Lockheed Martin Corporation received this contract from Naval Air Systems Command, Department of the Navy: $21.35M obligated so far for aircraft, fixed wing. It runs to 2028-12-31.

Key facts · data as of Oct 25, 2026

Recipient
Lockheed Martin Corporation
Awarding agency
Department of the Navy (Department of Defense)
Contracting office
Naval Air Systems Command (N00019)
Obligated to date
$21.35M
Potential value
$28.88M
Ends
2028-12-31

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award N0001923F0656, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_N0001923F0656_9700_N0001923D0022_9700

THIS DELIVERY ORDER IS PLACING AN ORDER FOR THE DEVELOPMENT OF PRODUCTION ENGINEERING CHANGE PROPOSALS (ECPS), RETROFIT ENGINEERING RELEASE REPORTS (ERRS), LEVEL OF EFFORT (LOE) INVESTIGATIONS AND PROGRAM SUPPORT.

Delivery Order · Department of the Navy · to Lockheed Martin Corporation (UEI G4KDGE4JFFK7) · data as of 2026-10-25

Obligated to date$21.35M20 actions
Current value$28.88Mwith options exercised
Period2023-09-22 → 2028-12-31current end date

What it is

Product or service
Aircraft, Fixed Wing (PSC 1510)
Industry
Aircraft Manufacturing (NAICS 336411)
Contracting office
Naval Air Systems Command (N00019)
Competition
Not competed
Pricing
Cost plus fixed fee
How it was bought
Single-award IDIQ · under N0001923D0022
Solicitation
N0001922R0065
Where the work is
Tarrant, TX · district TX-12

Obligations by fiscal year

FY2023$11.20M
FY2024$3.82M
FY2025$3.35M
FY2026$2.97M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

20 actions since 2023-09-22. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-05-26P00019Supplemental agreement (work within scope)$2.89MFUND CLIN 7007 OVERRUN AND CLIN 5007 INCREMENTAL FUNDING.
2026-04-10P00018Administrative change$0CORRECT TOTALS ON SECTION A.
2026-03-26P00017Administrative change$0FUNDING & POP CHANGES.
2026-03-02P00016Administrative change$61.7KTHE PURPOSE OF THIS MODIFICATION IS TO ADDRESS THE CLIN 6002 OVERRUN.
2026-02-26P00015Additional work (new agreement)$0ADDITIONAL CLIN 5007 SCOPE
2026-01-30P00014Additional work (new agreement)$18.0KADD ASM SCOPE
2025-12-04P00013Administrative change$0DELIVERY DATE EXTENSION FOR CLINS 2002, 3007, AND 7007.
2025-09-25P00012Administrative change$0EXTENDED DELIVERY DATES.
2025-07-24P00011Additional work (new agreement)$100.9KEPIC 2 DO 1 LOE HOURS INCREASE
2025-06-23P00010Administrative change$0THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO EXTEND CLIN 3007/7007 FROM 6/30 TO 12/31.
2025-04-23P00009Funding only$84.5KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE OVERRUNNING FUNDING FOR CLINS 2001/6001
2025-03-12P00008Funding only$3.17MTHE PURPOSE OF THIS CONTRACT MODIFICATION IS TO ADD INCREMENTAL FUNDING TO CLIN 5007
2024-12-16P00007Administrative change$0EXTEND POP DATE AND CHANGE HOURS TO LOT
2024-11-14P00006Administrative change$0THIS DELIVERY ORDER IS PLACING AN ORDER FOR THE DEVELOPMENT OF PRODUCTION ENGINEERING CHANGE PROPOSALS (ECPS), RETROFIT ENGINEERING RELEASE REPORTS (ERRS), LEVEL OF EFFORT (LOE) INVESTIGATIONS AND PROGRAM SUPPORT.
2024-10-03P00005Administrative change$0THIS DELIVERY ORDER IS PLACING AN ORDER FOR THE DEVELOPMENT OF PRODUCTION ENGINEERING CHANGE PROPOSALS (ECPS), RETROFIT ENGINEERING RELEASE REPORTS (ERRS), LEVEL OF EFFORT (LOE) INVESTIGATIONS AND PROGRAM SUPPORT.
2024-09-12P00004Funding only$3.82MTHIS DELIVERY ORDER IS PLACING AN ORDER FOR THE DEVELOPMENT OF PRODUCTION ENGINEERING CHANGE PROPOSALS (ECPS), RETROFIT ENGINEERING RELEASE REPORTS (ERRS), LEVEL OF EFFORT (LOE) INVESTIGATIONS AND PROGRAM SUPPORT.
2024-07-16P00003Administrative change$0THIS DELIVERY ORDER IS PLACING AN ORDER FOR THE DEVELOPMENT OF PRODUCTION ENGINEERING CHANGE PROPOSALS (ECPS), RETROFIT ENGINEERING RELEASE REPORTS (ERRS), LEVEL OF EFFORT (LOE) INVESTIGATIONS AND PROGRAM SUPPORT.
2024-04-11P00002Administrative change$0THIS DELIVERY ORDER IS PLACING AN ORDER FOR THE DEVELOPMENT OF PRODUCTION ENGINEERING CHANGE PROPOSALS (ECPS), RETROFIT ENGINEERING RELEASE REPORTS (ERRS), LEVEL OF EFFORT (LOE) INVESTIGATIONS AND PROGRAM SUPPORT.
2024-02-26P00001Administrative change$0THIS DELIVERY ORDER IS PLACING AN ORDER FOR THE DEVELOPMENT OF PRODUCTION ENGINEERING CHANGE PROPOSALS (ECPS), RETROFIT ENGINEERING RELEASE REPORTS (ERRS), LEVEL OF EFFORT (LOE) INVESTIGATIONS AND PROGRAM SUPPORT.
2023-09-220$11.20MTHIS DELIVERY ORDER IS PLACING AN ORDER FOR THE DEVELOPMENT OF PRODUCTION ENGINEERING CHANGE PROPOSALS (ECPS), RETROFIT ENGINEERING RELEASE REPORTS (ERRS), LEVEL OF EFFORT (LOE) INVESTIGATIONS AND PROGRAM SUPPORT.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗