FA452825F0053↗

Mattson Construction Co received this contract from Fa4528 5 Cons, Department of the Air Force: $802.9K obligated so far for construction of missile system facilities. Its period of performance ended 2026-11-13.

Key facts · data as of Nov 10, 2026

Recipient
Mattson Construction Co
Awarding agency
Department of the Air Force (Department of Defense)
Contracting office
Fa4528 5 Cons (FA4528)
Obligated to date
$802.9K
Potential value
$1.43M
Ends
2026-11-13

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Nov 10, 2026.

Cite this page: SpendQuery, Award FA452825F0053, data as of Nov 10, 2026, https://spendquery.com/award?id=CONT_AWD_FA452825F0053_9700_FA452820D0002_9700

PROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH.

Delivery Order · Department of the Air Force · to Mattson Construction Co (UEI KGJLDUL5QU79) · data as of 2026-11-10

Obligated to date$802.9K4 actions
Current value$802.9Kwith options exercised
Potential value$1.43Mif every option is used
Period2025-10-07 → 2026-11-13current end date

Up for re-bid: ends 2026-11-13. Recompete brief →

What it is

Product or service
Construction of Missile System Facilities (PSC Y1BF)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
Fa4528 5 Cons (FA4528)
Competition
Full and open after exclusion of sources · 2 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under FA452820D0002
Where the work is
Ward, ND · district ND-00

Obligations by fiscal year

FY2025$802.9K
FY2026$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

4 actions since 2025-09-11. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-15P00003Administrative change$0PROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH.
2026-04-30P00002Supplemental agreement (work within scope)$0PROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH.
2025-09-24P00001Option exercised$177.8KPROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH.
2025-09-110$625.1KPROVIDE ALL PLANT, LABOR, EQUIPMENT, SUPERVISION, SERVICES, FUEL, AND MATERIALS NECESSARY TO REMOVE AND REPAIR THE EXISTING CENTER MAINTENANCE RAIL, BASE PLATE, TURNTABLE ASSEMBLY, AND DEMOLISH AND EXCAVATE THE CONCRETE SLAB AND SOIL BENEATH.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-11-10). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗