East Coast Powerline LLC received this contract from Southwestern Power Administration, Department of Energy: $5.00M obligated so far for construction of other industrial buildings. It runs to 2027-10-14.
Key facts · data as of Oct 23, 2026
- Recipient
- East Coast Powerline LLC
- Awarding agency
- Department of Energy
- Contracting office
- Southwestern Power Administration (895036)
- Obligated to date
- $5.00M
- Potential value
- $12.93M
- Ends
- 2027-10-14
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award 89503626CSW000088, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_89503626CSW000088_8900_-NONE-_-NONE-
East Coast Powerline LLC: all federal awards · Department of Energy: spending · Southwestern Power Administration: what it buys · The follow-on: recompete brief
REBUILD OF THE LIBERTY TO VAN BUREN PORTION OF SOUTHWESTERNS VAN BUREN TO WELEETKA 161KV TRANSMISSION LINE
Up for re-bid: ends 2027-10-14. Recompete brief →
What it is
- Product or service
- Construction of Other Industrial Buildings (PSC Y1EZ)
- Industry
- Power and Communication Line and Related Structures Construction (NAICS 237130)
- Contracting office
- Southwestern Power Administration (895036)
- Competition
- Full and open after exclusion of sources · 6 offers received
- Set-aside
- Small business
- Pricing
- Firm fixed price
- How it was bought
- Standalone contract
- Solicitation
- 89503625RSW000052
- Where the work is
- Crawford, AR · district AR-03
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
1 action since 2026-01-30. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-01-30 | 0 | $5.00M | REBUILD OF THE LIBERTY TO VAN BUREN PORTION OF SOUTHWESTERNS VAN BUREN TO WELEETKA 161KV TRANSMISSION LINE |