FA452825F0053↗
Mattson Construction Co received this contract from Fa4528 5 Cons, Department of the Air Force: $802.9K obligated so far for construction of missile system facilities. Its period of performance ended 2026-11-13.
Key facts · data as of Nov 10, 2026
- Recipient
- Mattson Construction Co
- Awarding agency
- Department of the Air Force (Department of Defense)
- Contracting office
- Fa4528 5 Cons (FA4528)
- Obligated to date
- $802.9K
- Potential value
- $1.43M
- Ends
- 2026-11-13
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 10, 2026.
Cite this page: SpendQuery, Award FA452825F0053, data as of Nov 10, 2026, https://spendquery.com/award?id=CONT_AWD_FA452825F0053_9700_FA452820D0002_9700
Mattson Construction Co: all federal awards · Department of Defense: spending · Fa4528 5 Cons: what it buys · The follow-on: recompete brief
PROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH.
Up for re-bid: ends 2026-11-13. Recompete brief →
What it is
- Product or service
- Construction of Missile System Facilities (PSC Y1BF)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Fa4528 5 Cons (FA4528)
- Competition
- Full and open after exclusion of sources · 2 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under FA452820D0002
- Where the work is
- Ward, ND · district ND-00
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
4 actions since 2025-09-11. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-15 | P00003 | Administrative change | $0 | PROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH. |
| 2026-04-30 | P00002 | Supplemental agreement (work within scope) | $0 | PROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH. |
| 2025-09-24 | P00001 | Option exercised | $177.8K | PROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH. |
| 2025-09-11 | 0 | $625.1K | PROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-10). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗