FA820624C0002↗

Beaver Aerospace & Defense, Inc. received this contract from Fa8206 Afsc Pzaca (Icbm), Department of the Air Force: $19.10M obligated so far for electrical and electronic assemblies, boards, cards, and associated hardware. It runs to 2029-03-09.

Key facts · data as of Oct 25, 2026

Recipient
Beaver Aerospace & Defense, Inc.
Awarding agency
Department of the Air Force (Department of Defense)
Contracting office
Fa8206 Afsc Pzaca (Icbm) (FA8206)
Obligated to date
$19.10M
Potential value
$36.02M
Ends
2029-03-09

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award FA820624C0002, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_FA820624C0002_9700_-NONE-_-NONE-

STARTUP, FIRST ARTICLE, PRODUCTION OF FLYWHEEL MODULE.

Definitive Contract · Department of the Air Force · to Beaver Aerospace & Defense, Inc. (UEI C94KLMMN1WB3) · data as of 2026-10-25

Obligated to date$19.10M7 actions
Current value$19.10Mwith options exercised
Potential value$36.02Mif every option is used
Period2024-09-30 → 2029-03-09current end date

What it is

Product or service
Electrical and Electronic Assemblies, Boards, Cards, and Associated Hardware (PSC 5998)
Industry
Other Aircraft Parts and Auxiliary Equipment Manufacturing (NAICS 336413)
Contracting office
Fa8206 Afsc Pzaca (Icbm) (FA8206)
Competition
Not competed · 1 offer received
Pricing
Firm fixed price
How it was bought
Standalone contract
Solicitation
FA820624R0117
Where the work is
Wayne, MI · district MI-12

Obligations by fiscal year

FY2024$877.9K
FY2025$0
FY2026$18.22M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

7 actions since 2024-09-25. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-21P00006Administrative change$0STARTUP, FIRST ARTICLE, PRODUCTION OF FLYWHEEL MODULE.
2026-07-16P00005Administrative change$0STARTUP, FIRST ARTICLE, PRODUCTION OF FLYWHEEL MODULE.
2026-03-19P00004Administrative change$0STARTUP, FIRST ARTICLE, PRODUCTION OF FLYWHEEL MODULE.
2026-03-09P00001Option exercised$18.22MSTARTUP, FIRST ARTICLE, PRODUCTION OF FLYWHEEL MODULE.
2025-08-12P00003Administrative change$0STARTUP, FIRST ARTICLE, PRODUCTION OF FLYWHEEL MODULE.
2025-07-30P00002Administrative change$0STARTUP, FIRST ARTICLE, PRODUCTION OF FLYWHEEL MODULE.
2024-09-250$877.9KSTARTUP, FIRST ARTICLE, PRODUCTION OF FLYWHEEL MODULE.