89303122FEM400243↗
Four Rivers Nuclear Partnership LLC received this contract from Em-Portsmouth/Paducah Project Ofc, Department of Energy: -$2.70M obligated so far for other environmental services. Its period of performance ended 2024-09-30.
Key facts · data as of Oct 23, 2026
- Recipient
- Four Rivers Nuclear Partnership LLC
- Awarding agency
- Department of Energy
- Contracting office
- Em-Portsmouth/Paducah Project Ofc (893031)
- Obligated to date
- -$2.70M
- Potential value
- $1.75M
- Ends
- 2024-09-30
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 89303122FEM400243, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_89303122FEM400243_8900_DEEM0004895_8900
Four Rivers Nuclear Partnership LLC: all federal awards · Department of Energy: spending · Em-Portsmouth/Paducah Project Ofc: what it buys
PURPOSE OF TASK ORDER PARTIAL DISMANTLEMENT OF C-535-2 SWITCHYARD; PARTIAL CHARACTERIZATION OF C-531-2 SWITCHYARD; PARTIAL CHARACTERIZATION OF C-533-2 SWITCHYARD; PLUS OTHER OPTIONAL ITEMS.
What it is
- Product or service
- Other Environmental Services (PSC F999)
- Industry
- Remediation Services (NAICS 562910)
- Contracting office
- Em-Portsmouth/Paducah Project Ofc (893031)
- Competition
- Full and open competition
- Pricing
- Cost plus fixed fee
- How it was bought
- Single-award IDIQ · under DEEM0004895
- Solicitation
- DE-SOL-0008746
- Where the work is
- Mccracken, KY · district KY-01
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
2 actions since 2023-09-29. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2024-03-04 | P00002 | Funding only | -$6.12M | PURPOSE OF THIS MODIFICATION IS TO TO DE OBLIGATE EXCESS FUNDS |
| 2023-09-29 | P00001 | Supplemental agreement (work within scope) | $3.43M | PURPOSE OF THIS MODIFICATION IS TO ADD ADDITIONAL FUNDING TO CLIN 01005 TO DISMANTLE AND REMOVE ADDITIONAL TRANSMISSION TOWERS FROM THE PADUCAH SITE. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗