FA231824FB012↗

NCS Technologies Inc received this contract from Fa2318 Aflcmc C3MK, Department of the Air Force: $4.51M obligated so far for it and telecom - compute: mainframe (hardware and perpetual license software). Its period of performance ended 2025-09-15.

Key facts · data as of Oct 25, 2026

Recipient
NCS Technologies Inc
Awarding agency
Department of the Air Force (Department of Defense)
Contracting office
Fa2318 Aflcmc C3MK (FA2318)
Obligated to date
$4.51M
Potential value
$4.51M
Ends
2025-09-15

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award FA231824FB012, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_FA231824FB012_9700_GS35F115DA_4732

THIS PROCUREMENT IS FOR THE ACQUISITION OF TWO FINISHED PRODUCTS. ITEM A, A TOWER WORKSTATION COMPLETE WITH ESSENTIAL PERIPHERALS AND ACCESSORIES AND ITEM B, AN EXTRA SOLID-STATE DRIVE (SSD), MIRRORING THE SPECIFICATIONS OF THOSE INCLUDED IN ITEM A.

Delivery Order · Department of the Air Force · to NCS Technologies Inc (UEI MDTGPS4LMMR5) · data as of 2026-10-25

Obligated to date$4.51M3 actions
Current value$4.51Mwith options exercised
Period2024-09-25 → 2025-09-15current end date

What it is

Product or service
IT and Telecom - Compute: Mainframe (Hardware and Perpetual License Software) (PSC 7B21)
Industry
Electronic Computer Manufacturing (NAICS 334111)
Contracting office
Fa2318 Aflcmc C3MK (FA2318)
Competition
Full and open competition · 8 offers received
Set-aside
Small business
Pricing
Firm fixed price
How it was bought
GSA Schedule · under GS35F115DA
Where the work is
Middlesex, MA · district MA-05

Obligations by fiscal year

FY2024$4.51M
FY2025$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

3 actions since 2024-09-27. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2025-08-29P00002Administrative change$0THIS PROCUREMENT IS FOR THE ACQUISITION OF TWO FINISHED PRODUCTS. ITEM A, A TOWER WORKSTATION COMPLETE WITH ESSENTIAL PERIPHERALS AND ACCESSORIES AND ITEM B, AN EXTRA SOLID-STATE DRIVE (SSD), MIRRORING THE SPECIFICATIONS OF THOSE INCLUDED IN ITEM A.
2025-04-10P00001Administrative change$0THIS PROCUREMENT IS FOR THE ACQUISITION OF TWO FINISHED PRODUCTS. ITEM A, A TOWER WORKSTATION COMPLETE WITH ESSENTIAL PERIPHERALS AND ACCESSORIES AND ITEM B, AN EXTRA SOLID-STATE DRIVE (SSD), MIRRORING THE SPECIFICATIONS OF THOSE INCLUDED IN ITEM A.
2024-09-270$4.51MTHIS PROCUREMENT IS FOR THE ACQUISITION OF TWO FINISHED PRODUCTS. ITEM A, A TOWER WORKSTATION COMPLETE WITH ESSENTIAL PERIPHERALS AND ACCESSORIES AND ITEM B, AN EXTRA SOLID-STATE DRIVE (SSD), MIRRORING THE SPECIFICATIONS OF THOSE INCLUDED IN ITEM A.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗