TERMINAL FLIGHT DATA MANAGER IGF::OT::IGF
Up for re-bid: ends 2028-06-29. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
126 actions since 2022-10-20. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-18 | P00210 | Funding only | $446.8K | 1) MEMORIALIZE THE AGREEMENT BETWEEN FAA AND LEIDOS TO INCORPORATE 30 ADDITIONAL SITES A. UPDATE CLIN 06-002 (IMPLEMENTATION CLIN) TO ADD THE LAST 30 SITES. B. UPDATE CLIN 0018 (PRODUCTION CLIN) TO AUTHORIZE SYSTEM PRODUCTION FOR 30 ADDITIONAL SITE |
| 2026-09-16 | P00209 | Funding only | $379.0K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) SECTION B INCREASED THE CEILING FOR ADDITIONAL SLOC ON 05-005 (60 SLOC) & 05-005M (82 SLOC). 2) SECTION G ADDS FUNDING TO CLINS 05-005, 05-005M, AND 06-001M. THE AMOUNT OF FUNDS OBLIGATED INCREASE FRO |
| 2026-09-09 | P00208 | Funding only | $6.41M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B TO ADJUST CLIN CEILINGS A. DECREASE 04-004A TO ALIGN WITH ACTUAL FUNDING B. DECREASE 05-004 TO ALIGN WITH ACTUAL FUNDING C. DECREASE 05-004A TO ALIGN WITH ACTUAL FUNDING D. INCREASE 06- |
| 2026-09-02 | P00207 | Funding only | $545.0K | MOD 207 |
| 2026-08-22 | P00206 | Administrative change | -$82 | 1) UPDATE SECTION B TO UPDATE CLIN 07-006 DESCRIPTION TO ADDRESS ATTACHMENT J-11 (REV. 16) DISPLAY SIZES FOR TTS-1 AND TTS-2 TRAINING EQUIPMENT PER AIRPORT. 2) UPDATE ATTACHMENT J-11 (REV. 16) TO UPDATE THE WATERFALL SCHEDULE AND REVISE TABLES 1 AN |
| 2026-08-19 | P00205 | Funding only | $0 | 1) UPDATE SECTION B TO UPDATE CLIN 07-006 DESCRIPTION TO ADDRESS ATTACHMENT J-11 (REV. 16) DISPLAY SIZES FOR TTS-1 AND TTS-2 TRAINING EQUIPMENT PER AIRPORT. 2) UPDATE ATTACHMENT J-11 (REV. 16) TO UPDATE THE WATERFALL SCHEDULE AND REVISE TABLES 1 AN |
| 2026-08-04 | P00204 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO: UPDATE SECTION G TO REALLOCATE FUNDING TO CLINS 06-001 AND 06-005. 1) FUNDING IS REALLOCATED FROM CLIN 03-002 TO CLIN 06-005 IN THE AMOUNT OF: WA-25-06916 12782A0250.2025.5FF72B07A0.WAG5310000.31047.17 |
| 2026-07-10 | P00203 | Funding only | $1.00M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) EXERCISE CLIN 06-001 AND ESTABLISH CLIN 06-001M TO MEMORIALIZE THE OFFER FROM LEIDOS RECEIVED ON MAY 11, 2026, TO SUPPORT THE TFDM LOGISTICS, SUPPLY SUPPORT, CONTRACTOR SUPPORT SERVICES, AND REMOTE MONITORI |
| 2026-07-10 | P00202 | Funding only | $424.9K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) EXERCISE CLIN 06-001 AND ESTABLISH CLIN 06-001M TO MEMORIALIZE THE OFFER FROM LEIDOS RECEIVED ON MAY 11, 2026, TO SUPPORT THE TFDM LOGISTICS, SUPPLY SUPPORT, CONTRACTOR SUPPORT SERVICES, AND REMOTE MONITORI |
| 2026-07-01 | P00201 | Funding only | $879.1K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) EXERCISE CLIN 06-001 AND ESTABLISH CLIN 06-001M TO MEMORIALIZE THE OFFER FROM LEIDOS RECEIVED ON MAY 11, 2026, TO SUPPORT THE TFDM LOGISTICS, SUPPLY SUPPORT, CONTRACTOR SUPPORT SERVICES, AND REMOTE MONITORI |
| 2026-06-24 | P00200 | Funding only | $816.4K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B TO DEFINITIZE CLIN 06-004 AND CLIN 06-004A, INCREASE THE CEILING FOR CLIN 06-004, AND INCREASE THE CEILING CLIN FOR CLIN 06-004A. 2) UPDATE SECTION G TO INCREMENTALLY FUND CLINS 06-004 AN |
| 2026-06-24 | P00199 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE CEILING, TRACKING TABLE AND FUND CLIN 05-004 2) ADMINISTRATIVE CORRECTION TO THE PERIOD OF PERFORMANCE FOR CLIN 0016M IN SECTION F 3) UPDATE H.5 KEY PERSONNEL FOR A CHANGE IN THE LEAD SYSTEM ARCHIT |
| 2026-06-18 | P00198 | Funding only | $3.50M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B TO MEMORIALIZE THE FAA OFFER PROVIDED TO LEIDOS MAY 6, 2026 IN SUPPORT OF CPFF CLINS 06-005 (F&E) AND 06-005M (OPS) FOR BUILD 2.7 REQUIREMENTS. 2) SECTION F ESTABLISHMENT AND ADJUST |
| 2026-06-09 | P00197 | Funding only | $2.51M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B A. ESTABLISH CLIN 0016M B. INCREASE CLIN 0017M CEILING TO SUPPORT CONTINUED REQUIREMENTS C. INCREASE CLIN 04-005 TO COVER AUTHORIZED COSTS FOR JUNE 2) SECTION F ADJUST AND ESTABLISHMENT |
| 2026-05-15 | P00196 | Funding only | $14.49M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B A. ADD DELTA SPARES MATERIALS ON CLIN 07-006 RESULTING FROM THE PROVISIONING CONFERENCE B. AUTHORIZED $5,000 FOR ENGINEERING ESTIMATE FOR THE BUILD 2.5T DELTA PCA AND INCREASE THE CEILING |
| 2026-05-15 | P00195 | Funding only | $535.4K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B A. INCREASE THE SLOC REQUIREMENT ON CLIN 05-005M (OPS) AND CORRECT THE TRAVEL REFERENCE FROM CLIN 0017 TO CLIN 0017M. B. INCREASE THE SLOC REQUIREMENT FOR CLIN 05-005 (F&E) C. UPDATE |
| 2026-05-08 | P00194 | Funding only | $46.0K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B TO CLARIFY APPLICABILITY OF CLIN 0017M TO SUPPORT ALL OPS CLIN TRAVEL REQUIREMENTS AND INCREASE THE CEILING. 2) EXTEND THE PERIOD OF PERFORMANCE (POP) FOR CLIN 0017M THROUGH OCTOBER 2026. |
| 2026-04-27 | P00193 | Funding only | $2.33M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B TO INCREASE THE CEILING A. CLIN 07-006 FOR ADDITIONAL MATERIALS AS A RESULT OF THE PROVISIONING CONFERENCE. B. CLIN 05-004 TO UPDATE THE FUNDING AMOUNT IN THE TRACKING TABLE FOR 05-004 AN |
| 2026-04-22 | P00192 | Funding only | $435.0K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B TO AUTHORIZE CLIN 0020 FOR PROPOSAL PREPARATION ON CLIN 06-001/06-001M 2) UPDATE SECTION G TO PROVIDE INCREMENTAL FUNDING FOR CLIN 05-005M A. FUNDING IS INCREMENTALLY FUNDED ON CLIN 05-00 |
| 2026-04-17 | P00191 | Funding only | $4.38M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B FOR 15 MORE SITES A. ESTABLISH CLIN 0018 B. APPLY SHIPPING FOR 15 SITES TO CLIN 04-006 C. INCREASE CLIN 05-002 FOR 15 SITES 2) REVISE THE STATEMENT OF WORK (SOW) C.4.4.1.5 PER SECURITY |
| 2026-04-14 | P00190 | Funding only | $750.8K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B: A. INCREASE CEILING ON CLIN 07-006 FOR ADDITIONAL MATERIAL AND UPDATE THE CLIN DESCRIPTION B. INCREASE CEILING ON CLIN 05-004 TO SHOW UPDATES TO THE TASK ORDER AUTHORIZATION LEVELS C. I |
| 2026-04-09 | P00189 | Funding only | $1.84M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE CLIN 07-006 IN SECTION B TO INCREASE THE CEILING FOR ADDITIONAL LAB MATERIALS. 2) FUND CLIN 07-006 IN SECTION G TO SUPPORT LAB MATERIALS. WA-26-03980 IN THE AMOUNT OF $1,839,864.00 THEREFORE, THIS |
| 2026-04-06 | P00188 | Funding only | -$417.5K | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE TO DPAS RATING LANGUAGE 2) UPDATE SECTION B: A. CLIN 0004 TO APPLY CREDITS FOR ENGINEERING STUDY AND SOFTWARE (SW) NOW PROVIDED BY THE GOVERNMENT AND REMOVE A PARAGRAPH THAT IS CAPTURED IN TABLE |
| 2026-03-16 | P00187 | Funding only | $24.73M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) SECTION B CHANGE TO MEMORIALIZE THE CLIN 07-006 DEFINITIZED REQUIREMENTS AND COSTS TO ESTABLISHING THE NEW CLIN 07-006 TO SUPPORT BULK BUY AND LONG LEAD MATERIAL. 2) SECTION F IS UPDATED TO EXTEND THE PER |
| 2026-03-04 | P00186 | Funding only | $14.64M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) UPDATE SECTION B A. UPDATE CEILING AND SUMMARY TABLE FOR CLIN 05-004. B. UPDATE CEILING FOR CLIN 05-004A. C. CLIN 0004 SITE SIZE CORRECTION FOR RSW AND HOU. D. INCREASE CLIN 0017 CEILING TO SUPPORT UPCO |
| 2026-02-13 | P00185 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO: 1) APPLY DPAS RATING TO THE CONTRACT DTFAWA-16-C-00021 2) UPDATES TO SECTION B A. ADD AIR TRAFFIC (AT) TRAINING DELTA PACKS TO CLIN 04-005T B. APPLY CREDITS FOR SOFTWARE (SW), UPDATE SITES SIZES, AND CAI/IO |
| 2026-02-05 | P00184 | Funding only | $4.60M | THE PURPOSE OF THIS MODIFICATION IS TO: 1) SECTION B INCREASE AUTHORIZATION TO PROCEED (ATP) ON CLIN 07-006 2) SECTION F CLIN 04-005 MILESTONE UPDATED LANGUAGE 3) SECTION G ADD INCREMENTAL FUNDING AND ADMINISTRATIVE CORRECTION TO CLIN 02-004 FROM |
| 2026-01-28 | P00183 | Funding only | -$42.5K | THE PURPOSE OF THIS MODIFICATION IS TO: 1. UPDATE SECTION B: A. REVISE TASK ORDER TRACKER IN CLIN 05-004 TO INCLUDED RECENT CHANGES FOR TO 52, 53, 55 B. INCREASE CLIN 07-006 CEILING FOR AN AUTHORIZATION TO PROCEED (ATP) FOR TWO SUPPORT LABS C. AU |
| 2026-01-21 | P00182 | Funding only | $550.0K | THE PURPOSE OF THIS MODIFICATION IS TO 1) MEMORIALIZE THE AGREEMENT BETWEEN FAA AND LEIDOS TO INCORPORATE 7 SITES. A. UPDATE CLIN 05-002 FOR SITE IMPLEMENTATION B. UPDATE CLIN 0004 FOR PAT C. UPDATE CLIN 04-006 FOR SHIPPING COSTS D. INCREASE CL |
| 2026-01-12 | P00181 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CEILING ON CLIN 04-005 BY $152,055 TO SUPPORT AIR TRAFFIC (AT) TRAINING SUBJECT MATTER EXPERT (SME). THEREFORE, THIS CONTRACT IS MODIFIED AS FOLLOWS: |
| 2026-01-06 | P00180 | Funding only | $170.0K | THE PURPOSE OF THIS MODIFICATION IS TO 1) UPDATE SECTION B A. REFRESH THE TASK ORDER TRACKER IN CLIN 05-004. B. INCREASE CLIN 04-005 CEILING FOR AN ADDITIONAL PTR (#115) FIX. C. NOTE: THE CLIN 0017 CEILING WAS INCREASE BY $22,000.00 IN MOD 179 B |
| 2025-12-22 | P00179 | Funding only | $15.85M | THE PURPOSE OF THIS MODIFICATION IS TO 1) UPDATE SECTION B A. INCREASE CLIN 07-006 CEILING FOR AN AUTHORIZATION TO PROCEED (ATP) FOR LONG LEAD EQUIPMENT. B. INCREASE CLIN 0017 FOR TRAVEL EXPENSES 2) UPDATE SECTION G A. CHANGE FAA PROGRAM MANAGE |
| 2025-12-15 | P00178 | Funding only | $400.0K | THE PURPOSE OF THIS MODIFICATION IS TO 1) MEMORIALIZE THE AGREEMENT BETWEEN FAA AND LEIDOS TO INCORPORATE 2 ADDITIONAL SITES. 2) INCREASE CLIN 04-005 CEILING TO ACCOUNT FOR ONE ADDITIONAL PTR FIX. 3) EXTEND PERIOD OF PERFORMANCE (POP) TO CLIN 04- |
| 2025-12-02 | P00177 | Funding only | $444.7K | THE PURPOSE OF THIS MODIFICATION IS TO 1) UPDATE SECTION B AS FOLLOWS: A. INCREASE THE CEILING BY $1,873.51 ON CLIN 03-002 FOR MEDIA CONVERTERS LEIDOS REPLACED AT IAH. B. DECREASE THE CEILING FOR CLIN 03-004 TO MATCH CURRENT REDUCED FUNDING. FUN |
| 2025-12-01 | P00176 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO 1) SECTION B CHANGE TO DEFINITIZE TFDM CLINS: A. MEMORIALIZE THE CLIN 04-005T DEFINITIZED COSTS IN RESPONSE TO ESTABLISHING THE NEW CLIN TO SUPPORT BUILD 2.5T. B. MEMORIALIZE THE CLIN 05-001 DEFINITIZED REQU |
| 2025-11-24 | P00175 | Funding only | $1.19M | THE PURPOSE OF THIS MODIFICATION IS TO 1) UPDATES TO SECTION B: A. INCREASE THE AUTHORIZATION TO PROCEED (ATP) ON CLIN 07-006 BY $1,561,995.97 FROM $700,000.00 TO $2,261,995.97 TO SUPPORT LONG LEAD EQUIPMENT FOR THE TSLE LAB AND DL360 GEN 10 UPGRA |
| 2025-11-19 | P00174 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO 1) UPDATES TO SECTION B A. REDUCE CLIN 04-001 CEILING (NOT FUNDED AMOUNT) TO ACCOUNT FOR OPS FUNDING COVERED UNDER CLIN 05-001M IN MOD 165. B. UPDATE TASK ORDER TRACKER IN CLIN 05-004 TO SHOW COST ASSOCIATE |
| 2025-10-22 | P00173 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO 1) ADMINISTRATIVE CORRECTION IN SECTION J TO UPDATE DID TRNG-13 THAT WAS INTENDED FOR INCLUSION IN MOD 137 WHEN THE CORRESPONDING CDRL TR-13 WAS UPDATED AND THE CORRESPONDING UPDATES TO THE SECTION J-LIST AND |
| 2025-09-24 | P00172 | Funding only | $800.0K | THE PURPOSE OF THIS MODIFICATION IS TO 1) UPDATE AND EXERCISE CLIN 05-001 AND MEMORIALIZE THE AUTHORIZED TO PROCEED (ATP) COST OF $800,000.00 TO SUPPORT THE TFDM LOGISTICS, SUPPLY SUPPORT, CONTRACTOR SUPPORT SERVICES, AND REMOTE MONITORING AND LO |
| 2025-09-23 | P00171 | Funding only | $700.0K | THE PURPOSE OF THIS MODIFICATION IS TO 1) UPDATE AND EXERCISE CLIN 07-006 AND MEMORIALIZE AGREED TO AUTHORIZED TO PROCEED (ATP) COST OF $700,000.00 TO SUPPORT THE BULK BUY AND LONG LEAD EQUIPMENT ITEMS FOR TECHNOLOGY REFRESHMENT OF COTS HARDWARE A |
| 2025-09-16 | P00170 | Funding only | $3.81M | THE PURPOSE OF THIS MODIFICATION IS TO 1) SECTION B CHANGES: A. ADJUST CLIN 0020 AUTHORIZED PROPOSAL PREPARATION TO SUPPORT CLIN 05-001 PROPOSAL SUBMISSION. B. ESTABLISH CLIN 04-001M TO RECLASSIFY F&E FUNDING FROM CLIN 04-001 TO 04-001M |
| 2025-09-16 | P00169 | Funding only | $1.96M | THE PURPOSE OF THIS MODIFICATION IS TO 1) REVISIONS TO SECTION B FOR CLINS 05-004 AND 05-004A: A. INCREASE THE CEILING ON CLIN 05-004 TO SUPPORT TASK ORDER 55 FOR THE TECH REFRESH EQUIPMENT PURCHASES, PROCUREMENT LABOR, AND INSTALLATION LABOR |
| 2025-09-05 | P00168 | Funding only | $235.5K | THE PURPOSE OF THIS MODIFICATION IS TO 1) MEMORIALIZE THE AGREEMENT BETWEEN FAA AND LEIDOS TO INCORPORATE 8 ADDITIONAL SITES A. UPDATE CLIN 05-002 (IMPLEMENTATION CLIN) TO ADD AUS, DAY, SDF, IAD, RSW, SMF, HOU, AND SAN. B. UPDATE CLIN 0004 (PRO |
| 2025-09-03 | P00167 | Funding only | $1.67M | THE PURPOSE OF THIS MODIFICATION IS TO 1) ESTABLISH 04-005T AND MEMORIALIZE AGREED TO AUTHORIZED TO PROCEED (ATP) COST OF $1,673,443.00 FOR ESTIMATED 2.5 TO 3 MONTHS OF 04-005T TASKS RELATED TO BUILD 2.5T ENHANCEMENTS/ADDITIONAL FUNCTIONALITY F |
| 2025-08-25 | P00166 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO 1)UPDATES TO SECTION B TO MEMORIALIZE AGREED TO COST FOR TASKS RELATED TO DEN AND FLL PROVIDED TO LEIDOS ON AUGUST 13, 2025, IN SUPPORT OF CLIN 04-002 IMPLEMENTATION: PRE-SITE SURVEY, INSTALLATION, INTEGRATI |
| 2025-08-24 | P00165 | Administrative change | $1.70M | THE PURPOSE OF THIS MODIFICATION IS TO 1) UPDATE SECTION B TO MEMORIALIZE FAA OFFER PROVIDED TO LEIDOS AUGUST 4, 2025 IN SUPPORT OF CPFF CLIN 05-001M &CLIN 0017M. A. ADD NEW CLIN 0017M B. ADD CLIN 05-001M 2) REVISE SECTION C TO ADD DIRECTI |
| 2025-08-08 | P00164 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO 1)MEMORIALIZE THE AGREEMENT BETWEEN FAA AND LEIDOS TO INCORPORATE UPDATES FROM THE CURRENT WATERFALL SCHEDULE A. UPDATE CLIN 04-002 (IMPLEMENTATION CLIN) TO ADD EWR, PHL, LGA, JFK, ORD, BOS, AND MCO PER THE |
| 2025-08-06 | P00163 | Funding only | $274.0K | THE PURPOSE OF THIS MODIFICATION IS TO ADD INCREMENTAL FUNDING TO CLIN 03-006 AND 04-001 IN SECTION G. PR# WA-25-08410 IN THE AMOUNT OF $21,000.00 PR# WA-25-08412 IN THE AMOUNT OF $253,000.00 THE AMOUNT OF FUNDS CURRENTLY OBLIGATED IS INCREASED |
| 2025-07-16 | P00162 | Administrative change | $1.04M | 1)INFORMATIONAL CORRECTION TO CLEAR UP MOD NUMBERING ALIGNMENT FROM 154 TO 161 BETWEEN THE MOD ACTION AND PRISM. 2)CLIN 0020 CORRECTION AND UPDATE A. AUTHORIZE PROPOSAL PREPARATION COSTS FOR CLIN 05-001. B. ADMINISTRATION CORRECTION IN SECTION B T |
| 2025-07-03 | P00161 | Administrative change | $1.81M | TO CORRECT THE MOD NUMBERING ISSUE FOR TFDM WE WILL PROCESS MODS 160 AND 161 TOGETHER IN PRISM MOD 160 1) INCREASE THE COST, FEE, AND CEILING AMOUNT FOR CLIN 04-001 FROM $6,068,936.75 TO $7,195,397.15 2) REVISE SECTION C.11 AND SUBSECTIONS IN SUP |
| 2025-06-25 | P00160 | Administrative change | $10.45M | 1) UPDATE SECTION B TO INCREASE THE CEILING FOR CLINS 04-004A TO $138,933.00, 0016 TO $15,052,840.48, 0017 TO $330,110.08, AND 0020. 2) REALLOCATE UNUSED VALUE TO CLIN 20 FOR FUTURE PROPOSAL PREPARATION COSTS. 3) EXTEND PERIOD OF PERFORMANCE ON CLI |
| 2025-06-18 | P00159 | Administrative change | $1.79M | 1) UPDATE SECTION B TO MEMORIALIZE FAA OFFER PROVIDED TO LEIDOS JUNE 2, 2025 IN SUPPORT OF CPFF CLINS 05-005 & CLIN 05-005M. 2) UPDATE APPROPRIATE SECTIONS TO ESTABLISH NEW CLIN 05-005M. 3) AUTHORIZE ASSOCIATED TRAVEL UNDER CLINS 17 IN SUPPO |
| 2025-06-17 | P00158 | Administrative change | $0 | 1) SECTION B ADMINISTRATIVE CORRECTION: A. ADMINISTRATIVE CORRECTION IN SECTION B FOR CLIN 02-005AA CEILING AND REESTABLISH THE ESTIMATED COST/FEE TO CORRECT AMOUNTS ESTABLISHED IN MOD 147. B. ADMINISTRATIVE INCLUSION OF E47 PRICING IN SECTION B I |
| 2025-06-16 | P00157 | Administrative change | $0 | THE PURPOSE OF THIS MOD IS TO REDUCE CEILINGS FOR COMPLETED CLINS AND UNPRICED OPTION CLINS. CLIN 0001 - TFDM SYSTEM DESIGN & DEVELOPMENT THROUGH SITE ACCEPTANCE TESTING FOR INITIAL SITES FROM: CLIN 0001 CEILING $117,109,985.23 OVERRUN TO: CLI |
| 2025-06-02 | P00156 | Administrative change | $0 | SECTION F SPECIFIC CHANGES INSERT PERIOD OF PERFORMANCE FOR PHASE OUT AND SUPPORTING TRAVEL FOR PHASE OUT CLINS MISSING FROM THE BASE CONTRACT. SECTION G SPECIFIC CHANGES IN MODIFICATION 129, THE TOTAL CONTRACT CEILING BY MOD (G.23.A) ACCURATEL |
| 2025-05-23 | P00155 | Funding only | $2.08M | MOD 152 PR# WA-25-03407 IN THE AMOUNT OF $328,000.00 MOD 154 PR# WA-25-05578 IN THE AMOUNT OF $152,000.00 PR# WA-25-05574 IN THE AMOUNT OF $1,130,000.00 PR# WA-25-05665 IN THE AMOUNT OF $30,169.00 PR# WA-25-05575 IN THE AMOUNT OF $5,000.00 |
| 2025-05-13 | P00154 | Administrative change | $0 | 1)ADJUST CEILING IN SECTION B ON CLINS 02-005AA (FROM MOD 153 REALLOCATION) AS WELL AS 03-004A, 04-004A, 04-004, 04-007, 05-007, 06-007, AND 07-009 TO SUPPORT ADDITIONAL FUNDING CHANGES. 2)UPDATE SECTION B CLINS 03-006, 04-002, AND 0004 TO REPLACE P |
| 2025-05-01 | P00153 | Administrative change | $0 | 1) UPDATE SECTION G TO REALLOCATE $2,136,013.13 FROM CLIN 02 005AA TO 04 005 WHICH IS THE ACTIVE CLIN SUPPORTING FUTURE ENHANCEMENTS/ADDITIONAL FUNCTIONALITY FOR TFDM SYSTEM. A. FUNDING IS REALLOCATED FROM CLIN 02-005AA IN THE AMOUNT OF: PR# WA-24 |
| 2025-05-01 | P00152 | Administrative change | $0 | 1)INCREASE CEILING FOR CLIN 0016 FROM $11,791,822.08 TO $12,607,076.68. 2)UPDATE SECTION C TO DEFINE CDRL E47 IN SUPPORT OF THE REVISED OPERATIONAL BUILD RELEASE. 3)EXTEND THE PERIOD OF PERFORMANCE FOR CLIN 0016 TO JUNE 30, 2025. 4)PROVIDE INCREME |
| 2025-04-02 | P00151 | Administrative change | $0 | 1) UPDATE SECTION B TO MEMORIALIZE AGREED TO LANGUAGE PERTAINING TO MILESTONE PAYMENT. 2) UPDATE SECTION F, CLIN 0011D BUILD 2.3 TO EXTEND OT READINESS DATE FROM 3/24/2025 TO 3/28/2025. 3) UPDATE SECTION F TO EXTEND CLIN 4 PERIOD OF PERFORMANCE TO |
| 2025-03-06 | P00150 | Funding only | $475.0K | INADVERTENTLY LEFT OFF OF MOD 144. |
| 2025-03-04 | P00149 | Funding only | $2.20M | PLEASE NOTE THAT PRISM MOD 149 IS LEIDOS MOD 150 1) INCREASE THE COST AND FEE TO CLIN 0016 FOR A 1 MONTH PERIOD OF PERFORMANCE EXTENSION. 2) UPDATE SECTION B CLIN CEILINGS AND VALUE. A) ADMINISTRATIVE UPDATE TO CLIN 0008 CEILING FROM A MOD 129 RED |
| 2025-02-26 | P00148 | Funding only | $0 | PLEASE NOTE THAT PRISM MOD 148 IS LEIDOS MOD 149 A. CLIN 0020 PERIOD OF PERFORMANCE IS EXTENDED TO JUNE 29, 2025. B. SECTION F.2.2 BASE CLIN PERIODS OF PERFORMANCE IS CHANGED AS FOLLOWS: CHANGES TO SECTION F IN WILL BE REFLECTED IN THE NEXT UPDATE |
| 2025-02-25 | P00147 | Administrative change | $0 | PLEASE NOTE THAT PRISM MOD 147 IS LEIDOS MOD 149 CLIN 02-005AA 1) ALL PREVIOUSLY PLANNED CLIN 02-005AA WORK IN PROCESS (WIP) (E.G. REMAINING SOFTWARE DEVELOPMENT, IMPLEMENTATION, TEST ACTIVITIES AND PTR RESOLUTION) FOR BUILD 2.4 BEYOND JANUARY 3, 2 |
| 2025-02-18 | P00146 | Administrative change | $0 | PLEASE NOTE THAT PRISM MOD 146 IS LEIDOS MOD 148 REQUEST THE CONTINUANCE OF BI-WEEKLY TRAINING COURSE REVIEW MEETINGS (SECTION C.11.6.5.2 BI-WEEKLY REVIEWS) IN JANUARY 2025 THROUGH JUNE 30, 2025 AND UPDATE ATTACHMENT J-07 (WORK GROUP LISTING) ACCORD |
| 2025-02-14 | P00145 | Administrative change | $0 | PLEASE NOTE THAT PRISM MOD 145 IS LEIDOS MOD 147 UPDATE SECTION F TO AUTHORIZE THE EXTENSION TO THE PERIOD OF PERFORMANCE (POP) FOR CLIN 0004 FROM DECEMBER 31, 2024 TO MARCH 31, 2025. A. ALLOW TIME FOR THE FAA TO REVIEW THE CLIN 0004 ENGINEERING ST |
| 2025-01-24 | P00144 | Funding only | $4.24M | THE PURPOSE OF THE MOD IS TO INCREASE THE COST AND FEE FOR CLIN 11D BUILD 2.3 FOR AN ADDITIONAL 350 SLOC AND TO UPDATE THE APPLICABLE SECTIONS OF THE CONTRACT. SECTION B COSTS FOR THIS CHANGE IN CLIN 11D IS REVISED AND INCREASED BY $1,596,784.87 AN |
| 2024-11-25 | P00143 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THE MOD IS TO INCREASE THE COST AND FEE FOR CLIN 11D BUILD 2.3 FOR AN ADDITIONAL 350 SLOC AND TO UPDATE THE APPLICABLE SECTIONS OF THE CONTRACT. SECTION B COSTS FOR THIS CHANGE IN CLIN 11D IS REVISED AND INCREASED BY $1,596,784.87 AN |
| 2024-11-21 | P00142 | Funding only | $3.18M | THE PURPOSE OF THE MOD IS TO INCREASE THE COST AND FEE FOR CLIN 11D BUILD 2.3 FOR AN ADDITIONAL 350 SLOC AND TO UPDATE THE APPLICABLE SECTIONS OF THE CONTRACT. SECTION B COSTS FOR THIS CHANGE IN CLIN 11D IS REVISED AND INCREASED BY $1,596,784.87 AN |
| 2024-11-19 | P00141 | Change order definitized | $1.97M | THE PURPOSE OF THE MOD IS TO INCREASE THE COST AND FEE FOR CLIN 11D BUILD 2.3 FOR AN ADDITIONAL 350 SLOC AND TO UPDATE THE APPLICABLE SECTIONS OF THE CONTRACT. SECTION B COSTS FOR THIS CHANGE IN CLIN 11D IS REVISED AND INCREASED BY $1,596,784.87 AN |
| 2024-10-14 | P00140 | Supplemental agreement (work within scope) | $0 | REVISE COST FOR CLIN 04-001 |
| 2024-09-25 | P00139 | Funding only | $10.46M | CLIN 0016 PERIOD OF PERFORMANCE EXTENSION |
| 2024-09-18 | P00138 | Administrative change | $2.18M | INCREASE THE COST AND FEE TO CLIN 0011D FOR ADDITIONAL 1,200 SLOC REQUIRED FOR BUILD 2.3 |
| 2024-09-17 | P00137 | Supplemental agreement (work within scope) | $0 | MEMORIALIZE THE DEFINITIZATION OF CLIN 04-001 |
| 2024-09-13 | P00136 | Administrative change | $0 | UPDATE SECTION B TO COMBINE ALL COST AND FEE VALUES UNDER CLINS 02-005 AA AND AB INTO CLIN 02-005AA. |
| 2024-09-06 | P00135 | Supplemental agreement (work within scope) | $0 | UPDATE SECTION B TO REDUCE CEILINGS OF SELECT EXPIRED UNEXECUTED CLINS AND OPTIONAL UNPRICED CEILING CLINS |
| 2024-08-21 | P00134 | Supplemental agreement (work within scope) | $0 | MEMORIALIZE THE DEFINITIZED REQUIREMENTS AND COSTS IN RESPONSE TO THE BASELINE CHANGE DECISION (BCD) REQUEST FOR OFFER (RFO) |
| 2024-08-06 | P00133 | Supplemental agreement (work within scope) | $0 | CLIN 0004 AND 0004A CHANGES |
| 2024-07-23 | P00132 | Administrative change | $10.67M | INCREMENTAL FUNDING |
| 2024-07-18 | P00131 | Supplemental agreement (work within scope) | $0 | DEFINITIZE CHANGES TO CLINS 03-006 AND 04-002 |
| 2024-07-15 | P00130 | Supplemental agreement (work within scope) | $0 | UPDATE SECTIONS B AND G |
| 2024-07-03 | P00129 | Funding only | $0 | UPDATE SECTIONS B AND G |
| 2024-06-17 | P00128 | Funding only | $562.5K | ADD INCREMENTAL FUNDING |
| 2024-06-04 | P00127 | Supplemental agreement (work within scope) | $0 | REVISE SECTION B TO ADD CLIN 0011D COST |
| 2024-06-03 | P00126 | Funding only | $314.0K | ADD FUNDING |
| 2024-05-14 | P00125 | Funding only | $4.36M | ADD FUNDING |
| 2024-05-10 | P00124 | Supplemental agreement (work within scope) | $0 | CHANGE SCHEDULE DATES FOR THE UPCOMING PRODUCTION ACCEPTANCE TEST (PAT) |
| 2024-04-11 | P00123 | Supplemental agreement (work within scope) | $0 | AUTHORIZE LEIDOS TO BEGIN TRAINING WORKGROUP MEETINGS UNDER CLIN 11D |
| 2024-04-02 | P00122 | Change order | $0 | REVISE SCHEDULE OF WORK, SECTION B AND SECTION F |
| 2024-03-15 | P00121 | Funding only | $622.0K | FUNDING MODIFICATION |
| 2024-03-15 | P00120 | Funding only | $5.43M | FUNDING MODIFICATION |
| 2024-03-15 | P00119 | Change order | $0 | THE PURPOSE OF THIS CHANGE ORDER MODIFICATION IS TO AUTHORIZE LEIDOS TO BEGIN ALL EFFORTS WITH RESPECT TO THE ADDITIONAL REQUIREMENTS FOR CLIN 0011D (TITLED FUTURE ENHANCEMENTS BUILD 1.5, 2.2, 2.3) OUTLINED IN THE ATTACHED SOW. CONTRACTOR SHALL SEGRE |
| 2024-03-05 | P00118 | Change order | $0 | MAKE CHANGES TO CLIN 02001 FEE AND CLIN 0020 |
| 2024-03-01 | P00117 | Funding only | $940.0K | MAKE CHANGES TO CLIN 0020 AND ADD FUNDING |
| 2024-02-22 | P00116 | Change order | $0 | MAKE CHANGES TO CLIN 0007D |
| 2023-12-22 | P00115 | Funding only | $4.23M | MAKE CHANGES TO CLINS 02-004A, 0008 AND 0020 |
| 2023-12-14 | P00114 | Change order | $75.0K | MAKE CHANGES TO CLINS 01-001, 0007A, 0008A, 0008, 0017, 03-002 AND 03-002A |
| 2023-09-18 | P00113 | Administrative change | $280.0K | MAKE CHANGES TO CLIN 0003, 0003B, 03-002 |
| 2023-09-09 | P00112 | Funding only | $8.57M | PROVIDE INCREMENTAL FUNDING |
| 2023-09-08 | P00111 | Administrative change | $1.04M | PROVIDE INCREMENTAL FUNDING |
| 2023-09-07 | P00110 | Administrative change | $0 | THE EXTENSION OF 2.3 TRR TO JULY WAS DRIVEN BY THE GOVERNMENT ADDITION OF REQUIREMENTS AND THE PREDECESSOR BUILD 2.2 SCHEDULE DELAY. |
| 2023-09-05 | P00109 | Supplemental agreement (work within scope) | $0 | EXECUTE ADMINISTRATIVE CHANGES TO SECTION B |
| 2023-08-17 | P00107 | Administrative change | $0 | PROVIDE INCREMENTAL FUNDING TO CONTINUE SERVICES |
| 2023-08-09 | P00108 | Funding only | $22.6K | PROVIDE INCREMENTAL FUNDING TO CONTINUE SERVICES |
| 2023-07-12 | P00106 | Funding only | $543.7K | PROVIDE INCREMENTAL FUNDING TO CONTINUE SERVICES |
| 2023-07-11 | P00105 | Supplemental agreement (work within scope) | $975.0K | PROVIDE INCREMENTAL FUNDING TO CONTINUE SERVICES |
| 2023-07-07 | P00104 | Supplemental agreement (work within scope) | $794.0K | PROVIDE INCREMENTAL FUNDING TO CONTINUE SERVICES |
| 2023-06-28 | P00103 | Funding only | $6.23M | PROVIDE INCREMENTAL FUNDING TO CONTINUE SERVICES |
| 2023-06-21 | P00102 | Administrative change | $715.0K | SOFTWARE DEVELOPMENT |
| 2023-06-08 | P00101 | Administrative change | $105.0K | TERMINAL FLIGHT DATA MANAGER - ADDED CLIN0007D |
| 2023-05-23 | P00100 | Administrative change | $0 | TERMINAL FLIGHT DATA MANAGER - SECTION J UPDATES |
| 2023-05-12 | P00099 | Administrative change | $0 | TERMINAL FLIGHT DATA MANAGER - SECTION J UPDATES |
| 2023-04-19 | P00098 | Funding only | $3.27M | TERMINAL FLIGHT DATA MANAGER - BUILD 1 QUALITY INCENTIVE FEE PAYMENT |
| 2023-04-17 | P00097 | Funding only | $67.0K | TERMINAL FLIGHT DATA MANAGER |
| 2023-03-23 | P00096 | Funding only | $450.0K | TERMINAL FLIGHT DATA MANAGER |
| 2023-03-20 | P00095 | Administrative change | $0 | TERMINAL FLIGHT DATA MANAGER |
| 2023-02-27 | P00094 | Funding only | $12.70M | TERMINAL FLIGHT DATA MANAGER |
| 2023-02-23 | P00093 | Change order definitized | $0 | TERMINAL FLIGHT DATA MANAGER |
| 2023-02-21 | P00092 | Change order | $0 | TERMINAL FLIGHT DATA MANAGER |
| 2023-02-02 | P00091 | Change order definitized | $382.6K | TERMINAL FLIGHT DATA MANAGER |
| 2023-01-20 | P00090 | Change order | $4.35M | TERMINAL FLIGHT DATA MANAGER |
| 2022-12-19 | P00089 | Funding only | $517.6K | TERMINAL FLIGHT DATA MANAGER |
| 2022-12-08 | P00088 | Funding only | $2.32M | TERMINAL FLIGHT DATA MANAGER |
| 2022-12-05 | P00087 | Administrative change | $0 | TERMINAL FLIGHT DATA MANAGER |
| 2022-12-05 | P00086 | Administrative change | $0 | TERMINAL FLIGHT DATA MANAGER |
| 2022-10-20 | P00085 | Change order | $0 | TERMINAL FLIGHT DATA MANAGER |