Huntington Ingalls Incorporated received this contract from Sup of Shipbuilding Conv and Repair, Department of the Navy: $222.09M obligated so far for combat ships and landing vessels. It runs to 2026-12-31.
Key facts · data as of Oct 22, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.
Cite this page: SpendQuery, Award N0002416C2427, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_N0002416C2427_9700_-NONE-_-NONE-
Huntington Ingalls Incorporated: all federal awards · Department of Defense: spending · Sup of Shipbuilding Conv and Repair: what it buys · The follow-on: recompete brief
DETAIL DESIGN AND CONSTRUCTION (DD&C) FOR LHA 8 (INITIAL EFFORT LIMITED TO PLANNING, ADVANCED ENGINEERING AND PROCUREMENT OF LONG LEAD TIME MATERIAL)
Up for re-bid: ends 2026-12-31. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
282 subawards totaling $72.89M (32.8% of what was obligated), as Huntington Ingalls Incorporated reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Thermal Spray Solutions, Inc. | $12.82M | 3 | VA | 2023-06-22 | 2025-04-24 |
| Industrial Corrosion Control Inc | $9.91M | 24 | MS | 2022-10-05 | 2025-09-22 |
| Surface Technologies Corporation | $8.27M | 7 | FL | 2023-12-12 | 2025-11-25 |
| Northrop Grumman Corporation | $4.84M | 4 | MS | 2024-06-19 | 2025-12-18 |
| Leonardo S.P.A. | $3.57M | 15 | MO, WI | 2024-03-27 | 2025-10-29 |
| Mantech International Corporation | $3.01M | 12 | AL | 2024-03-08 | 2026-01-23 |
| Trident Maritime Systems, Inc. | $2.64M | 6 | VA | 2022-10-12 | 2023-08-21 |
| Dearborn Mid-West Company, LLC | $2.19M | 1 | OH | 2024-04-24 | 2024-04-24 |
| L3Harris Maritime Power & Energy Solutions, Inc. | $1.30M | 8 | OK, PA | 2024-10-07 | 2025-10-15 |
| International Marine and Industrial Applicators LLC | $1.29M | 3 | AL | 2023-09-25 | 2023-12-11 |
| Societe De Negoce Et De Participation | $1.28M | 1 | NC | 2023-09-29 | 2023-09-29 |
| Bollinger Shipyards, Inc | $1.23M | 6 | LA | 2023-04-13 | 2023-10-26 |
| Cooper Machinery Services LLC | $1.21M | 6 | WI | 2024-02-06 | 2024-11-12 |
| In-Place Machining Company, LLC | $1.16M | 3 | WI | 2023-02-28 | 2025-02-26 |
| US, Inc. | $997.0K | 13 | AL | 2023-10-27 | 2025-12-09 |
| Eaton Corporation Public Limited Company | $983.3K | 7 | AL | 2024-03-25 | 2025-02-07 |
| R P M Supply Corporation | $918.6K | 1 | OH | 2023-12-11 | 2023-12-11 |
| Martin Energy Services, LLC | $879.2K | 2 | TX | 2025-02-28 | 2025-03-11 |
| Lake Shore Systems, Inc. | $788.3K | 9 | MI | 2023-09-25 | 2026-01-30 |
| Hydratight Operations Inc | $771.1K | 4 | WI | 2024-05-30 | 2025-12-19 |
| Crane Pumps & Systems PFT Corp | $697.3K | 2 | OH | 2022-12-20 | 2023-12-22 |
| Arcline Investment Management LP | $636.0K | 3 | WI | 2022-10-13 | 2023-05-25 |
| Chand, L.L.C. | $596.0K | 9 | LA | 2023-12-07 | 2025-04-17 |
| TCH Distributors, LLC | $555.6K | 2 | LA | 2024-11-26 | 2025-06-30 |
| Lockheed Martin Corporation | $546.4K | 4 | NJ | 2023-12-01 | 2025-09-30 |
The 25 largest of 88; the rest are on USAspending.gov.
| Date | To | Amount | For |
|---|---|---|---|
| 2023-06-22 | Thermal Spray Solutions, Inc. | $12.50M | LHA8 THERMAL SPRAY NON-SKID |
| 2023-12-12 | Surface Technologies Corporation | $4.75M | 01043-02 DECK COVER (NON-SKID) |
| 2024-04-30 | Surface Technologies Corporation | $2.75M | 01043-02 DECK COVERING |
| 2024-11-27 | Northrop Grumman Systems Corporation | $2.59M | LHA8-19005-011 |
| 2025-02-24 | DRS Naval Power Systems Inc | $2.40M | LHA8-04007-01 DIST SWITCHBOARD |
| 2023-03-09 | US Joiner LLC | $2.34M | LHA8 SOW INSULATION INSTALL |
| 2024-04-24 | RFD Beaufort Inc. | $2.19M | LIFE RAFT |
| 2025-12-18 | Northrop Grumman Systems Corporation | $1.48M | LHA8-19005-011 |
| 2023-09-29 | Vallen Distribution, Inc. | $1.28M | REPLENISHMENT AT SEA (EQN) |
| 2023-04-20 | Industrial Corrosion Control Inc | $1.10M | LHA8-09009-01 COATING SOW |
| 2023-06-16 | Industrial Corrosion Control Inc | $1.09M | LHA8-09009-01 COATING SOW |
| 2023-12-11 | R P M Supply Corporation | $918.6K | OSI LHA8 HMR 8-064 COSAL |
| 2025-11-18 | Imia, LLC | $904.8K | LHA 8 09182 SOW FOR COMP RESTORATION |
| 2025-02-28 | Martin Energy Services, LLC | $841.2K | LHA8 FUEL |
| 2023-09-08 | Chand, L.L.C. | $804.4K | OSI LHA8 HMR 8-053 COSAL TAPE |
| 2023-05-15 | Industrial Corrosion Control Inc | $762.2K | LHA8-09009-01 COATING SOW |
| 2023-03-30 | Industrial Corrosion Control Inc | $742.8K | LHA8-09009-01 COATING SOW |
| 2024-06-19 | Northrop Grumman Systems Corporation | $668.0K | VSR SA25007 |
| 2022-12-20 | Crane Pumps & Systems PFT Corp | $646.1K | LHA8-03121-01 SEWAGE PUMPS |
| 2023-12-11 | Imia, LLC | $643.8K | LHA8-09009-01 COATING SOW |
| 2024-12-16 | In-Place Machining Company, LLC | $635.9K | LHA 8 SOW FOR ANTENNA FOUNDATIONS (RND 2) |
| 2024-10-07 | L3Harris Maritime Power & Energy Solutions, Inc. | $620.0K | LHA8-04169-01 IPNC |
| 2024-02-06 | Fairbanks Morse, LLC | $617.5K | OSI LHA8 HMR 8-064 COSAL |
| 2023-06-28 | Industrial Corrosion Control Inc | $608.4K | LHA8-09009-01 COATING SOW |
| 2023-07-27 | Industrial Corrosion Control Inc | $586.2K | LHA8-09009-01 COATING SOW |
204 actions since 2022-10-03 (the newest 200 shown). Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-21 | A00589 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-07-21 | A00588 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-07-01 | A00587 | Supplemental agreement (work within scope) | -$136.1K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-06-22 | A00586 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-05-26 | A00585 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-05-06 | A00584 | Funding only | $1.00M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-05-04 | A00583 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-04-27 | A00582 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-04-22 | A00581 | Supplemental agreement (work within scope) | $10.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-04-08 | P00077 | Funding only | $53.65M | FPDS-NG VALUE TO ALLOW POSTING |
| 2026-03-31 | A00580 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-03-16 | P00076 | Funding only | $4.80M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-03-16 | P00075 | Administrative change | $70.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-02-11 | A00579 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-01-30 | P00074 | Funding only | $40.00M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-01-28 | A00578 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2026-01-16 | A00577 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-12-16 | A00576 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-12-11 | A00575 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-12-10 | P00073 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-12-04 | A00574 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-11-17 | A00573 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-11-17 | A00572 | Supplemental agreement (work within scope) | $365.7K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-11-12 | A00571 | Supplemental agreement (work within scope) | $2.38M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-11-03 | A00570 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-10-23 | A00569 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-10-23 | A00568 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-09-24 | A00567 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-09-23 | A00566 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-09-16 | A00565 | Supplemental agreement (work within scope) | $8.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-09-08 | A00564 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-08-25 | A00563 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-08-25 | A00562 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-08-20 | A00561 | Administrative change | -$8.6K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-08-14 | A00560 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-08-14 | A00559 | Administrative change | -$16.7K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-08-13 | A00558 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-08-12 | A00557 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-07-31 | A00556 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-07-31 | A00555 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-07-14 | P00072 | Funding only | $350.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-07-14 | A00554 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-07-10 | A00553 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-06-26 | P00071 | Administrative change | $79.40M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-06-11 | A00552 | Supplemental agreement (work within scope) | $10.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-06-05 | A00551 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-05-28 | A00550 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-05-27 | AZ0012 | Change order definitized | $64.7K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-05-20 | A00549 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-05-19 | A00548 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-04-25 | P00070 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-03-26 | A00547 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-03-24 | A00546 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-03-17 | A00545 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-02-28 | A00544 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-02-24 | P00069 | Funding only | $270.0K | FUNDING MOD |
| 2025-02-13 | A00543 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-02-13 | A00542 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-01-31 | A00541 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-01-28 | A00540 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-01-23 | A00539 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-01-22 | A00538 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-01-22 | A00537 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-01-17 | A00536 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-01-13 | A00535 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-01-13 | A00534 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2025-01-13 | A00533 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-12-20 | A00532 | Change order | $3.12M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-12-17 | P00068 | Administrative change | $117.5K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-12-17 | A00531 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-12-09 | A00530 | Funding only | $500.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-11-21 | A00529 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-11-20 | A00528 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-11-13 | A00527 | Supplemental agreement (work within scope) | $8.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-11-06 | P00067 | Administrative change | $250.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-31 | A00526 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-29 | A00525 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-15 | A00524 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-15 | A00523 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-07 | A00522 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-01 | A00521 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-09-12 | P00066 | Administrative change | -$41.8K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-09-12 | A00520 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-08-28 | P00065 | Administrative change | $108.2K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-08-27 | A00519 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-08-16 | A00518 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-08-07 | A00517 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-07-31 | A00516 | Supplemental agreement (work within scope) | $3.43M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-07-24 | A00515 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-07-16 | A00514 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-07-10 | A00513 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-07-01 | A00512 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-07-01 | A00511 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-06-18 | A00510 | Funding only | $8.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-06-17 | A00509 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-06-11 | A00508 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-06-04 | A00507 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-05-21 | A00506 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-05-09 | A00505 | Change order | $203.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-04-30 | P00064 | Funding only | $340.8K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-04-23 | A00504 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-04-10 | A00503 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-03-26 | A00502 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-03-26 | A00501 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-03-20 | A00500 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-03-18 | AZ0011 | Supplemental agreement (work within scope) | $592.9K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-03-05 | A00499 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-02-29 | A00498 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-02-29 | A00497 | Change order | $390.2K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-02-28 | A00496 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-02-21 | P00063 | Funding only | $131.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-02-13 | AZ0010 | Change order definitized | $155.7K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-02-08 | A00495 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-01-30 | AZ0009 | Change order definitized | $280.4K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-01-30 | A00494 | Funding only | $10.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-01-24 | AZ0008 | Change order definitized | $277.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-01-24 | A00493 | Funding only | $1.33M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-01-12 | A00492 | Funding only | $1.00M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2024-01-09 | A00491 | Funding only | $1.41M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-12-19 | A00490 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-12-13 | A00489 | Supplemental agreement (work within scope) | $77.1K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-12-13 | A00488 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-12-13 | A00487 | Change order | $112.5K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-12-06 | A00486 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-11-30 | P00062 | Administrative change | $4.72M | LHA 8 DETAIL DESIGN AND CONSTRUCTION. LAUNCH INCENTIVE FUNDING SLIN 000306. |
| 2023-11-30 | A00485 | Change order | $138.7K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-11-28 | A00484 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-11-28 | A00483 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-11-16 | P00061 | Administrative change | $276.9K | LHA 8 DETAIL DESIGN AND CONSTRUCTION. INCENTIVE FUNDING AND SPECIAL STUDIES FUNDING. |
| 2023-11-16 | A00482 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-10-31 | A00481 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-10-30 | A00480 | Change order | $843.5K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-10-19 | A00479 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-10-19 | A00478 | Change order | $76.2K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-10-17 | A00477 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-10-10 | P00060 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION, SHIFT HOURS UNDER CLINS AND CHANGE POP |
| 2023-10-10 | A00476 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-10-10 | A00475 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-09-20 | A00474 | Supplemental agreement (work within scope) | $3.26M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-09-19 | A00473 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-09-19 | A00472 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-09-13 | A00471 | Change order definitized | $87.3K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-09-07 | A00470 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-09-01 | P00059 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION SECTION B INCENTIVES UPDATE |
| 2023-08-30 | AZ0007 | Supplemental agreement (work within scope) | $22.7K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-08-30 | AZ0006 | Change order definitized | $96.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-08-25 | AZ0005 | Supplemental agreement (work within scope) | $196.5K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-08-23 | A00469 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-08-18 | A00468 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-08-18 | A00467 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-08-17 | AZ0004 | Supplemental agreement (work within scope) | $72.2K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-08-10 | A00466 | Supplemental agreement (work within scope) | $10.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-07-27 | P00058 | Administrative change | -$61.3K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-07-26 | A00465 | Change order | $41.3K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-07-25 | A00464 | Change order | $131.2K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-07-25 | A00463 | Change order | $194.3K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-07-12 | A00462 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-06-20 | A00461 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-06-14 | P00057 | Funding only | $240.9K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-06-13 | A00460 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-06-07 | A00459 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-06-06 | A00458 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-05-31 | A00457 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-05-31 | A00456 | Supplemental agreement (work within scope) | $483.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-05-23 | AZ0003 | Change order definitized | $266.7K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-05-18 | P00056 | Funding only | $710.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-05-18 | A00455 | Supplemental agreement (work within scope) | $662.2K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-05-12 | A00454 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-05-11 | A00453 | Change order | $2.79M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-04-25 | A00452 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-04-24 | A00451 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-04-21 | P00055 | Funding only | $400.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-04-07 | A00450 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-04-07 | A00449 | Supplemental agreement (work within scope) | $1.00M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-04-04 | A00448 | Funding only | $18.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-03-28 | A00447 | Supplemental agreement (work within scope) | $2.90M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-03-27 | P00054 | Supplemental agreement (work within scope) | $589.6K | LHA 8 SNUBBERS MATERIAL ONLY |
| 2023-03-17 | A00446 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-03-09 | P00053 | Funding only | $1.60M | FUNDING ONLY |
| 2023-02-24 | A00445 | Supplemental agreement (work within scope) | $391.5K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-02-22 | A00444 | Supplemental agreement (work within scope) | $10.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-02-15 | A00443 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-02-14 | A00442 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-02-09 | A00441 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-01-30 | A00440 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-01-25 | A00439 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-01-23 | A00438 | Administrative change | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-01-23 | A00437 | Supplemental agreement (work within scope) | $1.59M | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-01-17 | A00436 | Supplemental agreement (work within scope) | -$76.4K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2023-01-10 | P00052 | Funding only | $100.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION. DEOB AND OBLIGATION OF FUNDING. CHANGE OF COR INFO UNDER SECTION G. |
| 2022-12-22 | A00435 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2022-12-15 | A00434 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2022-12-12 | A00433 | Supplemental agreement (work within scope) | $332.2K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2022-12-05 | A00432 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2022-11-23 | A00431 | Supplemental agreement (work within scope) | $283.2K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2022-11-21 | A00430 | Supplemental agreement (work within scope) | $395.0K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2022-11-14 | A00429 | Supplemental agreement (work within scope) | $211.4K | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2022-11-14 | A00428 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
| 2022-11-07 | P00051 | Option exercised | $1.06M | EXERCISE OPTION CLIN 0011, FUNDING CLIN 0003 AND 0011. |
| 2022-11-04 | A00427 | Supplemental agreement (work within scope) | $0 | LHA 8 DETAIL DESIGN AND CONSTRUCTION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗