INR17PC00023↗
CDM Constructors Inc received this contract from Upper Colorado Regional Office, Bureau of Reclamation: $270.52M obligated so far for construction of water supply facilities. It runs to 2027-02-28, or to 2028-12-31 if every option is exercised.
Key facts · data as of Oct 25, 2026
- Recipient
- CDM Constructors Inc
- Awarding agency
- Bureau of Reclamation (Department of the Interior)
- Contracting office
- Upper Colorado Regional Office (140R40)
- Obligated to date
- $270.52M
- Potential value
- $364.04M
- Ends
- 2027-02-28
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award INR17PC00023, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_INR17PC00023_1425_-NONE-_-NONE-
CDM Constructors Inc: all federal awards · Department of the Interior: spending · Upper Colorado Regional Office: what it buys · The follow-on: recompete brief
POJOAQUE BASIN REGIONAL WATER SYSTEM IGF::OT::IGF
Up for re-bid: ends 2027-02-28. Recompete brief → · Y--EAST CANAL EFFICIENCY IMPROVEMENTS ↗
What it is
- Product or service
- Construction of Water Supply Facilities (PSC Y1NE)
- Industry
- Water and Sewer Line and Related Structures Construction (NAICS 237110)
- Contracting office
- Upper Colorado Regional Office (140R40)
- Competition
- Full and open competition · 5 offers received
- Pricing
- Firm fixed price
- How it was bought
- Standalone contract
- Solicitation
- R16PS00829
- Where the work is
- Santa Fe, NM · district NM-03
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
38 actions since 2022-12-15. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-09-18 | P00067 | Supplemental agreement (work within scope) | $88.3K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-09-16 | P00066 | Supplemental agreement (work within scope) | $105.2K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-09-16 | P00065 | Funding only | $2.22M | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-09-04 | P00064 | Supplemental agreement (work within scope) | $20.8K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-08-25 | P00063 | Supplemental agreement (work within scope) | $2.01M | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-08-07 | P00062 | Supplemental agreement (work within scope) | $1.95M | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-07-01 | P00061 | Supplemental agreement (work within scope) | $6.0K | EO 14398-POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-06-24 | P00060 | Supplemental agreement (work within scope) | -$290.7K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-06-04 | P00059 | Supplemental agreement (work within scope) | $694 | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-05-12 | P00058 | Supplemental agreement (work within scope) | $89.8K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-05-07 | P00057 | Supplemental agreement (work within scope) | $30.5K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-04-29 | P00056 | Supplemental agreement (work within scope) | $180.7K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-04-27 | P00055 | Supplemental agreement (work within scope) | $19.7K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-04-03 | P00054 | Supplemental agreement (work within scope) | $11.3K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-03-30 | P00053 | Supplemental agreement (work within scope) | $71.9K | POJOAQUE BASIN REGIONAL WATER SYSTEM PHASE I |
| 2026-01-06 | P00052 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE COR |
| 2025-09-10 | P00051 | Funding only | $25.21M | THE PURPOSE OF THIS MODIFICATION IS INCREMENTALLY FUND THE CONTRACT. |
| 2025-09-10 | P00050 | Supplemental agreement (work within scope) | $6.2K | THE PURPOSE OF THIS MODIFICATION IS FOR THE CONTRACTOR (CDM) TO PERFORM MUSEUM AND ARCHIVAL SERVICES AT THE TEWA CENTER. |
| 2025-08-18 | P00049 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS FOR THE CONTRACTOR (CDM) TO PERFORM A REDESIGN OF THE PBRWS DISTRIBUTION PIPELINE (REACH FWS46_SAN) TO GO AROUND THE NEW DEERTAIL HOUSING DEVELOPMENT. |
| 2025-07-28 | P00048 | Supplemental agreement (work within scope) | $29.2K | THE PURPOSE OF THIS MODIFICATION IS FOR THE CONTRACTOR (CDM) TO PERFORM A REDESIGN OF THE PBRWS DISTRIBUTION PIPELINE (REACH FWS46_SAN) TO GO AROUND THE NEW DEERTAIL HOUSING DEVELOPMENT. |
| 2025-07-03 | P00047 | Administrative change | $0 | CORRECT THE PERIOD OF PERFORMANCE DATES OF CLINS IN THE PRISM SYSTEM. |
| 2025-07-02 | P00046 | Supplemental agreement (work within scope) | $67.2K | ADDITIONAL VIBRATION MONITORING |
| 2025-05-16 | P00045 | Supplemental agreement (work within scope) | $290.7K | PERMANENT POWER |
| 2025-02-28 | P00044 | Supplemental agreement (work within scope) | $0 | CORRECT THE PERIOD OF PERFORMANCE OF VARIOUS CLINS |
| 2025-01-15 | P00043 | Administrative change | $62.50M | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND THE CONTRACT. |
| 2024-12-13 | P00042 | Supplemental agreement (work within scope) | $162.4K | THE PURPOSE OF THIS MODIFICATION IS TO COMPENSATE THE CONTRACTOR VIA AN (EQUITABLE ADJUSTMENT) FOR ADDITIONAL EXPENSES ASSOCIATED WITH THE DELAY OF THE GOVERNMENT TO EXECUTE THE BALANCE OF WORK BEFORE THE MEMBRANE SUPPLIER (WIGEN) PROPOSAL EXPIRED. |
| 2024-12-09 | P00041 | Supplemental agreement (work within scope) | $10.3K | THE PURPOSE OF THIS MODIFICATION IS TO OBTAIN RADIO LICENSES FOR THE POJOAQUE REGIONAL WATER REGIONAL WATER AUTHORITY UPON ITS FORMATION. |
| 2024-08-29 | P00040 | Supplemental agreement (work within scope) | $203.2K | THE PURPOSE OF THIS MODIFICATION IS TO IS TO COMPENSATE THE CONTRACTOR FOR ADDITIONAL EXPENSES ASSOCIATED WITH THE DIRECTION FROM RECLAMATION TO INSTALL PERMEANT POWER FROM JMEC'S (JEMEZ MOUNTAIN COOPERATIVE INC) SUBSTATION TO NM-502 AT ENTRADA |
| 2024-08-15 | P00039 | Funding only | $125.00M | THE PURPOSE OF THIS MODIFICATION IS TO INCREMENTALLY FUND THE CONTRACT. |
| 2024-08-15 | P00038 | Supplemental agreement (work within scope) | $25.8K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE MISCELLANEOUS DESIGN ALIGNMENT UPDATES INTO THE CONTRACT. |
| 2024-06-20 | P00037 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT THE PERIOD OF PERFORMANCE DATE OF CLIN 506 IN THE PRISM SYSTEM. THIS IS AN ADMINISTRATIVE MODIFICATION. |
| 2024-04-08 | P00036 | Administrative change | $0 | ADMINISTRATIVE MODIFICATION TO CORRECT THE PERIOD OF PERFORMANCE RECORDED IN THE CONTRACT WRITING SYSTEM (PRISM) USED BY THE BUREAU OF RECLAMATION. |
| 2024-03-01 | P00035 | Supplemental agreement (work within scope) | $56.0K | THE PURPOSE OF THIS MODIFICATION IS TO INTEGRATE DESIGN CHANGES SPECIFICALLY ELEVATION CHANGES TO THE SOUTH FOREBAY TANK AND ELEVATION CHANGES TO THE EL RANCHO PIPELINE ALIGNMENTS. |
| 2023-12-15 | P00034 | Supplemental agreement (work within scope) | $50.00M | PBRWS P00034 - BALANCE OF CONSTRUCTION |
| 2023-08-14 | P00033 | Administrative change | $0 | POJOAQUE BASIN REGIONAL WATER SYSTEM |
| 2023-03-15 | P00032 | Supplemental agreement (work within scope) | $0 | POJOAQUE BASIN REGIONAL WATER SYSTEM |
| 2023-02-09 | P00031 | Supplemental agreement (work within scope) | $447.6K | POJOAQUE BASIN REGIONAL WATER SYSTEM |
| 2022-12-15 | P00030 | Supplemental agreement (work within scope) | $0 | POJOAQUE BASIN REGIONAL WATER SYSTEM |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗