FA863418C2698↗
The Boeing Company received this contract from Fa8634 Aflcmc Waqk F15, Department of the Air Force: $39.96M obligated so far for aircraft, fixed wing. It runs to 2026-12-31.
Key facts · data as of Oct 25, 2026
- Recipient
- The Boeing Company
- Awarding agency
- Department of the Air Force (Department of Defense)
- Contracting office
- Fa8634 Aflcmc Waqk F15 (FA8634)
- Obligated to date
- $39.96M
- Potential value
- $170.56M
- Ends
- 2026-12-31
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award FA863418C2698, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_FA863418C2698_9700_-NONE-_-NONE-
The Boeing Company: all federal awards · Department of Defense: spending · Fa8634 Aflcmc Waqk F15: what it buys · The follow-on: recompete brief
ACAT II, F-15, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION
Up for re-bid: ends 2026-12-31. Recompete brief →
What it is
- Product or service
- Aircraft, Fixed Wing (PSC 1510)
- Industry
- Aircraft Manufacturing (NAICS 336411)
- Contracting office
- Fa8634 Aflcmc Waqk F15 (FA8634)
- Competition
- Not competed · 1 offer received
- Pricing
- Cost plus fixed fee
- How it was bought
- Standalone contract
- Where the work is
- Saint Louis, MO · district MO-01
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
28 subawards totaling $43.08M (107.8% of what was obligated), as The Boeing Company reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Resideo Technologies, Inc. | $16.25M | 9 | AZ | 2023-05-24 | 2024-03-14 |
| Honeywell International Inc. | $13.43M | 5 | AZ | 2022-11-22 | 2023-03-31 |
| Pip Manufacturing, Inc. | $12.10M | 8 | AZ | 2024-04-08 | 2026-03-03 |
| L3Harris Technologies, Inc. | $438.6K | 2 | GA | 2023-11-12 | 2024-07-24 |
| Huneed Technologies Co., LTD. | $406.6K | 1 | 2023-05-15 | 2023-05-15 | |
| Elbit Systems LTD | $285.6K | 1 | TX | 2023-04-03 | 2023-04-03 |
| Fine Laboratories, Inc. | $184.1K | 2 | MO | 2023-07-26 | 2024-06-04 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2024-03-14 | Honeywell International Inc. | $8.51M | SYSTEMS |
| 2025-11-07 | Honeywell International Inc. | $5.10M | SYSTEMS |
| 2026-03-03 | Honeywell International Inc. | $4.41M | SYSTEMS |
| 2022-11-22 | Honeywell International Inc. | $3.39M | SYSTEMS |
| 2023-07-14 | Honeywell International Inc. | $3.17M | SYSTEMS |
| 2023-01-26 | Honeywell International Inc. | $3.03M | SYSTEMS |
| 2023-01-26 | Honeywell International Inc. | $3.03M | SYSTEMS |
| 2023-03-31 | Honeywell International Inc. | $2.00M | SYSTEMS |
| 2023-03-29 | Honeywell International Inc. | $1.98M | SYSTEMS |
| 2023-06-15 | Honeywell International Inc. | $1.33M | SYSTEMS |
| 2024-04-08 | Honeywell International Inc. | $1.18M | SYSTEMS |
| 2023-11-02 | Honeywell International Inc. | $958.2K | SYSTEMS |
| 2025-11-07 | Honeywell International Inc. | $763.0K | SYSTEMS |
| 2023-09-05 | Honeywell International Inc. | $750.0K | AVIONICS |
| 2023-08-31 | Honeywell International Inc. | $721.0K | SYSTEMS |
| 2023-05-24 | Honeywell International Inc. | $420.9K | SYSTEMS |
| 2023-05-15 | Huneed Technologies Co., LTD. | $406.6K | SYSTEMS |
| 2023-11-12 | L3Harris Technologies, Inc. | $394.3K | SYSTEMS |
| 2024-04-23 | Honeywell International Inc. | $336.4K | SYSTEMS |
| 2023-04-03 | Elbitamerica, Inc. | $285.6K | NON PRODUCTION |
| 2023-12-05 | Honeywell International Inc. | $213.5K | SYSTEMS |
| 2026-03-03 | Honeywell International Inc. | $187.0K | SYSTEMS |
| 2023-12-14 | Honeywell International Inc. | $173.2K | SYSTEMS |
| 2023-07-26 | Fine Laboratories, Inc. | $96.6K | COMMON AEROSPACE COMMODITIES |
| 2024-06-04 | Fine Laboratories, Inc. | $87.4K | COMMON AEROSPACE COMMODITIES |
Every action
37 actions since 2022-10-06. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-01-06 | P00070 | Supplemental agreement (work within scope) | $11.15M | F-15 ADVANCED DISPLAY CORE PROCESSOR II |
| 2025-09-30 | P00071 | Administrative change | $0 | F-15 ADVANCED DISPLAY CORE PROCESSOR II (ADCP II) |
| 2025-09-29 | P00069 | Supplemental agreement (work within scope) | $10.01M | F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II ICS_FSR P6&7 |
| 2025-09-18 | P00068 | Supplemental agreement (work within scope) | -$12.83M | F-15 ADVANCED DISPLAY CORE PROCESSOR II |
| 2025-07-31 | P00067 | Supplemental agreement (work within scope) | $0 | ADVANCED DISPLAY CORE PROCESSOR II |
| 2025-06-30 | P00066 | Supplemental agreement (work within scope) | $502.0K | F-15 ADVANCED DISPLAY CORE PROCESSOR II |
| 2025-04-16 | P00065 | Supplemental agreement (work within scope) | $0 | F-15 ADVANCED DISPLAY CORE PROCESSOR II |
| 2024-12-05 | P00064 | Option exercised | $193.3K | ACAT II, F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2024-11-21 | P00063 | Supplemental agreement (work within scope) | $1.35M | ACAT II, F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2024-09-27 | P00062 | Supplemental agreement (work within scope) | -$555.0K | ACAT II, F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2024-07-31 | P00061 | Supplemental agreement (work within scope) | $0 | ACAT II, F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2024-06-06 | P00060 | Supplemental agreement (work within scope) | $2.76M | ACAT II F-15 ADVANCED DISPLAY CORE PROCESSOR ADCP II PRODUCTION |
| 2024-06-06 | P00060 | Supplemental agreement (work within scope) | -$2.80M | ACAT II F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2024-02-01 | PZ0059 | Change order definitized | $16.84M | ACAT II F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2024-02-01 | PZ0059 | Change order definitized | $2.06M | ACAT II F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2024-01-29 | P00058 | Supplemental agreement (work within scope) | -$106.4K | ACAT II F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2024-01-29 | P00058 | Supplemental agreement (work within scope) | -$8.19M | ACAT II F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2024-01-29 | P00058 | Supplemental agreement (work within scope) | -$171.2K | ACAT II F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-12-19 | P00057 | Supplemental agreement (work within scope) | $127.9K | F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-11-30 | P00056 | Supplemental agreement (work within scope) | $5.48M | F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-11-30 | P00056 | Supplemental agreement (work within scope) | $1.37M | F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-11-16 | P00055 | Supplemental agreement (work within scope) | $0 | F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-10-12 | P00054 | Funding only | $0 | F-15, ACAT II, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-09-25 | P00053 | Supplemental agreement (work within scope) | $120.7K | F-15 ADVANCED DISPLAY CORE PROCESSOR (ADCP) II |
| 2023-09-13 | P00052 | Supplemental agreement (work within scope) | $248.2K | F-15, ACAT II, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-07-27 | P00051 | Supplemental agreement (work within scope) | $0 | F-15, ACAT II, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-07-06 | P00050 | Supplemental agreement (work within scope) | $3.39M | F-15, ACAT II, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-05-19 | P00049 | Supplemental agreement (work within scope) | $0 | F-15 ADVANCED DISPLAY CORE PROCESSOR II PRODUCTION |
| 2023-05-08 | P00048 | Supplemental agreement (work within scope) | $0 | F-15/ADVANCED DISPLAY CORE PROCESSOR II PRODUCTION |
| 2023-04-12 | P00047 | Supplemental agreement (work within scope) | $6.89M | F-15/ADVANCED DISPALY CORE PROCESSOR II PRODUCTION |
| 2023-04-12 | P00047 | Supplemental agreement (work within scope) | $2.04M | F-15/ADVANCED DISPLAY CORE PROCESSOR II PRODUCTION |
| 2023-02-28 | P00046 | Supplemental agreement (work within scope) | $0 | F-15, ACAT II, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-02-06 | P00045 | Supplemental agreement (work within scope) | $72.2K | ADCP II, F-15, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2023-01-23 | P00044 | Supplemental agreement (work within scope) | $0 | ACAT II, F-15, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2022-12-21 | P00043 | Supplemental agreement (work within scope) | $0 | ACAT II, F-15, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2022-10-31 | P00042 | Supplemental agreement (work within scope) | $0 | ACAT II, F-15, ADVANCED DISPLAY CORE PROCESSOR (ADCP) II PRODUCTION |
| 2022-10-06 | P00041 | Supplemental agreement (work within scope) | $0 | F-15 CLIN 0009 AND 2001 SECTION F UPDATE |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗