PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS)
Up for re-bid: ends 2027-10-02. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
28 actions since 2022-12-02. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-29 | P00030 | Option exercised | $2.06M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE ALL OPTION YEAR 4 CLINS, PROVIDE THE ASSOCIATED FUNDING AND INCREASE THE CEILING FOR CLIN 00408. |
| 2026-09-22 | P00029 | Administrative change | $0 | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - THE PURPOSE OF THIS UNILATERAL MODIFICATION (P00029) IS TO IMPLEMENT A MANDATORY CLAUSE DOE-H-2087. |
| 2026-06-18 | P00028 | Funding only | $550.0K | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - THE PURPOSE OF THIS UNILATERAL MODIFICATION (P00028) IS TO PROVIDE INCREMENTAL FUNDING IN THE AMOUNT OF $550,000.00. |
| 2026-04-08 | P00027 | Funding only | $2.29M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - THE PURPOSE OF THIS UNILATERAL MODIFICATION (P00027) IS TO PROVIDE INCREMENTAL FUNDING IN THE AMOUNT OF $2,285,231.30. |
| 2025-12-22 | P00026 | Funding only | $1.14M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - THE PURPOSE OF THIS UNILATERAL MODIFICATION (P00026) IS TO PROVIDE INCREMENTAL FUNDING IN THE AMOUNT OF $1,142,629.65. |
| 2025-11-18 | P00025 | Supplemental agreement (work within scope) | $0 | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - THE PURPOSE OF THIS BILATERAL MODIFICATION (P00025) IS TO MOVE FUNDING BETWEEN CLINS AS FOLLOW. THIS IS A ZERO DOLLAR MODIFICATION. |
| 2025-11-04 | P00024 | Funding only | -$441.0K | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - THE PURPOSE OF THIS BILATERAL MODIFICATION (P00024) IS TO DE-OBLIGATE FUNDS IN THE AMOUNT OF $441,016.40. |
| 2025-09-29 | P00023 | Funding only | $688.0K | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - THE PURPOSE OF UNILATERAL MODIFICATION P00023 IS TO ADD INCREMENTAL FUNDING IN THE AMOUNT OF $688,021.88. |
| 2025-09-24 | P00022 | Option exercised | $1.43M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - UNILATERAL MODIFICATION P00022 IS TO EXERCISE OPTION PERIOD 3 AND ADD INCREMENTAL FUNDING IN THE AMOUNT OF $1,428,948.20. |
| 2025-07-07 | P00021 | Funding only | $1.59M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - UPDATE CLAUSE DOE-H-2070; REVISE KEY PERSONNEL |
| 2025-05-06 | P00020 | Administrative change | $0 | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - UPDATE CLAUSE DOE-H-2070; REVISE KEY PERSONNEL |
| 2025-03-13 | P00019 | Funding only | $1.53M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - UPDATE CLAUSE DOE-H-2070; REVISE KEY PERSONNEL |
| 2025-03-06 | P00018 | Administrative change | $0 | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - UPDATE CLAUSE DOE-H-2070; REVISE KEY PERSONNEL |
| 2025-02-21 | P00017 | Administrative change | $0 | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - REMOVE CLAUSE DOE-H-2041 |
| 2024-12-20 | P00016 | Funding only | $1.53M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - INCREMENTAL FUNDING |
| 2024-10-02 | P00015 | Administrative change | $0 | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - INCORPORATE CHANGES IN KEY PERSONNEL |
| 2024-09-23 | P00014 | Option exercised | $1.66M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - EXERCISE OPTION YR 2 |
| 2024-08-12 | P00013 | Administrative change | $0 | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - CHANGE IN KEY PERSONNEL |
| 2024-07-17 | P00012 | Supplemental agreement (work within scope) | $205.8K | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) - ADD FUNDING FOR TA-3 |
| 2024-02-08 | P00011 | Funding only | $0 | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) |
| 2024-01-22 | P00010 | Supplemental agreement (work within scope) | $40.2K | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) |
| 2024-01-04 | P00009 | Funding only | $3.54M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) |
| 2023-12-21 | P00008 | Funding only | $200.0K | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) |
| 2023-09-25 | P00007 | Option exercised | $1.18M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) |
| 2023-06-13 | P00006 | Funding only | $642.6K | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) |
| 2023-05-09 | P00005 | Supplemental agreement (work within scope) | $146.3K | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) |
| 2023-03-06 | P00004 | Funding only | $428.4K | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) |
| 2022-12-02 | P00003 | Funding only | $2.78M | PORTFOLIO ANALYSIS AND MANAGEMENT SYSTEM (PAMS) |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗