DEAC0500OR22725↗
Ut-Battelle LLC received this contract from SC Oak Ridge Office, Department of Energy: $10.93B obligated so far for oper of government r&d goco facilities. It runs to 2030-03-31.
Key facts · data as of Oct 21, 2026
- Recipient
- Ut-Battelle LLC
- Awarding agency
- Department of Energy
- Contracting office
- SC Oak Ridge Office (892431)
- Obligated to date
- $10.93B
- Potential value
- $43.82B
- Ends
- 2030-03-31
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 21, 2026.
Cite this page: SpendQuery, Award DEAC0500OR22725, data as of Oct 21, 2026, https://spendquery.com/award?id=CONT_AWD_DEAC0500OR22725_8900_-NONE-_-NONE-
Ut-Battelle LLC: all federal awards · Department of Energy: spending · SC Oak Ridge Office: what it buys
MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY
What it is
- Product or service
- Oper of Government R&D Goco Facilities (PSC M181)
- Industry
- Facilities Support Services (NAICS 561210)
- Contracting office
- SC Oak Ridge Office (892431)
- Competition
- Full and open competition · 2 offers received
- Pricing
- Cost plus award fee
- How it was bought
- Standalone contract
- Where the work is
- Anderson, TN · district TN-03
- Funding law
- Other emergency or disaster supplementals
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
138 actions since 2022-10-28. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-30 | 1411 | Funding only | $81.81M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-09-30 | 1410 | Funding only | $150.54M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-08-27 | 1409 | Funding only | $71.73M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-08-27 | 1408 | Funding only | $107.30M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-08-17 | 1407 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-07-31 | 1406 | Funding only | $31.72M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-07-31 | 1405 | Funding only | $129.37M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-07-21 | 1404 | Administrative change | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-06-26 | 1403 | Funding only | $262.32M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-06-25 | 1402 | Funding only | $279.85M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-05-28 | 1401 | Funding only | $22.45M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-05-28 | 1400 | Funding only | $133.45M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-05-06 | 1399 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-04-29 | 1398 | Funding only | $80.52M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-04-29 | 1397 | Funding only | $506.67M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-03-27 | 1396 | Funding only | $34.77M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-03-27 | 1395 | Funding only | $100.01M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-02-26 | 1394 | Funding only | $23.62M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-02-26 | 1393 | Funding only | $167.68M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-02-06 | 1392 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-01-29 | 1391 | Funding only | $18.21M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2026-01-29 | 1390 | Funding only | $67.40M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-12-23 | 1389 | Funding only | $105.14M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-12-23 | 1388 | Funding only | $66.64M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-12-16 | 1387 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-11-25 | 1386 | Funding only | $7.25M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-11-24 | 1385 | Funding only | $495.0K | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-11-24 | 1384 | Funding only | $509.16M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-11-14 | 1383 | Funding only | $2.51M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-11-14 | 1382 | Funding only | $17.78M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-10-31 | 1381 | Funding only | $334.7K | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-10-31 | 1380 | Funding only | $12.78M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-09-30 | 1379 | Funding only | $2.30M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-09-30 | 1378 | Funding only | $133.37M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-09-30 | 1377 | Funding only | $191.94M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-08-29 | 1376 | Funding only | $20.60M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-08-29 | 1375 | Funding only | $180.98M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-07-31 | 1374 | Funding only | $24.83M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-07-30 | 1373 | Funding only | $117.40M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-07-10 | 1370 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-06-27 | 1372 | Funding only | $1.04M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2025-06-27 | 1371 | Funding only | $323.90M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2025-06-18 | 1362 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2025-05-28 | 1369 | Funding only | $24.05M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-05-28 | 1368 | Funding only | $203.37M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-05-13 | 1365 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-04-30 | 1367 | Funding only | $39.15M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-04-30 | 1366 | Funding only | $165.29M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-03-28 | 1364 | Funding only | $1.60M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-03-28 | 1363 | Funding only | $6.08M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2025-03-14 | 1361 | Funding only | $10.91M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT |
| 2025-03-13 | 1360 | Funding only | $55.48M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2025-03-07 | 1359 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY CONTRACT EXTENSION. |
| 2025-03-05 | 1351 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2025-02-27 | 1358 | Funding only | $40.46M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE FUNDS. |
| 2025-02-27 | 1357 | Funding only | $29.63M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE FUNDS. |
| 2025-02-07 | 1356 | Administrative change | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2025-02-07 | 1340 | Administrative change | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $7,858,834.54 IN NASA FUNDS FOR JULY 2024. |
| 2025-01-31 | 1355 | Funding only | $16.84M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2025-01-31 | 1354 | Funding only | $437.75M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-12-20 | 1353 | Funding only | $81.10M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-12-20 | 1352 | Funding only | $116.75M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-12-05 | 1346 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-11-22 | 1350 | Funding only | $13.66M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-11-22 | 1349 | Funding only | $77.75M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-10-30 | 1348 | Funding only | $2.21M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-10-30 | 1347 | Funding only | $361.31M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-09-26 | 1345 | Funding only | $106.74M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-09-26 | 1344 | Funding only | $113.07M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-09-16 | 1334 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TO REPLACE CHANGE NOTICE (RCN) OR 96 WITH RCN OR 97 DATED MAY 29,2024, IN SECTION J, APPENDIX E. |
| 2024-09-12 | 1343 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-09-10 | 1339 | Administrative change | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY |
| 2024-08-30 | 1342 | Funding only | $57.64M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $57,636,916.41 IN DEPARTMENT OF DEFENSE FUNDS FOR AUGUST 2024. |
| 2024-08-30 | 1341 | Funding only | $119.22M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $120,925,369.05 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $1,701,471.41 CUMULATIVE NAF = $1,150,371,462.52 |
| 2024-07-31 | 1338 | Funding only | $7.86M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $7,858,834.54 IN NASA FUNDS FOR JULY 2024. |
| 2024-07-30 | 1337 | Funding only | $196.11M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $198,456,100.69 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $2,345,745.20 CUMULATIVE NAF = $1,148,669,991.11 |
| 2024-06-27 | 1336 | Funding only | $10.06M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $10,064,475.52 NASA FUNDS FOR JUNE 2024. |
| 2024-06-26 | 1335 | Funding only | $265.68M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $265,679,247.32 IN DOE AND UKRAINE FUNDS FOR JUNE 2024. |
| 2024-05-30 | 1333 | Funding only | $26.81M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $26,813,341.46 IN SPP/VA MAY 2024. |
| 2024-05-30 | 1332 | Funding only | $226.95M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $227,625,483.11 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $674,944.66 CUMULATIVE NAF = $1,108,113,843.38 |
| 2024-04-30 | 1331 | Funding only | $22.68M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $25,437,315.24. NON-APPROPRIATED FUNDING (NAF): $2,753,819.60 IN NAF AND 22,683,495.64 IN STRATEGIC PARTNERSHIP PROJECTS |
| 2024-04-30 | 1330 | Funding only | $244.01M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $244,014,467.65 IN DOE FUNDS. |
| 2024-04-12 | 1326 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TO REPLACE CHANGE NOTICE (RCN) OR 95 WITH RCN OR 96 DATED FEBRUARY 29,2024, IN SECTION J, APPENDIX E. |
| 2024-04-08 | 1329 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY UPDATE CONTRACT SECTIONS H & J. |
| 2024-03-28 | 1328 | Funding only | $19.85M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $19,849,331.79 IN SPP/NASA MAR 2024. |
| 2024-03-28 | 1327 | Funding only | $154.29M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $155,433,372.23 IN DOE FUNDS. CURRENT NAF = 1,148,296.43 CUMULATIVE NAF = $1,082,001,583.48 |
| 2024-02-29 | 1325 | Funding only | $11.67M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $11,665,453.95 IN SPP/NASA FEB 2024. |
| 2024-02-28 | 1324 | Funding only | $228.79M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $231,870,745.18 IN DOE FUNDS. CURRENT NAF = $3,085,400.71 CUMULATIVE NAF = $1,080,853,287.05 |
| 2024-01-29 | 1323 | Funding only | $14.11M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $14,105,819.68 IN SPP/AIR FORCE JAN 2024. |
| 2024-01-29 | 1322 | Funding only | $35.26M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $37,154,515.28 IN DOE FUNDS. CURRENT NAF = $1,482,000.00 CUMULATIVE NAF = $1,077,767,886.34 |
| 2024-01-19 | 1321 | Funding only | $57.93M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $57,931,180.31 IN DOE FUNDS. CURRENT NAF = $0.00 CUMULATIVE NAF = $1,075,876,864.15 |
| 2023-12-26 | 1320 | Funding only | $10.51M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $10,505,105.61 IN SPP/NASA DEC 2023. |
| 2023-12-26 | 1319 | Funding only | $277.34M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $277,946,265.36 IN DOE FUNDS AND NON APPROPRIATED FUNDS. CURRENT NAF = $604,865.60 CUMULATIVE NAF = $1,075,876,864.15 |
| 2023-12-26 | 1318 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TO REPLACE CHANGE NOTICE (RCN) OR 94 WITH RCN OR 95 DATED NOVEMBER 30, 2023 , IN SECTION J, APPENDIX E. |
| 2023-11-30 | 1317 | Funding only | $34.64M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $34,642,307.51 IN DOE FUNDS. |
| 2023-11-17 | 1316 | Funding only | $23.93M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $23,926,003.89 IN SPP/DOD NOV 2023. |
| 2023-11-17 | 1315 | Funding only | $58.07M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $59,576,208.83 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = 1,508,993.30 CUMULATIVE NAF = $1,075,271,998.55 |
| 2023-10-30 | 1314 | Funding only | $628.2K | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $628,194.11 IN SPP/AIR FORCE OCT 2023. |
| 2023-10-30 | 1313 | Funding only | $222.45M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $225,582,556.21 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $3,137,419.40 CUMULATIVE NAF = $1,073,763,005.25 |
| 2023-09-29 | 1312 | Funding only | $36.53M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $36,528,971.72 IN SPP/STATE SEPT 2023. |
| 2023-09-29 | 1311 | Funding only | $169.55M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $170,922,037.28 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $1,373,418.26 CUMULATIVE NAF = $1,070,625,585.85 |
| 2023-09-28 | 1310 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TO REPLACE CHANGE NOTICE (RCN) OR 93 WITH RCN OR 94 DATED AUGUST 31, 2023 , IN SECTION J, APPENDIX E. ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED. |
| 2023-08-31 | 1309 | Funding only | $57.75M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $57,751,440.94 IN SPP/COMMERCE AUG 2023. |
| 2023-08-31 | 1308 | Funding only | $330.46M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $181,296,450.60 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $(149,167,944.39) CUMULATIVE NAF = $1,069,252,167.59 |
| 2023-07-31 | 1307 | Funding only | $21.80M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $21,803,878.46 IN SPP/VA JUL 2023. |
| 2023-07-28 | 1306 | Funding only | $143.89M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $151,713,866.61 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF $7,824,194.93 CUMULATIVE NAF $1,218,420,111.98. |
| 2023-06-30 | 1305 | Administrative change | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY - CORRECTING TYPOGRAPHICAL ERROR ON 1304. |
| 2023-06-30 | 1304 | Funding only | $11.04M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TAS :: 97 0400 :: TAS SPP/DOD PREDOMINANT FUNDING JUNE 2023, OBLIGATING NET $11,040,825.05 WHICH INCLUDES $436,893.20 IN COVID FUNDS FROM TAS 75 0943. |
| 2023-06-30 | 1303 | Funding only | $38.0K | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $41,857,148.93 IN DOE UKRAINE AND NON APPROPRIATED FUNDS. CURRENT NAF = $41,819,148.93 CUMULATIVE NAF = $1,210,595,917.05. |
| 2023-06-30 | 1302 | Funding only | $38.07M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $38,066,445.20 IN DOE FUNDS. CURRENT NAF = $0 CUMULATIVE NAF = $1,168,776,768.12. |
| 2023-05-31 | 1301 | Funding only | $864.2K | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $864,153.23 IN DOE FUNDS. CURRENT NAF = $0.00 CUMULATIVE NAF = $1,168,776,768.12. |
| 2023-05-30 | 1300 | Funding only | $36.27M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TAS :: 36 0167 :: TAS SPP/VA PREDOMINANT FUNDING MAY 2023 |
| 2023-05-30 | 1299 | Funding only | -$2.17M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $35,619,955.92 IN DEOBLIGATED DOE UKRAINE AND NON APPROPRIATED FUNDS. CURRENT NAF = $35,619,955.92 CUMULATIVE NAF = $1,168,776,768.12. |
| 2023-05-30 | 1298 | Funding only | $100.20M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $100,204,571.49 IN DOE FUNDS. CURRENT NAF = $0.00 CUMULATIVE NAF = $1,133,156,812.20. |
| 2023-05-23 | 1294 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY // TO REPLACE REQUIREMENT CHANGE NOTICE (RCN) OR-91 WITH RCN OR-92 DATED MARCH 26, 2023 |
| 2023-04-28 | 1297 | Funding only | -$74 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $12,306,301.73 IN DEOBLIGATED DOE COVID AND NON APPROPRIATED FUNDS. CURRENT NAF = $12,306,375.80 CUMULATIVE NAF = $1,133,156,812.20. |
| 2023-04-28 | 1296 | Funding only | $12.19M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TAS :: 97 0400 :: TAS SPP/DOD PREDOMINANT FUNDING APR 2023 |
| 2023-04-28 | 1295 | Funding only | $179.56M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $179,560,409.05 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $12,306,375.80 CUMULATIVE NAF = $1,133,156,812.20. |
| 2023-03-31 | 1293 | Funding only | $19.90M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TAS :: 97 0440 :: TAS SPP/DOD PREDOMINANT FUNDING MAR 2023 |
| 2023-03-31 | 1292 | Funding only | $440.76M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $453,538,262.51 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $12,780,417.50 CUMULATIVE NAF = $1,120,850,436.40. |
| 2023-02-28 | 1291 | Funding only | $4.54M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $4,540,000.00 IN DOE FUNDS. |
| 2023-02-28 | 1286 | Administrative change | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY // TO INCORPRATE TWO NEW H-CLAUSES, RCN-91 AND FY 2023 PEMP. |
| 2023-02-27 | 1290 | Funding only | $18.55M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TAS :: 57 3400 :: TAS SPP/USAF PREDOMINANT FUNDING FEB 2023 |
| 2023-02-27 | 1289 | Funding only | $342.26M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $33,946,548,149.24 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $8,036,950.95 CUMULATIVE NAF = $1,108,070,018.90. |
| 2023-01-31 | 1288 | Funding only | $12.79M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $12,793,851.08 IN SPP/DOD JAN 2023. |
| 2023-01-31 | 1287 | Funding only | $264.86M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $281,759,871.26IN DOE FUNDS. CURRENT NAF = $16,900,723.39 CUMULATIVE NAF = $1,100,033,067.95 |
| 2023-01-13 | 1285 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY - TO INCORPORATE POLICY FLASH 2022-35 MODEL EMPLOYEE COMPENSATION: PAY AND BENEFITS CORPORATE H CLAUSE |
| 2022-12-27 | 1284 | Funding only | $114.60M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $114,600,000.00 IN DOE FUNDS. CURRENT NAF = $0.00 CUMULATIVE NAF = $1,083,132,344.56 |
| 2022-12-23 | 1283 | Funding only | $4.61M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $4,356,831.62 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = -$249,044.00 CUMULATIVE NAF = $1,083,132,344.56 |
| 2022-12-23 | 1282 | Funding only | $9.48M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TAS :: 75 0600 :: TAS SPP/HHS DEC 2022 |
| 2022-12-22 | 1281 | Funding only | $2.60M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $2,596,840.78 IN DOE FUNDS. CURRENT NAF = $0.00 CUMULATIVE NAF = $ 1,083,381,388.56. |
| 2022-12-22 | 1280 | Funding only | -$10.5K | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $5,077,757.19 IN DEOBLIGATED COVID AND NON APPROPRIATED FUNDS. CURRENT NAF = $5,088,263.04 CUMULATIVE NAF = $ 1,083,381,388.56. |
| 2022-11-30 | 1279 | Funding only | $9.93M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TAS :: 70 0566 :: TAS SPP/DEPARTMENT OF HOMELAND SECURITY NOV 2022 |
| 2022-11-29 | 1278 | Funding only | $40.19M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $44,315,957.10 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $4,127,413.50 CUMULATIVE NAF = $1,078,293,125.52. |
| 2022-11-08 | 1274 | Supplemental agreement (work within scope) | $0 | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY // TO INCORPORATE RCN NO. OR-90 |
| 2022-10-31 | 1277 | Funding only | $1.45M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY TAS :: 57 3600 :: TAS SPP/AIR FORCE PREDOMINANT FUNDING OCT 2022 |
| 2022-10-31 | 1276 | Funding only | $1.25M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE $1,250,000.00 IN DOE FUNDS. |
| 2022-10-28 | 1275 | Funding only | $289.05M | MANAGEMENT AND OPERATION OF THE OAK RIDGE NATIONAL LABORATORY OBLIGATE NET $308,477,549.80 IN DOE AND NON APPROPRIATED FUNDS. CURRENT NAF = $19,426,571.66 CUMULATIVE NAF = $1,074,165,712.02. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-21). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗