THE WORK INCLUDES INSTALLATION OF ELECTRICAL INFRASTRUCTURE REQUIRED FOR ELECTRIC VEHICLE CHARGING STATIONS AT SEVERAL LOCATIONS ACROSS JBSA. THE WORK WILL TAKE PLACE FROM THE PRIMARY OVERHEAD POWER LINES TO THE DESIGNATED LOCATIONS.
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
2 actions since 2024-09-25. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-08-27 | P00001 | Terminated for convenience | -$9.14M | THE WORK INCLUDES INSTALLATION OF ELECTRICAL INFRASTRUCTURE REQUIRED FOR ELECTRIC VEHICLE CHARGING STATIONS AT SEVERAL LOCATIONS ACROSS JBSA. THE WORK WILL TAKE PLACE FROM THE PRIMARY OVERHEAD POWER LINES TO THE DESIGNATED LOCATIONS. |
| 2024-09-25 | 0 | $9.91M | THE WORK INCLUDES INSTALLATION OF ELECTRICAL INFRASTRUCTURE REQUIRED FOR ELECTRIC VEHICLE CHARGING STATIONS AT SEVERAL LOCATIONS ACROSS JBSA. THE WORK WILL TAKE PLACE FROM THE PRIMARY OVERHEAD POWER LINES TO THE DESIGNATED LOCATIONS. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗