EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS.
Up for re-bid: ends 2027-06-30. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
9 actions since 2025-07-01. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-05-29 | P00008 | Supplemental agreement (work within scope) | $6.03M | EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS. |
| 2026-04-23 | P00007 | Funding only | $1.53M | EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS. |
| 2026-03-13 | P00006 | Funding only | $11.33M | EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS. |
| 2026-03-09 | P00005 | Administrative change | $2.86M | EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS. |
| 2025-12-03 | P00004 | Funding only | $4.67M | EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS. |
| 2025-09-02 | P00003 | Funding only | $5.08M | EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS. |
| 2025-08-07 | P00002 | Funding only | $327.5K | EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS. |
| 2025-07-11 | P00001 | Administrative change | -$6.2K | EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS. |
| 2025-07-01 | 0 | $8.25M | EFFORT REQUIRED FOR SEA-BASED WEAPON SYSTEMS (WS) GPI CAPABILITY DEVELOPMENT, INCLUDING CONCEPT DEVELOPMENT, STUDIES AND ANALYSES, REQUIREMENTS GENERATION, DESIGN SPECIFICATIONS ACROSS THE AEGIS WS, AND PARTICIPATION IN MEETINGS AND WORKING GROUPS. |