UPDATES SECTIONS I AND J.
Up for re-bid: ends 2027-04-11. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
88 actions since 2022-11-02. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-30 | 628 | Funding only | $55.50M | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION B, SUPPLIES OR SERVICES AND PRICES/COSTS TO OBLIGATE INCREMENTAL FUNDING UNDER PURCHASE REQUISITION NUMBER 26EM001966, IN THE TOTAL AMOUNT OF $55,499,902.37 FOR HIGH-LEVEL WASTE. |
| 2026-09-17 | 627 | Funding only | $507.94M | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION B, SUPPLIES OR SERVICES AND PRICES/COSTS AND OBLIGATE INCREMENTAL FUNDING IN THE AMOUNT OF $507,938,027.16. |
| 2026-08-20 | 626 | Supplemental agreement (work within scope) | $0 | THIS MODIFICATION UPDATES SECTION J, LIST OF ATTACHMENTS, ATTACHMENT J-E, LIST OF APPLICABLE DIRECTIVES, TO ALIGN WITH PROJECT VELOCITY DIRECTION FROM DOE HQ. |
| 2026-07-23 | 625 | Supplemental agreement (work within scope) | $0 | SECTION I HAS BEEN UPDATED TO INCORPORATE FAR 52.222-90, DUE TO EXECUTIVE ORDER (EO) 14398. ADDITIONAL REVISIONS HAVE BEEN MADE TO SECTION C, SECTION G, SECTION H, AND SECTION I. |
| 2026-07-16 | 624 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REDUCE THE TOTAL CONTRACT VALUE BY $516,722.41 (COST OF $482,467.24, FEE OF $34,255.17) AS A RESULT OF DUPLICATION OF MULTI-EMPLOYER PENSION PLAN COSTS. |
| 2026-07-01 | 623 | Funding only | $75.00M | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION B, SUPPLIES OR SERVICES AND PRICES/COSTS, AND OBLIGATE $75,000,000.00 OF APPROPRIATION YEAR 2026 INCREMENTAL FUNDING TO PROVIDE CONTINUITY FOR EHC EFFORTS THROUGH AUGUST 2026. |
| 2026-06-09 | 622 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE SECTION B, SECTION G, SECTION J-E AND REPLACE SECTION J-M IN ITS ENTIRETY. |
| 2026-05-21 | 621 | Funding only | $210.00M | THE PURPOSE OF THIS MODIFICATION IS TO REVISE SECTION B TO OBLIGATE INCREMENTAL FUNDING OF $210,000,000.00 TO PROVIDE CONTINUITY OF OPERATIONS FOR HLW PHASE 1B THRU OCTOBER 2026. |
| 2026-05-18 | 620 | Change order | $0 | THE PURPOSE OF THIS CHANGE ORDER MODIFICATION IS TO DIRECT THE CONTRACTOR WITH A LIMITED NOTICE-TO-PROCEED AND NOT-TO-EXCEED IN THE AMOUNT OF $10,000,000.00 TO BEGIN THE NECESSARY TRANSITION OF DFLAW OPERATIONS TO THE OPERATING CONTRACTOR. |
| 2026-05-07 | 619 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION J, LIST OF ATTACHMENTS, ATTACHMENT E, LIST OF APPLICABLE DIRECTIVES (DEAR 970.5204-2), TO INCORPORATE DOE O 205.1D (CRD). |
| 2026-04-09 | 618 | Funding only | $120.00M | REVISE SECTION B TO OBLIGATE INCREMENTAL FUNDING IN THE AMOUNT OF $120,000,000 TO PROVIDE CONTINUITY OF OPERATIONS FOR DFLAW EXTENDED HOT COMMISSIONING THROUGH JULY 2026. |
| 2026-04-06 | 617 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION J - LIST OF ATTACHMENTS, ATTACHMENT B - HANFORD SITE SERVICES AND INTERFACE MATRIX REQUIREMENTS. |
| 2026-03-23 | 615 | Administrative change | $0 | REVISE CONTRACT SECTION C TO UPDATE STANDARD 1 REMOVING 6 REQUIRED DOCUMENTS LOCATED IN C.6 STANDARD 1 D PROJECT REPORTING, 4 ELECTRONIC DATA AND I UPDATING CLAUSE I.29BA REVISING BNIS FISCAL YEAR 2026 WTP PREMIUM OVERTIME ESTIMATE. |
| 2026-03-12 | 616 | Change order definitized | $35.00M | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE REQUEST FOR EQUITABLE ADJUSTMENT (REA) 2025-004, REV 0, MULTI-EMPLOYER PENSION PLAN CONTRIBUTION FOR PLAN YEAR 2025 PROVIDE INCREMENTAL FUNDING FOR $35,000,000 TO SUPPORT WTP COMMISSIONING. |
| 2026-02-26 | 614 | Change order definitized | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE 3 CHANGE ORDERS; UPDATE CONTRACT SECTIONS B, C, F, AND J TO REFLECT CHANGES; AND EXTEND THE PERIOD OF PERFORMANCE. |
| 2026-02-12 | 613 | Funding only | $135.00M | REVISE SECTION B TO OBLIGATE INCREMENTAL FUNDING OF $135,000,000 TO PROVIDE CONTINUITY OF OPERATIONS FOR BOTH DFLAW EHC THROUGH MARCH 2026, DFHLW PHASE 1A THROUGH MARCH 2026, AND DFHLW PHASE 1B THROUGH JUNE 2026. |
| 2026-02-05 | 612 | Change order definitized | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE REQUEST FOR EQUITABLE ADJUSTMENT 2025002, WASHINGTON STATE INITIATIVE MEASURE NO. 1433 CRAFT SICK LEAVE CALENDAR YEAR 2024 AND MULTI-EMPLOYER PENSION PLAN CONTRIBUTION FOR PLAN YEAR 2024 |
| 2026-01-08 | 611 | Change order | $0 | THIS CHANGE ORDER MODIFICATION PROVIDES FOR A 45-DAY PERIOD OF WORK BEGINNING JANUARY 14, 2026, TO THE END OF FEBRUARY 2026. THE CONTRACTOR IS AUTHORIZED TO INCUR COSTS UP TO A NOT-TO-EXCEED VALUE OF $49,500,000 CONSISTENT WITH CONTRACT TERMS. |
| 2026-01-08 | 610 | Change order | $0 | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE BNI WITH A NOTICE TO PROCEED, NOT TO EXCEED, AND REVISION TO SEC. J, ATTACH. J, ADVANCE UNDERSTANDING ON COSTS, FOR EFFLUENT MANAGEMENT FACILITY EVAPORATOR BOTTOMS SCOPE TRANSMITTED IN LETTER 25-WTP-0063 |
| 2025-12-10 | 609 | Funding only | $52.00M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ADDITIONAL FUNDING TO ENSURE CONTINUITY OF OPERATIONS FOR THE EXTENDED HOT COMMISSIONING WORK SCOPE ON THE DFLAW FACILITY. |
| 2025-12-04 | 608 | Administrative change | $0 | REFORMAT SECTION J, ATTACHMENT E IN ITS ENTIRETY AND UPDATE SECTION J, ATTACHMENT F WITH A KEY PERSONNEL CHANGE. |
| 2025-12-01 | 607 | Administrative change | $0 | REVISE SECTION B TO INCORPORATE $20,000,000.00 DFHLW PHASE 1A DESIGN PROCESS IMPROVEMENT INCENTIVE FEE. REVISE SECTION J, ATTACHMENT R TO REPLACE 2025 PEMP, REV. 0 WITH 2025-26 PEMP REV. 1. |
| 2025-11-13 | 606 | Change order | $0 | DIRECT THE CONTRACTOR TO PROCEED WITH THE NECESSARY WORK SCOPE TO COMPLETE THE DESIGN OF THE HIGH-LEVEL WASTE (HLW) FACILITY, DESIGN COMPLETION PERIOD PHASE 1B IN A DIRECT FEED HLW CONFIGURATION AND EXTEND THE PERIOD OF PERFORMANCE TO 09/30/2026. |
| 2025-11-13 | 604 | Change order | $0 | THE PURPOSE OF THIS CHANGE ORDER IS TO DIRECT THE CONTRACTOR WITH A LIMITED NOTICE TO PROCEED AND NOT TO EXCEED FOR THE NECESSARY EXTENDED HOT COMMISSIONING WORK SCOPE ON THE DFLAW FACILITY. |
| 2025-10-14 | 605 | Administrative change | $0 | THIS IS AN ADMINISTRATIVE MOD TO UPDATE SECTIONS C, G, AND J ATTACHMENT O. THESE REVISIONS ARE AT NO COST TO THE GOVERNMENT. |
| 2025-09-30 | 603 | Funding only | $49.97M | THIS IS TO ADD $49,965,393.50 OF INCREMENTAL FUNDING TO WTP COMMISSIONING AND REVISE SECTION B TO REFLECT THESE CHANGES. |
| 2025-09-29 | 602 | Change order definitized | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE 3 CHANGE ORDERS; UPDATE CONTRACT SECTIONS B, C, F, AND J TO REFLECT CHANGES; AND EXTEND THE PERIOD OF PERFORMANCE. |
| 2025-09-10 | 601 | Funding only | $293.28M | THIS IS TO ADD $293,277,275.78 OF INCREMENTAL FUNDING TO HLW AND LAW BASELINES AND WTP COMMISSIONING AND REVISE SECTION B TO REFLECT THESE CHANGES. |
| 2025-09-04 | 600 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE SECTION I WITH EEO UPDATES. |
| 2025-08-26 | 599 | Funding only | $121.00M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE CAPITAL FUNDS IN THE AMOUNT OF $37M FOR LAW BASELINE, ADD $84M FOR HLW FEE, AND REVISE SECTION B TO REFLECT THESE CHANGES. |
| 2025-08-15 | 598 | Funding only | -$15.66M | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS IN THE AMOUNT OF -$15,662,520.09 FOR LAB, BOF, AND EMF. |
| 2025-08-11 | 597 | Administrative change | $0 | THIS IS AN ADMINISTRATIVE MODIFICATION TO UPDATE SECTION J, ATTACHMENTS E AND J. |
| 2025-07-31 | 596 | Funding only | $35.00M | THIS MODIFICATION WILL PROVIDE INCREMENTAL CAPITAL FUNDING TO THE DFLAW PROJECT IN THE AMOUNT OF $35,000,000.00. |
| 2025-07-21 | 595 | Change order | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A CHANGE ORDER WITH A LIMITED NOTICE TO PROCEED AND NOT TO EXCEED IN THE AMOUNT OF $4,000,000.00. |
| 2025-07-02 | 594 | Funding only | $40.00M | PROVIDE INCREMENTAL FUNDING TO THE DFLAW BASELINE. |
| 2025-06-30 | 593 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE TO ALIGN WITH THE NOT-TO-EXCEED RUN OUT DATE OF 9/30/2025 AND UPDATE THE CONTRACT ACCORDINGLY. |
| 2025-06-20 | 592 | Funding only | $0 | UPDATE SECTION B, TABLE B.3., INTER-ENTITY WORK ORDER FUNDING. |
| 2025-06-18 | 590 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MOD IS TO REVISE SECTIONS C, G, J-E, AND J-F. |
| 2025-06-04 | 591 | Administrative change | $0 | ADMINISTRATIVE MOD TO MOVE VALUE AND FUNDS OBLIGATED WITHIN STRIPES FROM ITEMS 00002 THROUGH 00005 INTO ITEM 00001 FOR A NET ZERO CHANGE IN VALUE AND FUNDS OBLIGATED. |
| 2025-05-19 | 589 | Change order definitized | $0 | DEFINITIZE THE CHANGE ORDER FOR EFFLUENT MANAGEMENT FACILITY MODIFICATIONS. UPDATE CONTRACT SECTION B TO REFLECT THE NEGOTIATED VALUES. UPDATE SECTION J, ATTACHMENT J, ADVANCE UNDERSTANDING ON COSTS, TABLE 13-B |
| 2025-05-06 | 588 | Supplemental agreement (work within scope) | $0 | UPDATE SECTION B, TABLE B.3, INTER-ENTITY WORK ORDER FUNDING, TO REVISE FUNDING ON IEWO 89303918FEM400008 FUNDING (UNITECH) AND SECTION J, ATT J, ADVANCE UNDERSTANDING ON COSTS, AND ADD WINTER PROTECTIVE CLOTHING. |
| 2025-04-17 | 587 | Administrative change | $0 | THIS IS AN ADMINISTRATIVE MODIFICATION IS TO REFORMAT SECTION J. |
| 2025-04-10 | 586 | Funding only | $30.00M | THIS IS AN ADMINISTRATIVE MODIFICATION IS TO ADD INCREMENTAL FUNDING FOR OPEX IN THE AMOUNT OF $30,000,000 AND INCREASE CLIN 5.0. |
| 2025-03-20 | 585 | Administrative change | $0 | THIS IS AN ADMINISTRATIVE MODIFICATION TO UPDATE SECTIONS G AND J. |
| 2025-03-06 | 584 | Funding only | $373.61M | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES AND PRICES/COSTS AND OBLIGATE $223,612,462.00 TO HLW BASELINE AND $150,000,000.00 TO LAW BASELINE OF INCREMENTAL FUNDING AND INCREASE DFLAW OVERRUN CLIN 5.0 BY $15 |
| 2025-02-27 | 583 | Change order | $0 | INCREASE NOT-TO-EXCEED CEILING VALUE ESTABLISHED IN MODIFICATION 0552 FOR WASTE TREATMENT PLANT HIGH-LEVEL WASTE FACILITY, DESIGN COMPLETION PERIOD PHASE 1A FROM $600 MILLION TO $800 MILLION. |
| 2025-02-26 | 582 | Change order definitized | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE REA 2023-005, REV. 0, WASHINGTON STATE INITIATIVE MEASURE NO. 1433 - CRAFT SICK LEAVE CALENDAR YEARS 2022-2023 AND MULTI-EMPLOYER PENSION PLAN CONTRIBUTION FOR PLAN YEAR 2023, DATED FEBRUARY 27, 2023 |
| 2025-02-06 | 581 | Change order | $0 | THE PURPOSE OF THIS CHANGE ORDER IS TO DIRECT THE CONTRACTOR TO PROCEED WITH THE NECESSARY WORK SCOPE TO COMPLETE THE DESIGN OF THE HIGH-LEVEL WASTE (HLW) FACILITY, DESIGN COMPLETION PERIOD PHASE 1A. |
| 2024-12-19 | 580 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION J, ATTACHMENT R, TO INCORPORATE THE CY 2025 PEMP, REV. 0 INTO SECTION J, LIST OF ATTACHMENTS, OF THE CONTRACT. |
| 2024-12-13 | 579 | Funding only | $100.00M | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES AND PRICES/COSTS AND OBLIGATE $100,000,000.00 OF INCREMENTAL FUNDING AND INCREASE CLIN 5.0. |
| 2024-12-09 | 578 | Change order definitized | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE REA 2022-002, REV. 0 AND MAKE CHANGES TO SECTION B, SUPPLIES OR SERVICES AND PRICES/COSTS, AND SECTION F, DELIVERIES OR PERFORMANCE. |
| 2024-11-21 | 577 | Funding only | $30.00M | THE PURPOSE OF THIS MODIFICATION IS TO CREATE A FUNDING LINE FOR WTP COMMISSIONING, PROVIDE $30M OF INCREMENTAL FUNDING FOR WTP COMMISSIONING, AND REVERSE UPDATES TO CLINS 1.0, 6.0 AND 6.1 AWARDED IN MODIFICATION 576. |
| 2024-10-30 | 576 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ADD HOT COMMISSIONING CLIN 6.0 TO THE CONTRACT. NO OBLIGATIONS ARE ASSOCIATED WITH THIS MODIFICATION. |
| 2024-10-16 | 575 | Administrative change | $0 | THIS MODIFICATION REVISES REFERENCES TO THE NAMES OF THE U.S. DEPARTMENT OF ENERGY ORGANIZATIONAL UNITS IDENTIFIED IN THE CONTRACT, EFFECTIVE OCTOBER 1, 2024. THE NEW OFFICE NAME FOR THE COMBINED OFFICE REPLACES TWO SEPARATE FIELD OFFICE NAMES WHICH |
| 2024-09-09 | 574 | Funding only | $312.55M | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES AND PRICES/COSTS AND OBLIGATE $312,546,718.57 OF INCREMENTAL FUNDING AND INCREASE CLIN 5.0. |
| 2024-09-04 | 573 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ESTABLISH CLIN 5.0 TO RECOGNIZE A COST OVERRUN ON CLINS 1.0 AND 2.0 (DIRECT-FEED LOW-ACTIVITY WASTE PROJECT) IN THE AMOUNT OF $1,140,284,028.00. |
| 2024-08-15 | 572 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE, ESTABLISH A DEDICATED CLIN FOR CONTRACT LINE ITEM 3.2 FOR HIGH LEVEL WASTE FUNDING, AND ESTABLISH HLW FUNDS FOR UNITECH. |
| 2024-07-10 | 571 | Funding only | $4.43M | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND THE CONTRACT TO PROVIDE FULL HLW FUNDING FOR CAPITAL LEASE OMEGA PARK 60/70 AND UPDATE SECTION B WITH $150K FOR UNITECH. |
| 2024-06-12 | 570 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION C, C.9 INTERFACE CONTROL DOCUMENTS ICD 20 & ICD 27 AS WELL AS UPDATE SECTION J, ATTACHMENT E LIST OF APPLICABLE TO CLARIFY APPLICABILITY OF DOE/RL-92-36, HANFORD SITE HOISTING AND RIGGING MANU |
| 2024-05-16 | 568 | Administrative change | -$33.00M | THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE $33M LAW/LAB/BOF FEE, UPDATE SECTION I.29(B), AND UPDATE SECTION J, ATTACHMENTS B AND M. |
| 2024-04-16 | 567 | Change order | $2.00M | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND $2M OF FUNDING TO EMF AND TO PERFORM EMF MODIFICATIONS TO ACCOMMODATE POTENTIAL HIGH DOSE WASTE STREAMS. |
| 2024-04-09 | 566 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ADD CY2023 HLW FEE AND OTHER ADMINISTRATIVE ACTIONS. |
| 2024-03-05 | 565 | Funding only | $320.00M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE $320M OF FY24 INCREMENTAL FUNDING FOR LAW, LAB, BOF AND HLW. |
| 2024-01-16 | 564 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE CONTRACT MODIFICATION PROPOSAL 2023-0003, REV. 0, ADDITIONAL LAB STACK SAMPLING. |
| 2023-12-21 | 563 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS A NET ZERO ADMINISTRATIVE MODIFICATION TO REALLOCATE $26M OF FUNDING FROM HLW BASELINE TO HLW FEE. |
| 2023-12-21 | 562 | Funding only | $166.00M | $166,000,000.00 OF INCREMENTAL FUNDING FOR FY24 LAB BASELINE, LAW BASELINE, BOF BASELINE AND HLW BASELINE. |
| 2023-12-20 | 561 | Supplemental agreement (work within scope) | $0 | INCORPORATE 2023-2024 AWARD FEE PLAN FOR THE HIGH-LEVEL WASTE PROJECT INTO CONTRACT SECTION J, REVISE CONTRACT SECTION B, AND MAKE AN ADMINISTRATIVE CHANGE. |
| 2023-11-20 | 560 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE REQUEST FOR EQUITABLE ADJUSTMENT (REA) 2022-001, REV. 0, COMBINED WEATHER, SMOKE, AND TUNNEL COLLAPSE IMPACTS (2016 THROUGH 2021). |
| 2023-11-14 | 559 | Administrative change | $0 | UPDATES SECTIONS I AND J. |
| 2023-11-07 | 558 | Funding only | $102.62M | INCREMENTAL FUNDING |
| 2023-09-27 | 557 | Funding only | $151.17M | INCREMENTAL FUNDING |
| 2023-09-20 | 556 | Administrative change | $0 | REMOVE COVID CONTRACT CLAUSES H.55, CARES ACT AND I.51A, FAR 52.223-99 |
| 2023-08-01 | 555 | Administrative change | $0 | UPDATE KEY PERSONNEL AND OTHER ADMINISTRATIVE ACTIONS. |
| 2023-07-12 | 554 | Funding only | $80.00M | OBLIGATES HLW BASELINE FUNDING. |
| 2023-07-12 | 553 | Funding only | -$22.78M | DEOBLIGATE FY20 FUNDS FROM EMF COVID, FY21 FUNDS FROM EMF BASELINE, FY20 FUNDS FROM LAW FEE, FY20 FUNDS FROM LAB FEE AND FY20 FUNDS FROM BOF FEE. |
| 2023-06-21 | 552 | Change order | $0 | ISSUE A CHANGE ORDER TO DIRECT THE CONTRACTOR TO PROCEED WITH WORK SCOPE TO COMPLETE THE DESIGN OF THE HLW FACILITY IN A DIRECT-FEED HLW CONFIGURATION. |
| 2023-06-08 | 551 | Supplemental agreement (work within scope) | $0 | DEFINITIZE REQUEST FOR EQUITABLE ADJUSTMENT (REA) 2023-002, REV. 0, MULTI-EMPLOYER PENSION PLAN CONTRIBUTION FOR PLAN YEAR 2022. |
| 2023-05-23 | 550 | Change order definitized | $0 | APPROVE CONTRACT MODIFICATION PROPOSAL 2022-005, REV. 0, GLASS SHARD SAMPLING AND REPORTING REQUIREMENTS. |
| 2023-05-08 | 549 | Administrative change | $0 | UPDATE SECTION G, CONTRACT ADMINISTRATION DATA AND SECTION J, ATTACHMENT F, KEY PERSONNEL. |
| 2023-04-11 | 548 | Administrative change | $0 | EXTEND THE PERIOD OF PERFORMANCE TO AUGUST 31, 2023. |
| 2023-03-27 | 547 | Administrative change | $0 | RECOGNIZE CY21 AND CY22 FINAL AWARD FEE. |
| 2023-02-22 | 546 | Funding only | $300.00M | PROVIDE $300M INCREMENTAL FUNDING FOR LAW AND LAB BASELINE. |
| 2023-02-15 | 545 | Change order definitized | $0 | DEFINITIZE REA CHANGE PROPOSAL 2021-005, REV. 0, TRAINING ADDITIONAL RESOURCES TO SUPPORT COMMISSIONING AND OPERATIONS. |
| 2023-01-25 | 544 | Funding only | $10.50M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE $10;500,000 OF INCREMENTAL FUNDING FOR LAW AND LAB BASELINE FUNDS AND LAW AND LAB COVID FUNDS. |
| 2023-01-25 | 543 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ADMINISTRATIVE CHANGES TO SECTIONS B, I AND J. |
| 2022-12-21 | 542 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO RESCIND AND REPLACE CONTRACT MODIFICATION NO. 417, SECTION B, TABLE B.1 TOTAL ESTIMATED CONTRACT PRICE. |
| 2022-11-03 | 541 | Funding only | $60.39M | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE $60,387,000 OF INCREMENTAL FUNDING FOR HLW AND DEOBLIGATE LAW AND LAB BASELINE FUNDS AND OBLIGATE TO LAW AND LAB COVID FUNDS. |
| 2022-11-02 | 540 | Change order definitized | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE REA 2022-003, REV. 0, WASHINGTON STATE INITIATIVE MEASURE NO. 1433, CRAFT SICK LEAVE, CALENDAR YEAR 2021. |