Lockheed Martin Corp received this contract from Fa8810 Space Sensing Ssc/Snk, Department of the Air Force: $3.34B obligated so far for national defense r&d services; atomic energy defense activities; r&d administrative expenses. It runs to 2029-07-31.
Key facts · data as of Oct 21, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 21, 2026.
Cite this page: SpendQuery, Award FA881018C0005, data as of Oct 21, 2026, https://spendquery.com/award?id=CONT_AWD_FA881018C0005_9700_-NONE-_-NONE-
Lockheed Martin Corp: all federal awards · Department of Defense: spending · Fa8810 Space Sensing Ssc/Snk: what it buys
NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
860 subawards totaling $1.02B (30.5% of what was obligated), as Lockheed Martin Corp reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Rockwell Collins Australia Pty Limited | $394.51M | 11 | CA | 2023-09-07 | 2025-02-27 |
| Northrop Grumman Corporation | $219.57M | 15 | CA, CO | 2022-11-04 | 2025-02-13 |
| RTX Corp | $201.03M | 6 | CA | 2022-11-28 | 2023-07-31 |
| Seakr Engineering, LLC | $47.19M | 5 | CO | 2022-11-14 | 2024-10-04 |
| Centil LLC | $21.39M | 38 | CO | 2022-10-12 | 2025-01-23 |
| Sterling Computers Corporation | $16.46M | 57 | SD | 2022-11-11 | 2025-02-26 |
| Prime Technical Services Inc | $7.85M | 19 | GA | 2022-10-18 | 2025-01-14 |
| Epoch Concepts LLC | $6.20M | 14 | CO | 2022-10-24 | 2024-12-05 |
| Constant Technologies Inc | $5.81M | 8 | RI | 2022-12-14 | 2025-01-10 |
| Caribou Thunder, LLC | $5.20M | 16 | WI | 2022-10-10 | 2024-12-05 |
| Beacon Hill Solutions Group, LLC | $4.97M | 14 | MA | 2023-04-11 | 2025-02-20 |
| Ennoble First Incorporated | $4.74M | 20 | VA | 2022-11-09 | 2025-02-20 |
| Apex Systems, LLC | $4.32M | 16 | VA | 2023-03-24 | 2025-01-27 |
| World Wide Technology Holding Co LLC | $4.17M | 8 | MO | 2023-04-03 | 2024-09-09 |
| Probo Data Group Inc | $4.08M | 2 | CA | 2022-11-15 | 2024-11-14 |
| General Dynamics Corp | $4.07M | 8 | AZ, MA | 2022-10-18 | 2024-12-13 |
| Eagle Tech Limited | $3.48M | 17 | CO | 2022-12-19 | 2025-02-20 |
| G. C. Micro Corporation | $3.21M | 19 | CA | 2022-12-08 | 2025-02-19 |
| L3Harris Technologies, Inc | $3.14M | 6 | CA, WA | 2023-01-19 | 2024-12-18 |
| Kaztronix LLC | $3.10M | 18 | VA | 2023-02-22 | 2025-01-30 |
| Moog Inc | $2.73M | 7 | NY, VA | 2022-10-07 | 2024-07-29 |
| Kratos S1, Inc. | $2.38M | 1 | CO | 2023-12-15 | 2023-12-15 |
| Fahrenheit IT, Inc | $2.09M | 8 | CO | 2022-10-21 | 2023-10-09 |
| Information Technology Engineering, LLC | $1.87M | 8 | CO | 2023-11-29 | 2025-01-20 |
| Stellar Solutions Inc | $1.86M | 2 | CA | 2023-08-14 | 2025-02-12 |
The 25 largest of 210; the rest are on USAspending.gov.
| Date | To | Amount | For |
|---|---|---|---|
| 2024-10-21 | Raytheon Company | $165.00M | PHASE 2.1B COST PHASE 2.1B FEE |
| 2023-05-31 | Northrop Grumman Systems Corporation | $131.51M | ##700LSBANL2NG##NC3 SPECIAL STUDIES PHASE 1 GEO MISSION PAYLOAD COST |
| 2023-12-20 | Raytheon Company | $91.64M | PHASE 1 AND 2.0 GEO MPL #1 COST |
| 2022-11-28 | Raytheon Company | $84.98M | PHASE 1 AND 2.0 GEO MIPL #1 FEE PHASE 1 AND 2.0 GEO MPL #1 COST |
| 2022-11-04 | Northrop Grumman Systems Corporation | $80.66M | PHASE 1 GEO MISSION PAYLOAD COST |
| 2023-05-18 | Raytheon Company | $75.11M | PHASE 1 AND 2.0 GEO MPL #1 COST SPECIAL STUDIES NC3 PHASE 2.0 |
| 2025-02-27 | Raytheon Company | $60.25M | PHASE 1 AND 2.0 GEO MIPL #1 FEE PHASE 1 AND 2.0 GEO MPL #1 COST PHASE 2.0 GEO MPL #2 COST |
| 2024-07-18 | Raytheon Company | $54.78M | PHASE 1 AND 2.0 GEO MPL #1 COST PHASE 2.0 GEO MPL #2 COST |
| 2023-07-28 | Raytheon Company | $40.82M | PHASE 2.1A COST PHASE 2.1A FEE |
| 2023-07-28 | Seakr Engineering, LLC | $28.39M | PDF FLIGHT 2 PDF FLIGHT 3 |
| 2023-09-07 | Raytheon Company | $24.01M | PHASE 1 AND 2.0 GEO MIPL #1 FEE PHASE 1 AND 2.0 GEO MPL #1 COST PHASE 2.0 GEO MPL #2 COST PHASE 2.0 GEO MPL #2 FEE |
| 2024-10-04 | Seakr Engineering, LLC | $12.73M | ASSY MODULE BACKPLANE FLT OPIR PDF ASSY MODULE BELLONA SBC FLT OPIR PDF ASSY MODULE I/O FLT OPIR PDF ASSY MODULE POWER FLT OPIR PDF. PDF FLIGHT 3 TOP ASSY KIT FLT |
| 2022-11-14 | Seakr Engineering, LLC | $4.07M | PAYLOAD DATA FORMATTER COST |
| 2024-06-04 | Constant Technologies Inc | $3.70M | ##BEL-F1DN004MOD-KM-4##BELKIN 4-PORT MOD ##CABLE BUNDLE ESTIMATE LARGE##CABLE EST ##COV-CLR-DM3-3P-1KB##FIBER CABLE DUPLE ##COV-CLR-LC-MMFPC-10##CLEERLINE FIBER L ##CRE-CP4N##4-SERIES(T) CONTROL SYSTEM… |
| 2022-11-15 | Probo Data Group Inc | $3.30M | FFP - EVDATA PRO M&S T&M - EVDATA PRO SW DEVELOPMENT |
| 2023-02-07 | Northrop Grumman Systems Corporation | $2.90M | PHASE 1 & 2.0 GEO MISSION PAYLOAD FEE PHASE 1 GEO MISSION PAYLOAD COST |
| 2024-10-31 | Northrop Grumman Systems Corporation | $2.90M | CLIN 0001 COST FEE POOL CLIN 0001 SCHEDULE FEE POOL CLIN 0001 SEIT COST CLIN 0006 COST FEE POOL CLIN 0006 GROUND COST CLIN 0006 SCHEDULE FEE POOL |
| 2023-05-23 | Epoch Concepts LLC | $2.60M | ##LS220## RH LEARNING SUBSCRIPTION STD RH OPENSHIFT PLTFM PLUS STD 3 YRS SPRT SW ENT LINUX VIRT DC SMT MGMT+SATELLITE SW RH ANSIBLE AUTOMATION PLTFM 3 YR |
| 2023-03-28 | L3 Technologies, Inc. | $2.44M | ##700LLBKRD2CT## CTP COST CTP FEE |
| 2023-12-15 | Kratos S1, Inc. | $2.38M | ##700LLBKND2RT##CSSTE TRAINING & SUPPORT |
| 2023-04-26 | Prime Technical Services Inc | $2.07M | NGG LABOR |
| 2023-04-12 | Moog Inc. | $1.89M | MSADA. |
| 2024-12-10 | Centil LLC | $1.86M | DEVSECOPS SOFTWARE LABOR NGG LABOR SWE NGG LABOR SYSTEMS ENGINEERING NGG NETWORK ENGINEERING LABOR NGG RELAY LAB P2 LABOR |
| 2022-12-14 | Constant Technologies Inc | $1.81M | ##9300L-24P-4X-A##M430052GPOE+ MAN ##AMX-FG2106-04##NX4200 NETLINX NX INTE ##AMX-FG5969-47##10IN MODERO TABLETOP TO ##APC-AP8841##RACK PDU 2G METERED ZERO ##BIA-TESIRAFORTE DAN VT##FIXED I/O DSP ##CABLE BUNDLE… |
| 2023-11-09 | Honeywell International Inc. | $1.75M | EARTH DECK BRACKET #1 NEXT GEN PAYLOAD EARTH DECK BRACKET #2 NEXT GEN PAYLOAD EPP BRACKET #1 NEXT GEN PAYLOAD ISOLATI EPP BRACKET #2 NEXT GEN PAYLOAD ISOLATI EPP BRACKET #3 NEXT GEN PAYLOAD ISOLATI EPP BRACKET #4… |
114 actions since 2022-10-07. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-26 | P00195 | Supplemental agreement (work within scope) | $1.01M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1 |
| 2026-06-04 | P00196 | Administrative change | $6.16M | NEXT GENERATION OVERHEAD PERSISTENT INFARED GEOSYNCHRONIS |
| 2026-05-19 | P00194 | Funding only | $6.08M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2026-04-16 | P00192 | Supplemental agreement (work within scope) | $3.91M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2026-04-13 | P00188 | Supplemental agreement (work within scope) | $17.19M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2026-04-09 | P00190 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS. |
| 2026-04-03 | P00191 | Funding only | $4.68M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2026-03-23 | P00189 | Funding only | $150.60M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2026-03-16 | P00187 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1. |
| 2026-03-06 | P00186 | Option exercised | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1 |
| 2026-02-10 | P00183 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1. |
| 2026-01-21 | P00184 | Funding only | $3.35M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1 |
| 2026-01-14 | P00182 | Funding only | $6.50M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1 |
| 2026-01-12 | P00181 | Administrative change | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1 |
| 2025-12-22 | P00180 | Supplemental agreement (work within scope) | $6.49M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-12-10 | P00170 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-12-08 | P00179 | Funding only | $44.11M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-12-02 | P00178 | Funding only | $120.00M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-12-02 | P00178 | Funding only | $35.04M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-11-21 | P00177 | Funding only | $34.50M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-11-14 | P00176 | Funding only | $9.66M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED SATELLITES - GEOSYNCHRONOUS, SPACE VEHICLES 1 & 2 |
| 2025-09-30 | P00155 | Supplemental agreement (work within scope) | $14.77M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-09-25 | P00174 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1 |
| 2025-09-17 | P00175 | Funding only | $7.42M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1 |
| 2025-09-10 | P00172 | Supplemental agreement (work within scope) | $175.4K | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1 |
| 2025-08-18 | P00173 | Funding only | $35.36M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS EARTH ORBIT SPACE VEHICLE 1-3 PHASE 1 |
| 2025-08-12 | P00171 | Funding only | $106.2K | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-08-07 | P00168 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-08-07 | P00167 | Funding only | $2.42M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-07-29 | P00169 | Administrative change | $0 | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-07-21 | P00165 | Supplemental agreement (work within scope) | $300.0K | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-07-17 | P00161 | Administrative change | $0 | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-07-14 | P00166 | Funding only | $2.05M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-07-09 | P00162 | Funding only | $4.30M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-06-23 | P00164 | Funding only | $25.84M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-06-23 | P00163 | Funding only | $34.50M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-06-03 | P00159 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-05-28 | P00160 | Funding only | $30.00M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2025-05-08 | P00153 | Supplemental agreement (work within scope) | $20.30M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-04-30 | P00158 | Funding only | $8.22M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-04-21 | P00157 | Funding only | $38.41M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-04-14 | P00156 | Funding only | $10.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-03-25 | P00154 | Funding only | $7.64M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-03-24 | P00146 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-02-20 | P00152 | Funding only | $16.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-02-05 | P00151 | Administrative change | $7.05M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-01-28 | P00150 | Funding only | $80.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2025-01-23 | P00149 | Supplemental agreement (work within scope) | $20.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-11-19 | P00148 | Supplemental agreement (work within scope) | $3.03M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-11-13 | P00143 | Administrative change | $15.49M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-11-08 | P00142 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-10-30 | P00147 | Funding only | $87.88M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-10-29 | P00140 | Supplemental agreement (work within scope) | $34.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-10-01 | P00141 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-09-16 | P00145 | Funding only | $13.60M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-09-09 | P00144 | Funding only | $37.90M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-08-21 | P00139 | Funding only | $11.46M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-08-08 | P00138 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-07-24 | P00128 | Funding only | $8.32M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-06-21 | P00127 | Supplemental agreement (work within scope) | $183.65M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS. |
| 2024-06-17 | P00137 | Supplemental agreement (work within scope) | $200.0K | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-05-28 | P00133 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-05-14 | P00136 | Funding only | $65.21M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-04-11 | P00135 | Funding only | $44.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-04-08 | P00134 | Funding only | $38.10M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-04-08 | P00132 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-03-25 | P00096 | Funding only | $3.96M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-03-22 | P00131 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-02-29 | P00129 | Supplemental agreement (work within scope) | $34.50M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-02-14 | P00130 | Funding only | $25.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-02-09 | P00126 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-01-30 | P00125 | Funding only | $9.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-01-25 | P00124 | Funding only | $51.81M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2024-01-23 | P00115 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-12-19 | P00123 | Funding only | $71.85M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-12-15 | P00122 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFARED GEOSYNCHONOUS |
| 2023-12-11 | P00121 | Funding only | $2.97M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-12-11 | P00121 | Funding only | $70.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-12-04 | P00119 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-11-30 | P00120 | Funding only | $16.90M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-11-30 | P00120 | Funding only | $8.29M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-11-29 | P00118 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-11-27 | P00117 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-11-21 | P00116 | Funding only | $15.39M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-11-21 | P00107 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-11-09 | P00114 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-11-01 | P00113 | Supplemental agreement (work within scope) | $2.00M | NEXT GERERANTION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-10-31 | P00112 | Funding only | $56.65M | NEXT GENERATION OVERHEAD INFRARED PERSISTENT GEOSYNCHRONOUS |
| 2023-10-19 | P00109 | Funding only | $7.11M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-09-21 | P00111 | Funding only | $73.2K | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-09-11 | P00110 | Funding only | $10.89M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-09-11 | P00110 | Funding only | $1.60M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-08-21 | P00108 | Funding only | $7.30M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-07-24 | P00106 | Funding only | $8.29M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-07-06 | P00105 | Funding only | $56.51M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-06-22 | P00104 | Funding only | $16.85M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-06-14 | P00103 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2023-06-02 | P00102 | Supplemental agreement (work within scope) | $28.73M | NEXT GENERATION GEOSYNCHRONOUS OVERHEAD PERSISTENT INFRARED |
| 2023-05-08 | P00101 | Supplemental agreement (work within scope) | $8.92M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-03-21 | P00099 | Funding only | $716.65M | NEXT GERNERATION OVERHEAD PERSISTENT INFRARED |
| 2023-03-21 | P00095 | Supplemental agreement (work within scope) | -$50.7K | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS_ATTACHMENT 2 AND 6 UPDATE |
| 2023-03-04 | P00100 | Supplemental agreement (work within scope) | $1.50M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED |
| 2023-03-02 | P00098 | Supplemental agreement (work within scope) | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2023-02-14 | P00097 | Funding only | $152.95M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS. |
| 2023-01-18 | P00094 | Funding only | $17.58M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS SATELLITE |
| 2023-01-12 | P00093 | Funding only | $100.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS SATELLITE SYSTEM |
| 2022-12-20 | P00092 | Funding only | $60.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2022-12-08 | P00091 | Funding only | $10.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2022-11-30 | P00089 | Funding only | $13.68M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2022-11-30 | P00089 | Funding only | $119.66M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2022-11-15 | PZ0087 | Change order definitized | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2022-10-31 | P00088 | Funding only | $130.00M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
| 2022-10-24 | P00086 | Administrative change | $0 | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHREONOUS |
| 2022-10-07 | P00085 | Funding only | $150.53M | NEXT GENERATION OVERHEAD PERSISTENT INFRARED GEOSYNCHRONOUS |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-21). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗