89303323FEM400390↗

North Wind Portage, Inc. received this contract from Em-Environmental Management Con Bus CTR, Department of Energy: $201.04M obligated so far for environmental systems protection- environmental remediation. It runs to 2027-04-30, or to 2027-11-05 if every option is exercised.

Key facts · data as of Oct 22, 2026

Recipient
North Wind Portage, Inc.
Awarding agency
Department of Energy
Contracting office
Em-Environmental Management Con Bus CTR (893033)
Obligated to date
$201.04M
Potential value
$227.24M
Ends
2027-04-30

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.

Cite this page: SpendQuery, Award 89303323FEM400390, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_89303323FEM400390_8900_89303322DEM000073_8900

SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.

Delivery Order · Department of Energy · to North Wind Portage, Inc. (UEI UVVNPHJPMNH7) · data as of 2026-10-22

Obligated to date$201.04M28 actions
Current value$227.24Mwith options exercised
Period2023-10-01 → 2027-04-30up to 2027-11-05 with options

Up for re-bid: ends 2027-04-30. Recompete brief → · HANFORD 222-S LABORATORY – FINAL REQUEST FOR PROPOSAL ↗

What it is

Product or service
Environmental Systems Protection- Environmental Remediation (PSC F108)
Industry
Remediation Services (NAICS 562910)
Contracting office
Em-Environmental Management Con Bus CTR (893033)
Competition
Full and open after exclusion of sources
Pricing
Firm fixed price
How it was bought
Single-award IDIQ · under 89303322DEM000073
Where the work is
Grand, UT · district UT-03

Obligations by fiscal year

FY2023$10.13M
FY2024$63.87M
FY2025$67.89M
FY2026$59.15M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

28 actions since 2023-09-29. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-09-29P00027Supplemental agreement (work within scope)$5.38MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00027 EXERCISES AN OPTION.
2026-09-23P00026Terminated for convenience$0SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00026 TERMINATES SOME WORK AND IS A SUPPLEMENTAL AGREEMENT.
2026-07-24P00025Supplemental agreement (work within scope)$5.52MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00025 ADDS MULTIPLE LINE ITEMS.
2026-07-15P00024Funding only$182.8KSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2026-05-06P00023Supplemental agreement (work within scope)$18.85MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00023 IS A SUPPLEMENTAL AGREEMENT TO A DELIVERABLE.
2026-02-05P00022Supplemental agreement (work within scope)$6.95MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00022 ADDS MULTIPLE LINE ITEMS.
2025-12-03P00021Funding only$17.47MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2025-10-23P00020Administrative change$0SCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00020 MAKES AN ADMINISTRATIVE CHANGE TO APPROPRIATION DATA.
2025-10-17P00019Funding only$4.80MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2025-09-23P00018Option exercised$1.22MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00018 EXERCISES AN OPTION WITH FUNDS AND ADMIN CHANGES.
2025-07-22P00017Funding only$21.09MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2025-07-02P00016Supplemental agreement (work within scope)$602.6KSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00016 ADDS MORE CELL ROCK COVER AND WORK.
2025-06-23P00015Funding only$5.69MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2025-05-16P00014Supplemental agreement (work within scope)$5.20MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00014 IS A SUPPLEMENTAL AGREEMENT.
2025-04-17P00013Funding only$4.86MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2025-03-07P00012Supplemental agreement (work within scope)$4.43MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00012 ADDS A GROUNDWATER COMPLIANCE ACTION PLAN LINE ITEM.
2025-01-07P00011Funding only$12.55MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2024-12-20P00010Supplemental agreement (work within scope)$2.35MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00010 ADDS A HAUL ROAD DESIGN/BUILD LINE ITEM.
2024-10-15P00009Funding only$9.91MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2024-09-25P00008Funding only$986.2KSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2024-09-03P00007Supplemental agreement (work within scope)$9.6KSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00007 ADDS A WETLANDS RECONNAISSANCE LINE ITEM.
2024-08-23P00006Option exercised$7.00MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00006 EXERCISES AN OPTION AND FUNDS THE TASK ORDER.
2024-06-26P00005Supplemental agreement (work within scope)$10.40MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00005 ADDS SECURITY REQUIREMENTS AND INCREMENTAL FUNDING.
2024-04-19P00004Supplemental agreement (work within scope)$8.38MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. P00004 ADDS MORE CELL ROCK COVER.
2024-02-22P00003Funding only$12.45MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2023-12-29P00002Funding only$15.66MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.
2023-11-14P00001Administrative change$8.98MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS. MOD P00001 FUNDS, SPECIFIES, AND CORRECTS THE TASK ORDER.
2023-09-290$10.13MSCOPE OF TASK ORDER 89303323FEM400390 INCLUDES COMPLETION OF THE MILL TAILINGS PILE REMEDIATION AT A RATE OF SPEED REFLECTING ESTABLISHED PRODUCTION CAPACITY UNDER SAFE WORKING CONDITIONS.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗