FA877223F0004↗
World Wide Technology LLC received this contract from Fa8772 Aflcmc Hnik, Department of the Air Force: $13.22M obligated so far for it and telecom - other data center facilities products (hardware and perpetual license software). Its period of performance ended 2025-06-30.
Key facts · data as of Oct 23, 2026
- Recipient
- World Wide Technology LLC
- Awarding agency
- Department of the Air Force (Department of Defense)
- Contracting office
- Fa8772 Aflcmc Hnik (FA8772)
- Obligated to date
- $13.22M
- Potential value
- $13.22M
- Ends
- 2025-06-30
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award FA877223F0004, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_FA877223F0004_9700_NNG15SC55B_8000
World Wide Technology LLC: all federal awards · Department of Defense: spending · Fa8772 Aflcmc Hnik: what it buys
BITI RECAP
What it is
- Product or service
- IT and Telecom - Other Data Center Facilities Products (Hardware and Perpetual License Software) (PSC 7C21)
- Industry
- Other Computer Related Services (NAICS 541519)
- Contracting office
- Fa8772 Aflcmc Hnik (FA8772)
- Competition
- Full and open competition · 6 offers received
- Pricing
- Firm fixed price
- How it was bought
- GWAC · under SEWP V (NNG15SC55B)
- Solicitation
- FA877223Q0005
- Where the work is
- Montgomery, AL · district AL-02
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
10 actions since 2023-07-19. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-12-23 | P00009 | Administrative change | $0 | TO PROCURE EQUIPMENT AND SUPPORT TO SATISFY AFSNS BITI RECAPITALIZATION WIRED INSTALLATIONS. |
| 2025-06-27 | P00008 | Additional work (new agreement) | $277.2K | TO PROCURE EQUIPMENT AND SUPPORT TO SATISFY AFSNS BITI RECAPITALIZATION WIRED INSTALLATIONS. |
| 2025-05-04 | P00007 | Funding only | $40.5K | TO PROCURE EQUIPMENT AND SUPPORT TO SATISFY AFSNS BITI RECAPITALIZATION WIRED INSTALLATIONS. |
| 2025-02-21 | P00006 | Funding only | $279.0K | TO PROCURE EQUIPMENT AND SUPPORT TO SATISFY AFSNS BITI RECAPITALIZATION WIRED INSTALLATIONS. |
| 2024-09-20 | P00005 | Supplemental agreement (work within scope) | $1.39M | TO PROCURE EQUIPMENT AND SUPPORT TO SATISFY AFSNS BITI RECAPITALIZATION WIRED INSTALLATIONS. |
| 2024-08-05 | P00004 | Funding only | $1.20M | TO PROCURE EQUIPMENT AND SUPPORT TO SATISFY AFSNS BITI RECAPITALIZATION WIRED INSTALLATIONS. |
| 2024-03-18 | P00003 | Change order | $749.9K | BITI RECAP |
| 2023-10-26 | P00002 | Option exercised | $5.02M | BITI RECAP |
| 2023-07-27 | P00001 | Funding only | $1.19M | BITI RECAP |
| 2023-07-19 | 0 | $3.07M | BITI RECAP |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗