189.0K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS. |
| 2023-04-28 | P00080 | Funding only | $55.20M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS. |
| 2023-04-27 | P00079 | Funding only | -$50.00M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS. |
| 2023-02-22 | P00078 | Funding only | $5.49M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE OBLIGATED FUNDS. |
| 2023-01-31 | P00077 | Funding only | $1.54B | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - OBLIGATION OF FUNDS. |
| 2022-12-30 | P00076 | Funding only | $77.2K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - OBLIGATION OF FUNDS. |
| 2022-12-30 | P00075 | Funding only | -$10.00M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DEOBLIGATION OF FUNDS. |
| 2022-12-19 | P00074 | Funding only | $0 | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DEOBLIGATION OF FUNDS. |
| 2022-12-14 | P00073 | Funding only | $100.0K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE IN OBLIGATION |
| 2022-11-30 | P00072 | Funding only | $94.90M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE IN OBLIGATION |
| 2022-10-31 | P00071 | Funding only | $375.13M | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - INCREASE IN OBLIGATION |
| 2022-10-27 | P00070 | Supplemental agreement (work within scope) | -$186.6K | MANAGEMENT AND OPERATION OF THE NAVAL NUCLEAR LABORATORY (NNL) - DECREASE OBLIGATED FUNDS, NEGO. FIXED FEE AND SMALL BUSINESS INCLUSION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-21). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗