Putting the award page together from the records…
Putting the award page together from the records…
DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION
Up for re-bid: ends 2026-11-02. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
18 actions since 2025-02-13. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-15 | P00017 | Supplemental agreement (work within scope) | $3.00M | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2026-06-02 | P00016 | Administrative change | $0 | NEXT GENERATION ADAPTIVE PROPULSION PROGRAM |
| 2026-04-22 | P00015 | Funding only | $29.07M | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2026-04-10 | P00014 | Supplemental agreement (work within scope) | $0 | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2026-02-17 | P00013 | Funding only | $29.50M | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2026-01-23 | P00012 | Funding only | $7.00M | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2025-12-19 | P00011 | Funding only | $21.00M | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2025-12-03 | P00010 | Supplemental agreement (work within scope) | $0 | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2025-11-18 | P00009 | Funding only | $62.50M | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2025-09-23 | P00008 | Funding only | $14.8K | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2025-09-17 | P00007 | Funding only | $1.25M | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2025-09-08 | P00006 | Funding only | $3.03M | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-05). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| 2025-08-11 | P00005 | Funding only | $24.00M | SUBJECT: INCREMENTAL FUNDING MODIFICATION CHANGE IN PRICE: $0.00 CHANGE IN OBLIGATION: $24,000,000.00 PCO EMAIL: [email protected] |
| 2025-07-01 | P00004 | Funding only | $25.00M | SUBJECT: INCREMENTAL FUNDING MODIFICATION CHANGE IN PRICE: $0.00CHANGE IN OBLIGATION: $25,000,000.00PCO EMAIL: [email protected] |
| 2025-06-09 | P00003 | Funding only | $17.43M | SUBJECT: INCREMENTAL FUNDING MODIFICATION CHANGE IN PRICE: $0.00CHANGE IN OBLIGATION: $17,427,029.00PCO EMAIL: [email protected] |
| 2025-03-13 | P00002 | Supplemental agreement (work within scope) | $200.0K | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2025-02-28 | P00001 | Administrative change | $0 | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |
| 2025-02-13 | 0 | $92.00M | DO3 - ENGINE BUILD, TEST, MATURATION AND INTEGRATION |