Huntington Ingalls Incorporated received this contract from Sup of Shipbuilding Conv and Repair, Department of the Navy: $1.49B obligated so far for combat ships and landing vessels. It runs to 2031-03-01.
Key facts · data as of Oct 22, 2026
- Recipient
- Huntington Ingalls Incorporated
- Awarding agency
- Department of the Navy (Department of Defense)
- Contracting office
- Sup of Shipbuilding Conv and Repair (N69316)
- Obligated to date
- $1.49B
- Potential value
- $5.17B
- Ends
- 2031-03-01
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.
Cite this page: SpendQuery, Award N0002418C2406, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_N0002418C2406_9700_-NONE-_-NONE-
Huntington Ingalls Incorporated: all federal awards · Department of Defense: spending · Sup of Shipbuilding Conv and Repair: what it buys
LPD 30 LLTM
What it is
- Product or service
- Combat Ships and Landing Vessels (PSC 1905)
- Industry
- Ship Building and Repairing (NAICS 336611)
- Contracting office
- Sup of Shipbuilding Conv and Repair (N69316)
- Competition
- Not competed · 1 offer received
- Pricing
- Fixed price incentive
- How it was bought
- Standalone contract
- Solicitation
- N0002418R2406
- Where the work is
- Jackson, MS · district MS-04
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
723 subawards totaling $244.63M (16.4% of what was obligated), as Huntington Ingalls Incorporated reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| DRS Naval Power Systems Inc | $21.02M | 2 | WI | 2022-10-14 | 2022-10-14 |
| Caterpillar Inc. | $16.61M | 2 | IL | 2023-10-09 | 2023-10-20 |
| American Superconductor Corp | $15.38M | 2 | MA | 2022-10-17 | 2022-12-02 |
| Johnson Controls Navy Systems, LLC | $13.40M | 7 | PA | 2022-11-28 | 2025-12-18 |
| Leonardo S.P.A. | $10.44M | 28 | MO, WI | 2022-10-25 | 2025-12-19 |
| Mantech International Corporation | $9.26M | 20 | AL | 2024-07-30 | 2026-01-19 |
| Carolina Power Systems of Sumter Inc | $8.51M | 17 | SC | 2023-01-19 | 2025-12-19 |
| Industrial Corrosion Control Inc | $7.62M | 20 | MS | 2022-10-10 | 2025-10-09 |
| Ellwood City Forge Company | $6.57M | 2 | PA | 2022-10-05 | 2022-12-21 |
| KPS Capital Partners, LP | $6.23M | 1 | OH | 2023-06-12 | 2023-06-12 |
| Carver Pump Company | $5.42M | 4 | IA | 2022-10-28 | 2025-10-24 |
| Alfa Laval Ab | $4.84M | 4 | PA | 2022-11-03 | 2025-06-20 |
| Milwaukee Valve Co, Inc | $4.64M | 30 | WI | 2022-11-17 | 2026-01-06 |
| B N L Industries Inc | $3.67M | 50 | CT | 2022-10-11 | 2026-01-30 |
| International Marine and Industrial Applicators LLC | $3.60M | 1 | AL | 2023-12-14 | 2023-12-14 |
| Southcoast Welding & Manufacturing, LLC. | $3.43M | 10 | CA | 2023-07-11 | 2025-04-16 |
| Ultra Poly, Inc. | $3.42M | 4 | WA | 2023-03-23 | 2024-09-17 |
| Parker-Hannifin Corporation | $2.88M | 2 | CA | 2024-04-25 | 2025-05-20 |
| Juniper Elbow Co. Inc. | $2.87M | 11 | NY | 2023-08-29 | 2025-04-16 |
| Griswold Industries | $2.84M | 20 | CA | 2022-10-13 | 2025-06-06 |
| Supreme Integrated Technology, Inc. | $2.47M | 3 | LA | 2024-07-31 | 2025-03-31 |
| Aarding Thermal Acoustics USA Inc | $2.46M | 3 | NY | 2023-06-09 | 2023-08-07 |
| Circor International Inc. | $2.45M | 3 | FL, NC | 2022-11-28 | 2023-07-06 |
| Appleton Marine Inc | $2.45M | 3 | WI | 2024-10-03 | 2024-12-20 |
| Abc Applicators Inc | $2.42M | 7 | AL | 2023-10-13 | 2024-12-11 |
The 25 largest of 173; the rest are on USAspending.gov.
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2023-10-09 | Caterpillar Inc | $16.42M | 03019-01 (PTS 6123-K) |
| 2022-10-14 | DRS Naval Power Systems Inc | $15.60M | 04014-01 (PTS 6323-K) |
| 2022-10-17 | American Superconductor Corp | $15.13M | 04001-01 (PTS 7901-J) |
| 2023-03-10 | Carolina Power Systems of Sumter Inc | $7.60M | 04021-01 (PTS 6290-K) |
| 2025-12-18 | Johnson Controls Navy Systems, LLC | $6.59M | 02002-01 (PTS 6305-K) |
| 2025-12-18 | Johnson Controls Navy Systems, LLC | $6.59M | 02002-01 (A/C PLANT) |
| 2022-12-21 | Ellwood National Forge Company | $6.50M | 03003-01 (PTS 6131-K) |
| 2023-06-12 | Howden North America Inc | $6.23M | 02506-01 (PTS 6182-K) |
| 2022-12-21 | Engineered Coil Company | $6.05M | 02501-01 (PTS 6284-K) |
| 2022-10-14 | DRS Naval Power Systems Inc | $5.41M | 04007-01 (PTS 6302-K) |
| 2022-11-03 | Alfa Laval Inc | $4.73M | 03018-01 (PTS 6171-K) |
| 2023-12-14 | Imia, LLC | $3.60M | 09106-01 (TANK PAINTING) |
| 2022-12-21 | Carver Pump Company | $3.24M | 03005-01 (PTS 6219-K) |
| 2024-04-25 | Parker Hannifin Corporation | $2.71M | 03041-01 (PTS 6189-K) |
| 2024-09-17 | Imia, LLC | $2.27M | 09106-01 (TANK PAINTING) |
| 2025-03-31 | Supreme Integrated Technology, Inc. | $2.17M | LPD32-01554-01 |
| 2022-11-28 | Circor Pumps North America LLC | $2.15M | 03020-01 (PTS 6177-K) |
| 2022-10-24 | Industrial Corrosion Control Inc | $1.97M | TERM ORDER LPD30 BLAST/PAI |
| 2024-12-20 | Appleton Marine Inc | $1.95M | 01509-02 (PTS 6181-K) |
| 2023-08-25 | American Metal Bearing Co | $1.91M | 03067-01 (PTS 6241-K) |
| 2023-08-30 | Asco Power Technologies, L..P. | $1.84M | 04058-01 (PTS 6336-K) |
| 2025-10-03 | Surface Technologies Corporation | $1.75M | LPD30 01043-01 NON-SKID SOW |
| 2022-11-11 | Dover Pumps & Process Solutions Segment Inc | $1.72M | 03004-02 (PTS 6177-K) |
| 2022-10-28 | Carver Pump Company | $1.67M | 03014-01 (PTS 6294-K) |
| 2024-07-09 | Southcoast Welding & Manufacturing, LLC. | $1.53M | 01036-01 (LPD32) |
Every action
144 actions since 2022-10-12. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-22 | A00323 | Supplemental agreement (work within scope) | $0 | LPD 30 REQUEST FOR WAIVER (RFW) 0830 & 0839. NO COST. |
| 2026-07-08 | A00322 | Supplemental agreement (work within scope) | $0 | REVISED REWEIGHTS AND BILLINGS 2026 1ST QUARTER LPD 30 AND 32 |
| 2026-06-02 | A00321 | Supplemental agreement (work within scope) | $0 | LDP 30 REQUEST FOR WAIVER (RFW) 0838 PROPULSION SHAFTING CORROSION AND PITTING- NO COST |
| 2026-05-28 | A00320 | Supplemental agreement (work within scope) | $0 | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2026-05-18 | AZ0012 | Change order definitized | $649.9K | HEADQUARTERS MODIFICATION REQUEST (HMR) 450 LPD 31 ENGINEERING CHANGE REQUEST (ECR) 2645 REV 1 UNITED STATES MARINE CORP (USMC) SPACE SAVER LOCKERS, DEFINITIZATION OF A00243 |
| 2026-05-13 | A00319 | Supplemental agreement (work within scope) | $1.83M | N00024-18-C-2406 HANDLING WATERFRONT TASK AUTHORIZATION (WTA) OVER THRESHOLD IN ALIGNMENT WITH ECR STANDARDS HMR 492, LPD 30, ACRN TA, CLIN 0001 HMR 488, LPD 31, ACRN TB, CLIN 0401 HMR 493, LPD 32, ACRN TE, CLIN 0501 |
| 2026-04-24 | A00318 | Supplemental agreement (work within scope) | $0 | HEADQUARTERS MODIFICATION REQUEST 319 LPD 30 WATERFRONT TASK AUTHORIZATION POOL CHANGES 1ST QUARTER 2026 |
| 2026-04-24 | A00317 | Supplemental agreement (work within scope) | $0 | LPD 30 DETAIL DESIGN AND CONSTRUCTION REQUEST FOR WAIVER (RFW) 0810 DECK TOLERANCES (DECK HEIGHT) CONTRACT LINE ITEM NUMBER 0001 |
| 2026-04-22 | A00316 | Supplemental agreement (work within scope) | $0 | HEADQUARTERS MODIFICATION REQUEST 353 LPD 31 WATERFRONT TASK AUTHORIZATION POOL CHANGES 1ST QUARTER 2026 |
| 2026-03-31 | P00023 | Funding only | $79.44M | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2026-03-27 | A00315 | Supplemental agreement (work within scope) | $0 | LPD 30 REQUEST FOR WAIVER(RFWQ) 0831 TWISTED TEE FLANGES. NO COST. |
| 2026-03-20 | A00314 | Change order | $8.75M | LPD 31 DETAIL DESIGN AND CONSTRUCTION CONTRACT LINE ITEM NUMBER (CLIN) 0401 UNPRICED CHANGE ORDER (UCO) FOR ENGINEERING CHANGE REQUEST (ECR) 2724 REPLACE HIGH TEMPERATURE SUPERCONDUCTING DEGAUSSING WITH COPPER DEGAUSSING |
| 2026-03-18 | A00313 | Supplemental agreement (work within scope) | $0 | LPD 30 DETAIL DESIGN AND CONSTRUCTION REQUEST FOR WAIVER (RFW) 0818 VEHICLE MINIMUM CLEARANCE - NO COST |
| 2026-03-17 | A00312 | Supplemental agreement (work within scope) | $0 | THIS MODIFICATION INCORPORATES TECHNICALLY APPROVED, NO COST REQUEST FOR WAIVER (RFW) 0837 LPD 30 PASSAGEWAY CLEARANCE 2-80-5-L-ES 98 DUCTING. |
| 2026-03-13 | A00311 | Supplemental agreement (work within scope) | $0 | LPD 30 REQUEST FOR WAIVER 0832 (FIRE DETECTION SYSTEM SHORT CIRCUIT ISOLATORS AND CABLING) NO COST CONTRACT LINE ITEM NUMBER 0001 |
| 2026-03-13 | A00310 | Change order | $5.11M | LPD 32 UNPRICED CHANGE ORDER (UCO) ENGINEERING CHANGE REQUEST (ECR) 2724 REPLACE HIGH TEMPERATURE SUPERCONDUCTING (HTS) DEGAUSSING WITH COPPER DEGAUSSING CONTRACT LINE ITEM NUMBER 0501 |
| 2026-03-06 | A00309 | Supplemental agreement (work within scope) | -$546.2K | HEADQUARTERS MODIFICATION REQUEST (HMR) 353 WATERFRONT TASK AUTHORIZATION (WTA) POOL DECREASE FOR LPD 31 |
| 2026-02-19 | A00308 | Supplemental agreement (work within scope) | $0 | LPD 31 WATERFRONT TASK AUTHORIZATION (WTA) POOL 4TH QUARTER 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR 353) |
| 2026-02-04 | A00307 | Supplemental agreement (work within scope) | $0 | LPD 30 REQUEST FOR WAIVER (RFW) 0834 NO. 1 EXHAUST BELLOW INSTALLATION MISALIGNMENT |
| 2026-01-06 | A00306 | Supplemental agreement (work within scope) | -$1.03M | LPD 30 CONTRACT LINE ITEM NUMBER 0001 HEADQUARTERS MODIFICATION REQUEST ENGINEERING CHANGE REQUEST 2707 DEGAUSSING SYSTEM STOP WORK |
| 2025-12-18 | A00305 | Supplemental agreement (work within scope) | $0 | LPD 30 DETAIL DESIGN AND CONSTRUCTION REQUEST FOR WAVIER (RFW) 0835 (MEDICAL WARD CURTAIN RAILING HEIGHT) |
| 2025-12-17 | A00304 | Supplemental agreement (work within scope) | $0 | HEADQUARTERS MODIFICATION REQUEST (HMR) 423 LPD 32 QUARTER 3 2025 WATERFRONT TASK AUTHORIZATION (WTA) |
| 2025-12-17 | A00303 | Supplemental agreement (work within scope) | $0 | LPD 30 WATERFRONT TASK AUTHORIZATION (WTA) POOL CHANGES QUARTER 3 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR) 319 |
| 2025-12-15 | A00302 | Supplemental agreement (work within scope) | $0 | LPD 31 WATERFRONT TASK AUTHORIZATION (WTA) POOL 2ND QUARTER 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR 353) |
| 2025-12-15 | A00301 | Change order | $3.68M | LPD 30 DETAIL DESIGN AND CONSTRUCTION UNPRICED CHANGE ORDER (UCO) FOR ENGINEERING CHANGE REQUEST (ECR) 2728 ADVANCED DEGAUSSING SYSTEM MATERIAL PURCHASE CONTRACT LINE ITEM NUMBER (CLIN) 0001 |
| 2025-10-07 | A00300 | Supplemental agreement (work within scope) | $1.85M | LPD 30 HEADQUARTERS MODIFICATION REQUEST (HMR) 461 CONSOLIDATED SHIPBOARD ALLOWANCE LIST INCREMENT 4. CONTRACT LINE ITEM NUMBER 0005 |
| 2025-10-06 | A00299 | Supplemental agreement (work within scope) | $689.0K | ENGINEERING CHANGE REQUEST 2655 LPD 31 32 CONTRACT LINE ITEM NUMBERS 0401 0501 - FIRE SAFETY CHANGES - HEADQUARTERS MODIFICATION REQUEST 471 |
| 2025-10-02 | A00298 | Funding only | -$774.9K | LPD 30 WATERFRONT TASK AUTHORIZATION POOL DEOB |
| 2025-09-30 | A00297 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1950 NO COST MODIFICATION THAT INCORPORATES VARIOUS CONDITION REPORTS (CRS) |
| 2025-09-11 | A00296 | Administrative change | $0 | LPD 32 2ND QUARTER 2025 REWEIGHTS AND BILLINGS |
| 2025-09-08 | A00295 | Administrative change | $0 | ADMIN MOD TO A00272 |
| 2025-09-03 | A00294 | Supplemental agreement (work within scope) | -$505.9K | LPD 32 WATERFRONT TASK AUTHORIZATION POOL DECREASE - HEADQUARTERS MODIFICATION REQUEST 423 |
| 2025-08-15 | A00293 | Supplemental agreement (work within scope) | $0 | INCORPORATE LPD 30 REQUEST FOR WAIVER (RFW) 0824 - BOAT AND CARGO CRANE INTO THE BASE CONTRACT AT NO COST - CONTRACT LINE ITEM NUMBER 0001 |
| 2025-08-01 | A00292 | Supplemental agreement (work within scope) | $0 | HEADQUARTERS MODIFICATION REQUEST 423 LPD 32 QUARTER 2 2025 WATERFRONT TASK AUTHORIZATION CONTRACT LINE ITEM 0501 |
| 2025-07-31 | A00291 | Supplemental agreement (work within scope) | $2.45M | LPD 31 AND 32 ENGINEERING CHANGE REQUEST 2650: MORIAH WIND SYSTEM BOUNDARY DEFENSE NETWORK RACK - HEADQUARTERS MODIFICATION REQUEST 463 CONTRACT LINE ITEM NUMBERS 0401 AND 0501 |
| 2025-07-11 | A00290 | Supplemental agreement (work within scope) | $0 | LPD 31 DETAIL DESIGN AND CONSTRUCTION WATERFRONT TASK AUTHORIZATION (WTA)POOL 2ND QUARTER 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR) 353 |
| 2025-07-09 | A00289 | Supplemental agreement (work within scope) | $0 | LPD 30 WATERFRONT TASK AUTHORIZATION (WTA) POOL CHANGES QUARTER 2 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR) 319 |
| 2025-07-08 | P00022 | Funding only | $19.16M | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2025-07-02 | A00288 | Supplemental agreement (work within scope) | $0 | RFW 0829 NO COST |
| 2025-06-26 | A00287 | Supplemental agreement (work within scope) | $86.2K | LPD 31 AND 32 ENGINEERING CHANGE REQUEST 2685 - HEADQUARTERS MODIFICATION REQUEST (HMR) 458: ADD HEAT DETECTORS TO COLLECTIVE PROTECTION SYSTEM (CPS) FAN ROOM DIRTY SIDE, CONTRACT LINE ITEM NUMBERS (CLIN) 0401 AND 0501 |
| 2025-06-25 | P00021 | Administrative change | $45.00M | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2025-06-18 | A00286 | Change order | $10.62M | LPD 31 AND 32 DETAIL DESIGN AND CONSTRUCTION UNPRICED CHANGE ORDER FOR HEADQUARTERS MODIFICATION REQUEST 469 ENGINEERING CHANGE REQUEST 2697 ADD ADDITIONAL AC PLANT - CONTRACT LINE ITEM NUMBERS 0401 AND 0501 |
| 2025-06-06 | A00285 | Supplemental agreement (work within scope) | $720.9K | HEADQUARTERS MODIFICATION REQUEST (HMR) 466 ENGINEERING CHANGE REQUEST (ECR) 2693 LPD 30-32 MAIN PROPULSION DIESEL ENGINE (MPDE) ALIGNMENT. CONTRACT LINE ITEM NUMBER (CLIN) 0001 LPD 30 CLIN 0401 LPD 31 CLIN 0501 LPD 32 |
| 2025-05-30 | A00284 | Supplemental agreement (work within scope) | $30.8K | LPD 31 AND 32 FIELD MODIFICATION REQUEST (FMR) 1925 ENGINEERING CHANGE REQUEST (ECR) 2692: 12CK INSTALLATION AS INTERCOMMUNICATION ANNOUNCING SYSTEM CONTRACT LINE ITEM NUMBER (CLIN) 0401 0501 |
| 2025-05-29 | P00020 | Administrative change | -$200.4K | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2025-05-27 | A00283 | Supplemental agreement (work within scope) | $23.6K | FIELD MODIFICATION REQUEST (FMR) 1926 ENGINEERING CHANGE REQUEST (ECR) 2702 LPD 32 REPLACEMENT OF AN/UPX-45 (C) WITH AN/UPX-50 - CONTRACT LINE ITEM NUMBER 0501 |
| 2025-05-27 | A00282 | Supplemental agreement (work within scope) | $1.00M | HMR 423 FUNDING PLUS UP $1M WTA LPD 32 |
| 2025-05-27 | A00281 | Supplemental agreement (work within scope) | $0 | LPD 30 REQUEST FOR WAIVER (RFW) 0821 (FILLER COMPOUND-FAIRWATER) NO COST. |
| 2025-05-21 | A00280 | Supplemental agreement (work within scope) | $800.0K | LPD 30 HMR 319 CLIN 0001 FUNDING PLUS UP |
| 2025-05-13 | A00279 | Supplemental agreement (work within scope) | $404.5K | WTA 30176 (NCDS AND ICDN UPDATES PART 2) |
| 2025-05-07 | A00278 | Supplemental agreement (work within scope) | $0 | REQUEST FOR WAIVER (RFW) 0823 NO COST WAIVER LPD 30: WELD DEFECTS ON THE BACK UP STRUCTURE FOR THE STERN GATE HYDRAULIC POWER UNIT (HPU) ASSEMBLY |
| 2025-05-02 | A00277 | Supplemental agreement (work within scope) | $17.5K | LPD 31 ENGINEERING CHANGE REQUEST 2711 ADDITIONAL DEGAUSSING CABLE CONDUITS - CONTRACT LINE ITEM 0401 - FIELD MODIFICATION REQUEST 1927 |
| 2025-04-29 | A00276 | Supplemental agreement (work within scope) | $0 | HEADQUARTER MODIFICATION REQUEST 423 LPD 32 WATERFRONT TASK AUTHORIZATION POOL CHANGES 4TH QUARTER 2024 |
| 2025-04-29 | A00275 | Supplemental agreement (work within scope) | $0 | WATERFRONT TASK AUTHORIZATION (WTA)POOL QUARTER 4 2024 HEADQUARTERS MODIFICATION REQUEST (HMR) 353 LPD 31 |
| 2025-04-28 | A00274 | Supplemental agreement (work within scope) | $0 | HEADQUARTER MODIFICATION REQUEST (HMR) 319 LPD 30 WATERFRONT TASK AUTHORIZATION Q4 2024 |
| 2025-03-19 | A00273 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1928 VARIOUS CONDITION REPORTS (CR) CR 23030, CR 24015, CR 24018, CR 24019, CR 24020 LPD 30-32 |
| 2025-03-13 | A00272 | Supplemental agreement (work within scope) | -$43.1K | HMR 319 LPD 30 WTA POOL DECREASE |
| 2025-02-24 | A00271 | Administrative change | $0 | ADMIN MOD TO A00268. NO COST MODIFICATION. |
| 2025-02-21 | A00270 | Supplemental agreement (work within scope) | $0 | REQUEST FOR WAIVER (RFW) 0816 TANKLESS ELECTRIC WATER HEATER LPD 30, 31, AND 32 |
| 2025-02-19 | A00269 | Supplemental agreement (work within scope) | -$361.4K | LPD 30 WTA POOL DECREASE |
| 2025-02-11 | A00268 | Supplemental agreement (work within scope) | $1.30M | HMR 457 ENGINEERING CHANGE REQUEST 2640 REPRICE 2 LPD 31 32 PHYSICAL SECURITY REQUIREMENTS UPDATE |
| 2025-01-21 | A00267 | Supplemental agreement (work within scope) | $0 | LPD 30 RFW 0822 AT NO COST TO THE BASE CONTRACT |
| 2024-12-19 | A00266 | Supplemental agreement (work within scope) | -$36.0K | HEADQUARTERS MODIFICATION REQUEST (HMR) 459 ENGINEERING CHANGE REQUEST (ECR) 2690 REV- LPD 32 MK 53 DECOY LAUNCHING SYSTEM, INTRODUCTION OF THE MK54 DECOY LAUNCH MESSAGE CONVERTOR |
| 2024-12-09 | A00265 | Supplemental agreement (work within scope) | $107.7K | HEADQUARTERS MODIFICATION REQUEST (HMR) 456 ENGINEERING CHANGE REQUEST (ECR) 2664 LPD 30-32 ADD MEDICAL STOREROOM IN CPS ZONE |
| 2024-12-09 | A00264 | Supplemental agreement (work within scope) | $469.1K | HEADQUARTERS MODIFICATION REQUEST (HMR) 455 ENGINEERING CHANGE REQUEST (ECR) 2661 CONFLAGRATION VIDEO MONITORING LPD 31 & 32 |
| 2024-12-06 | A00263 | Administrative change | $0 | LPD 32 DETAIL DESIGN AND CONSTRUCTION REWEIGHTS AND BILLING 3RD QUARTER 2024 |
| 2024-11-25 | A00262 | Funding only | $500.0K | LPD 30 DETAIL DESIGN AND CONSTRUCTION WATERFRONT TASK AUTHORIZATION (WTA) HEADQUARTER MODIFICATION REQUEST (HMR)319 POOL INCREASE |
| 2024-11-21 | A00261 | Supplemental agreement (work within scope) | $231.9K | HEADQUARTERS MODIFICATION REQUEST (HMR) 452 ENGINEERING CHANGE REQUEST (ECR) 2674 LPD 31/32 NEW WATER MIST RELIEF VALVE |
| 2024-11-21 | A00260 | Supplemental agreement (work within scope) | $0 | VARIOUS CONDITION REPORTS. THIS IS A NO COST CHANGE. FIELD MODIFICATION REQUEST 1921 |
| 2024-11-04 | P00019 | Funding only | $4.83M | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-23 | A00259 | Supplemental agreement (work within scope) | $0 | LPD 32 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 423 CLIN 0501 |
| 2024-10-23 | A00258 | Supplemental agreement (work within scope) | $0 | LPD 31 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 353 CLIN 0401 |
| 2024-10-23 | A00257 | Supplemental agreement (work within scope) | $0 | LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319 CLIN 0001 |
| 2024-10-08 | AZ0011 | Change order definitized | $138.3K | UNPRICED CHANGE ORDER (UCO)DEFINITIZATION OF MODIFICATION A00225. ENGINEERING CHANGE REQUEST (ECR)2658 REV 1 LPD 30 STUD MAST STRENGTHENING MODIFICATIONS. CLIN 0001 |
| 2024-09-26 | A00256 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1915 NO COST MODIFICATION THAT INCORPORATES VARIOUS CONDITION REPORTS. |
| 2024-09-24 | P00018 | Administrative change | $0 | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2024-09-16 | A00255 | Supplemental agreement (work within scope) | $0 | TO INCORPORATE LPD 30 REQUEST FOR WAIVER (RFW) 0812: FCA 14 MATERIAL INTO THE BASE CONTRACT AT NO COST. |
| 2024-09-16 | A00254 | Supplemental agreement (work within scope) | $80.3K | ENGINEERING CHANGE REQUEST (ECR) 2668 ARMORY DOOR ISSUE POINT LPD 31 & 32 HEADQUARTERS MODIFICATION REQUEST (HMR) 447 |
| 2024-09-16 | A00253 | Supplemental agreement (work within scope) | -$105.1K | HEADQUARTERS MODIFICATION REQUEST (HMR) 449 EMERGENT CHANGE REQUEST (ECR) LPD 32 REPLACE AN/URN-32 TACAN/OE-4691 ANTENNA GROUP WITH AN/URN-33 TACAN SYSTEM SCOPE DECREASE |
| 2024-09-03 | A00252 | Administrative change | $0 | 2024 2ND QUARTER REWEIGHTS AND REBILLINGS LPD 32 |
| 2024-08-19 | A00251 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1908 CONDITION REPORTS 23031, 24003, 24004, 24005, 24006 FOR LPD 30, 31, AND 32 |
| 2024-08-16 | A00250 | Supplemental agreement (work within scope) | $800.0K | HEADQUARTERS MODIFICATION REQUEST (HMR) 319 LPD 30 WATERFRONT MOD POOL INCREASE |
| 2024-08-06 | A00249 | Supplemental agreement (work within scope) | $0 | LPD 30, 31, AND 32 NO COST CONDITION REPORTS 23004 REV A, 23022, 23025, 23026, 23029 |
| 2024-08-05 | A00248 | Supplemental agreement (work within scope) | $0 | LPD 30, 31, AND 32 REQUEST FOR WAIVER 0800 REVISION 1 IMPRESSED CURRENT CATHODIC PROTECTION SYSTEM CLINS 0001, 0401, AND 0501 |
| 2024-07-25 | A00247 | Supplemental agreement (work within scope) | $0 | LPD 32 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 423 CLIN 0501 |
| 2024-07-18 | A00246 | Supplemental agreement (work within scope) | $1.69M | LPD 30 COORDINATED SHIPBOARD ALLOWANCE LIST (COSAL) 3RD INCREMENT HEADQUARTERS MODIFICATION REQUEST (HMR) 426 - CLIN 0005 |
| 2024-07-15 | A00245 | Supplemental agreement (work within scope) | $0 | REQUEST FOR WAIVER (RFW) 0805 - LPD 30-32 SWITCHBOARD EMI |
| 2024-06-17 | A00244 | Supplemental agreement (work within scope) | $269.9K | LPD 31 AND 32 ENGINEERING CHANGE REQUEST 2643 REV 1 UPGRADE OF ELECTRONIC CHART DISPLAY AND INFORMATION SYSTEM (ECDIS) EQUIPMENT |
| 2024-05-31 | A00243 | Change order | $1.19M | LPD 31 ENGINEERING CHANGE REQUEST (ECR) 2465 REVISION 1: USMC SPACE SAVER LOCKER, UNPRICED CHANGE ORDER (UCO) CLIN 0401 - HEADQUARTERS MODIFICATION REQUEST (HMR) 450 |
| 2024-05-29 | A00242 | Administrative change | $0 | MAY 2024 1ST QUARTER REWEIGHTS AND REBILLINGS LPD 31 & 32 |
| 2024-05-29 | A00241 | Supplemental agreement (work within scope) | $377.4K | HEADQUARTERS MODIFICATION REQUEST (HMR) 434 ENGINEERING CHANGE REQUEST (ECR) 2654 LPD 31 AND 32 AC PLANT ASW HELLAN STRAINER ISOLATION VALVES |
| 2024-05-28 | A00240 | Supplemental agreement (work within scope) | $204.8K | HEADQUARTERS MODIFICATION REQUEST (HMR) 443 ENGINEERING CHANGE REQUEST (ECR) 2659 STUB MAST STRENGTHENING MODIFICATIONS FOR LPD 31 AND 32 |
| 2024-04-29 | A00239 | Supplemental agreement (work within scope) | $0 | LPD 30 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319 |
| 2024-04-29 | A00238 | Supplemental agreement (work within scope) | $0 | LPD 32 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 423 |
| 2024-04-10 | A00237 | Supplemental agreement (work within scope) | $0 | LPD 32 DETAIL DESIGN AND CONSTRUCTION FIELD MODIFICATION REQUEST (FMR) 1860: CONDITION REPORT (CR) 22024 REV B AND CR 23010 REV A |
| 2024-03-28 | P00017 | Funding only | $1.04M | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2024-03-06 | A00236 | Supplemental agreement (work within scope) | $0 | LPD 30, 31, AND 32 NO COST CONDITION REPORTS 23012 REV C 23013 REV A, 23020, 23024, 23027 |
| 2024-02-07 | P00016 | Change order | $551.4K | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2024-01-19 | A00235 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1855 LPD 30 & 31 CONDITION REPORTS (CR) 21058 REV C, CR 22024 REV B, CR 23002, CR 23010 REV A, CR 23021 |
| 2024-01-19 | A00234 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1856 LPD 32 CONDITION REPORTS (CR) 21058 REV A, 22015 REV A, 23002, 23021, 23022 |
| 2024-01-19 | A00233 | Supplemental agreement (work within scope) | $0 | LPD 31 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 353 |
| 2023-12-22 | A00232 | Supplemental agreement (work within scope) | $2.41M | LPD 30 COORDINATED SHIPBOARD ALLOWANCE LIST (COSAL) 2ND INCREMENT HEADQUARTERS MODIFICATION REQUEST (HMR) 418 |
| 2023-12-22 | A00231 | Supplemental agreement (work within scope) | $254.4K | HEADQUARTERS MODIFICATION REQUEST (HMR) 427 LPD 32 ECR 2635 SHIP SERVICE DIESEL GENERATOR EUI CONVERSION |
| 2023-12-22 | A00230 | Administrative change | $0 | DECEMBER 2023 3RD QUARTER REWEIGHTS AND REBILLINGS LPD 31 & 32 |
| 2023-10-23 | A00229 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1863 CONDITION REPORTS (CR) 21019 REV A, 22042 REV A, 22046 REV E, 22057 REV A, 23016 REV A |
| 2023-10-10 | A00228 | Supplemental agreement (work within scope) | $0 | LPD 32 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MODIFICATION (SEPTEMBER 2023) HEADQUARTERS MODIFICATION REQUEST (HMR) 423 |
| 2023-10-10 | A00227 | Supplemental agreement (work within scope) | $0 | LPD 31 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MODIFICATION (SEPTEMBER 2023) HEADQUARTERS MODIFICATION REQUEST (HMR) 353 |
| 2023-10-10 | A00226 | Supplemental agreement (work within scope) | $0 | LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319 |
| 2023-09-14 | A00225 | Change order | $68.0K | LPD 30 DETAIL DESIGN AND CONSTRUCTION UNPRICED CHANGE ORDER (UCO) FOR ENGINEERING CHANGE REQUEST 2658 REVISION 1: STUB MAST STRENGTHENING MODIFICATIONS |
| 2023-09-13 | A00224 | Administrative change | $0 | 2023 2ND QUARTER REWEIGHTS AND REBILLINGS LPD 30,31, & 32. |
| 2023-09-07 | A00223 | Administrative change | $0 | ADMINISTRATIVE MODIFICATION TO REVISE MODIFICATION A00208 BY REMOVING CONDITION REPORT (CR) 22054 REVISION A FROM BOX 14 ON PAGE ONE OF THE MODIFICATION DOCUMENT AND FROM THE SUBJECT LINE AND SECTION 1A OF THE SF 30 BLOCK 14 CONTINUATION PAGE. |
| 2023-08-30 | A00222 | Supplemental agreement (work within scope) | $0 | LPD 32 DETAIL DESIGN AND CONSTRUCTION FIELD MODIFICATION REQUESTS 1841 & 1842 CONDITION REPORTS |
| 2023-08-23 | A00221 | Supplemental agreement (work within scope) | $0 | REQUEST FOR WAIVER (RFW) 0788 LPD 30-32 BOAT AND CARGO ELECTROMAGNETIC INTERFACE (EMI) |
| 2023-07-12 | A00220 | Funding only | $500.0K | HEADQUARTERS MODIFICATION REQUEST (HMR) 423 WTA ESTABLISHING FUNDING POOL LPD 32 |
| 2023-07-12 | A00219 | Supplemental agreement (work within scope) | $0 | LPD 31 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MODIFICATION (JUNE 2023) HEADQUARTERS MODIFICATION REQUEST (HMR) 353 |
| 2023-07-12 | A00218 | Supplemental agreement (work within scope) | $0 | LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319 |
| 2023-07-10 | A00217 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1831 LPD 30/31 CONDITION REPORTS (CR): CR 23006 CR 23007 CR 23009 CR 23011 CR 23014 |
| 2023-06-27 | A00216 | Supplemental agreement (work within scope) | $56.8K | FIELD MODIFICATION REQUEST (FMR) 1823 ENGINEERING CHANGE REQUEST (ECR) 2642 LPD 30 AND 31 RELOCATION OF THE DIGITABLE FLUXGATE MAGNETIC COMPASS |
| 2023-06-21 | A00215 | Supplemental agreement (work within scope) | $0 | REQUEST FOR WAIVER (RFW) 0795 REVISION 1 LPD 30-32 UNDERCOUNTER DISHWASHER |
| 2023-06-14 | A00214 | Supplemental agreement (work within scope) | $1.14M | LPD 31 HEADQUARTERS MODIFICATION REQUEST (HMR) 415 ENGINEERING CHANGE REQUEST (ECR) 2606 REVISION 2 CANES HARDWARE 2.0 AND 4.0 |
| 2023-06-12 | A00213 | Supplemental agreement (work within scope) | $18.5K | LPD 31 ENGINEERING CHANGE REQUEST (ECR) REPLACE TACAN ANTENNA GROUP |
| 2023-06-12 | A00212 | Supplemental agreement (work within scope) | $43.3K | LPD 31 ENGINEERING CHANGE REQUEST 2641 REVISION 1: PROVIDE AN/SPQ-9B VIDEO TO THE PILOT HOUSE |
| 2023-06-12 | A00211 | Supplemental agreement (work within scope) | $55.2K | LPD 31 ENGINEERING CHANGE REQUEST 2639: INTER-SPACE CABLE ROUTING GFI UPDATE |
| 2023-05-09 | P00015 | Administrative change | $0 | ADD AN CLIN FOR INSURANCE CLAIMS |
| 2023-04-20 | A00210 | Supplemental agreement (work within scope) | $0 | LPD 31 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MOD (MARCH 2023) HEADQUARTERS MODIFICATION REQUEST (HMR) 353 |
| 2023-04-20 | A00209 | Supplemental agreement (work within scope) | $0 | LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319 |
| 2023-04-06 | A00208 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1812 LPD 30 & 31 CONDITION REPORTS (CR) 22045 REV D, 22054 REV A, 22061, 23001 REV A, 23003 |
| 2023-03-31 | P00014 | Option exercised | $1.30B | LPD 32 DETAIL DESIGN AND CONSTRUCTION |
| 2023-03-24 | A00207 | Supplemental agreement (work within scope) | $0 | INCORPORATES CONDITION REPORTS AT NO COST TO THE CONTRACT |
| 2023-02-06 | A00206 | Supplemental agreement (work within scope) | $0 | LPD 30 & 31 FIELD MODIFICATION REQUEST (FMR) 1694 CONDITION REPORTS |
| 2023-02-02 | A00205 | Supplemental agreement (work within scope) | $0 | REQUEST FOR WAIVER (RFW) 0785 LPD 30 AIR RECEIVER VOLUME |
| 2023-01-26 | A00204 | Supplemental agreement (work within scope) | $0 | LPD 31 HEADQUARTERS MODIFICATION REQUEST (HMR) WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MOD - DECEMBER 2022 |
| 2023-01-25 | A00203 | Supplemental agreement (work within scope) | $0 | LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST 294 |
| 2023-01-23 | A00202 | Supplemental agreement (work within scope) | $30.7K | LPD 31 ENGINEERING CHANGE PROPOSAL REVISION 1: SHIP SELF DEFENSE SYSTEM (SSDS) MK 2 MOD 2E TI-16TR COMMAND CONTROL GROUP AND MAINTENANCE CONSOLE UPGRADE |
| 2023-01-23 | A00201 | Supplemental agreement (work within scope) | -$7.3K | FIELD MODIFICATION REQUEST (FMR) 1788 ENGINEERING CHANGE REQUEST (ECR) 2632 INSTALL AN/USQ-T52A T52 GOVERNMENT GIVEBACK |
| 2022-11-14 | A00200 | Supplemental agreement (work within scope) | $0 | LPD 30 & 31 FIELD MODIFICATION REQUEST (FMR) 1779 - MOD TO INCORPORATE NO COST CONDITION REPORTS |
| 2022-11-04 | A00199 | Supplemental agreement (work within scope) | $0 | FIELD MODIFICATION REQUEST (FMR) 1776 CONDITION REPORTS (CR) CR 22014 REV A (LPD 30/31) CR 22027 REV B (LPD 30/31) CR 22029 (LPD 30/31) CR 22030 REV. B (LPD 30/31) CR 22035 (LPD 30/31) |
| 2022-11-03 | AZ0010 | Change order definitized | $220.7K | HEADQUARTERS MODIFICATION REQUEST (HMR 407) ENGINEERING CHANGE REQUEST (ECR) 2621 LPD 31 MPDE STARTING AIR RECEIVER ADDITION AND DEFINITIZATION OF UNPRICED CHANGE ORDER (UCO) MODIFICATION A00187 DATED 29 AUG 2022. |
| 2022-11-03 | AZ0009 | Change order definitized | $297.5K | HEADQUARTERS MODIFICATION REQUEST (HMR) 400 ENGINEERING CHANGE REQUEST (ECR) 2621 MPDE STARTING AIR RECEIVER ADDITION. DEFINITIZATION FOR UNPRICED CHANGE ORDER (UCO) MODIFICATION A00170 DATED 11 MAR 2022 |
| 2022-10-24 | A00198 | Change order definitized | $96.2K | LPD 31 DD&C UNPRICED CHANGE ORDER DEFINITIZATION TO CONTRACT MODIFICATION A00189 ENGINEERING CHANGE REQUEST 2627 (MAIN PROPULSION DIESEL ENGINE EXHAUST BELLOWS NORDLOCK HARDWARE UPGRADE ACCOMPLISH |
| 2022-10-19 | A00197 | Supplemental agreement (work within scope) | $315.3K | LPD 30 & 31 DD&C ENGINEERING CHANGE REQUEST 2620 SHIP SELF DEFENSE SYSTEM (SSDS) MK 2 MOD 2E ADDITION OF SYCHRO GENERATORS AND IFF VIDEO INVERTERS |
| 2022-10-17 | A00196 | Supplemental agreement (work within scope) | $120.1K | ENGINEERING CHANGE REQUEST (ECR) 2619 UPDATE RAM MK MOD 3 GUIDED MISSILE WEAPON SYSTEM TO RAM MK 31 MOD 5 GMWS FIELD MODIFICATION REQUEST (FMR) 1744 |
| 2022-10-12 | A00195 | Supplemental agreement (work within scope) | $0 | LPD 30 WTA POOL QTR MOD |
| 2022-10-12 | A00194 | Supplemental agreement (work within scope) | $0 | LPD 31 WTA POOL ADMIN QTR MOD |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗