Bollinger Mississippi Shipbuilding, LLC received this contract from Sup of Shipbuilding Conv and Repair, Department of the Navy: $507.43M obligated so far for special service vessels. It runs to 2030-05-01.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award N0002419C2210, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_N0002419C2210_9700_-NONE-_-NONE-
Bollinger Mississippi Shipbuilding, LLC: all federal awards · Department of Defense: spending · Sup of Shipbuilding Conv and Repair: what it buys
POLAR SECURITY CUTTER #1 (FORMERLY HPIB) DETAIL DESIGN AND CONSTRUCTION
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
69 actions since 2022-10-31. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-10 | P00059 | Administrative change | $0 | FAR 52.222-90 CLAUSE INCORPORATION |
| 2026-05-06 | A00062 | Administrative change | $0 | A00062 - INCORPORATE TPS 222-1, 223, 224, AND 225. |
| 2026-03-13 | P00058 | Administrative change | $7.49M | INCREASE SCOPE AND NTE VALUE FOR CLIN 0022 LBTF/PIF LLTM UCA |
| 2026-02-09 | P00057 | Administrative change | $0 | INCORPORATION OF LAUNCH AND BUTT WELD INCENTIVES |
| 2025-12-18 | P00056 | Supplemental agreement (work within scope) | $16.51M | LBTF PIF LLTM UCA ESTABLISHMENT |
| 2025-12-15 | A00061 | Supplemental agreement (work within scope) | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-11-05 | P00055 | Supplemental agreement (work within scope) | $0 | CLIN 0020 CAPEX SPECIAL INCENTIVE |
| 2025-10-31 | A00060 | Administrative change | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-09-30 | P00054 | Funding only | $2.50M | DEOBLIGATE AND OBLIGATE FUNDING |
| 2025-09-29 | A00059 | Supplemental agreement (work within scope) | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-09-25 | P00053 | Funding only | $609.08M | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-08-13 | A00058 | Administrative change | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-08-06 | A00057 | Administrative change | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-07-30 | A00056 | Supplemental agreement (work within scope) | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-07-23 | P00052 | Supplemental agreement (work within scope) | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-07-23 | P00051 | Administrative change | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-06-24 | P00050 | Administrative change | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-06-12 | A00055 | Administrative change | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-05-16 | A00054 | Supplemental agreement (work within scope) | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-04-01 | P00049 | Administrative change | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-03-25 | P00048 | Supplemental agreement (work within scope) | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2025-02-20 | P00047 | Administrative change | $2.00M | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2025-02-06 | A00053 | Supplemental agreement (work within scope) | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-31 | P00046 | Funding only | $225.0K | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-31 | P00045 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-10-09 | P00044 | Funding only | $333.3K | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-09-24 | P00043 | Supplemental agreement (work within scope) | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-09-24 | P00042 | Funding only | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-08-22 | A00052 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-08-19 | P00041 | Funding only | $583.3K | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-08-13 | A00051 | Supplemental agreement (work within scope) | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-08-12 | P00040 | Change order | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-07-29 | A00050 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-05-16 | P00039 | Funding only | $583.3K | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-04-19 | P00038 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-04-10 | P00037 | Administrative change | -$141.70M | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-04-08 | A00049 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-03-26 | P00036 | Funding only | $666.7K | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-03-25 | A00048 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-03-04 | A00047 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-02-20 | P00035 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-02-08 | P00034 | Supplemental agreement (work within scope) | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-01-18 | A00046 | Supplemental agreement (work within scope) | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2024-01-09 | P00033 | Option exercised | $333.3K | SPECIAL INCENTIVES |
| 2023-12-21 | P00032 | Supplemental agreement (work within scope) | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-12-18 | P00031 | Supplemental agreement (work within scope) | $0 | PSC 1 DETAIL DESIGN AND CONSTRUCTION |
| 2023-11-14 | A00045 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-10-23 | P00030 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-09-26 | A00044 | Funding only | -$226.7K | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-09-21 | P00029 | Change order | $7.41M | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-09-11 | A00043 | Change order | $182.2K | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-08-21 | A00042 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-08-15 | A00041 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-06-13 | P00028 | Supplemental agreement (work within scope) | $0 | ADMIN UPDATES AND INCENTIVE RESTRUCTURE |
| 2023-06-12 | A00040 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-05-09 | A00039 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-04-18 | A00038 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-03-23 | A00037 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-02-14 | A00036 | Change order | $1.47M | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-01-11 | P00027 | Supplemental agreement (work within scope) | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-01-11 | A00035 | Vendor ID or name changed | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2023-01-03 | P00026 | Supplemental agreement (work within scope) | $0 | LLTM AUTHORIZATION ON PSC #2 |
| 2022-12-23 | A00034 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2022-12-22 | A00033 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2022-12-07 | P00025 | Change order | $0 | ADMIN ACTION TO UPDATE ATTACHMENTS TO REFLECT CHANGE ORDER ISSUED ON P00021 |
| 2022-12-06 | P00024 | Supplemental agreement (work within scope) | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2022-11-09 | P00023 | Change order | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2022-10-31 | P00022 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
| 2022-10-31 | A00032 | Administrative change | $0 | PSC 2 DETAIL DESIGN AND CONSTRUCTION |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗