Putting the award page together from the records…
Putting the award page together from the records…
Westinghouse Government Services LLC received this contract from Nnsa Non-Mo Cntrctng Ops Div, Department of Energy: $77.93M obligated so far for nuclear reactors. It runs to 2034-09-30, or to 2044-09-30 if every option is exercised.
Key facts · data as of Oct 22, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.
Cite this page: SpendQuery, Award DEAC0200DP00229, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_DEAC0200DP00229_8900_-NONE-_-NONE-
Westinghouse Government Services LLC: all federal awards · Department of Energy: spending · Nnsa Non-Mo Cntrctng Ops Div: what it buys
TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
19 actions since 2023-03-27. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-23 | 103 | Administrative change | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2026-03-23 | 102 | Administrative change | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2026-02-24 | 101 | Administrative change | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2025-12-18 | 100 | Funding only | $25.23M | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2025-12-11 | 99 | Supplemental agreement (work within scope) | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2025-06-09 | 98 | Administrative change | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2025-05-07 | 97 | Administrative change | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2025-04-28 | 96 | Administrative change | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2025-03-13 | 95 | Supplemental agreement (work within scope) | $561.8K | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2025-02-27 | 94 | Funding only | $24.40M | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2025-02-14 | 93 | Supplemental agreement (work within scope) | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2024-09-19 | 92 | Option exercised | $4.22M | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION (PHASE V OPTION) |
| 2024-06-06 | 91 | Funding only | $0 | THE CONTRACT IS REVISED TO PROVIDE FOR REALIGNMENT DUE TO RECASTING OF FUNDS FROM FY24. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-05-21 | 90 | Funding only | $0 | THE CONTRACT IS REVISED TO PROVIDE FOR REALIGNMENT DUE TO RECASTING OF FUNDS FROM FY22 AND FY23 ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-04-11 | 89 | Supplemental agreement (work within scope) | $0 | THE CONTRACT IS REVISED TO PROVIDE FOR A FUNDING REALIGNMENT DUE TO THE INACTIVITY REALIZED UNDER CLIN 0005 ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2024-03-01 | 88 | Funding only | $7.94M | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION |
| 2023-09-26 | 87 | Administrative change | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION |
| 2023-05-15 | 86 | Supplemental agreement (work within scope) | $0 | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION |
| 2023-03-27 | 85 | Funding only | $15.57M | TRITIUM PRODUCING BURNABLE ABSORBER ROD (TPBAR) FABRICATION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗