Huntington Ingalls Inc received this contract from Sup of Shipbuilding Conv and Repair, Department of the Navy: $1.70B obligated so far for combat ships and landing vessels. Its period of performance ended 2026-10-06.
Key facts · data as of Oct 21, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 21, 2026.
Cite this page: SpendQuery, Award N0002421C2106, data as of Oct 21, 2026, https://spendquery.com/award?id=CONT_AWD_N0002421C2106_9700_-NONE-_-NONE-
Huntington Ingalls Inc: all federal awards · Department of Defense: spending · Sup of Shipbuilding Conv and Repair: what it buys · The follow-on: recompete brief
FY21 RCOH ACCOMPLISHMENT
Up for re-bid: ends 2026-10-06. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
250 actions since 2022-10-03 (the newest 200 shown). Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-08 | A00120 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 ADJUDICATION MOD FOR THE TIMEFRAME OF 16 MAY 2026 - 15 JUNE 2026. |
| 2026-07-02 | A00119 | Supplemental agreement (work within scope) | $631.8K | CVN 74 N00024-21-C-2106 HUNTINGTON HALL MOD 30 MAY 2026 - 20 SEP 2026. |
| 2026-06-17 | A00118 | Supplemental agreement (work within scope) | $0 | TRANSFER GOVERNMENT PROPERTY FROM CONTRACT N00024-21-C-2106 (CVN 74 EXECUTION)TO CONTRACT N00024-24-C-2106 (CVN 75 ADVANCE PLANNING). |
| 2026-06-12 | P00051 | Supplemental agreement (work within scope) | $15.00M | SUPPLEMENTAL AGREEMENT |
| 2026-06-04 | A00117 | Supplemental agreement (work within scope) | $0 | N00024-21-C-2106 CVN 74 ADJUDICATION MOD FOR THE TIMEFRAME OF 15 APRIL 2026 TO 15 MAY 2026, WITH THE EXCEPTION OF FMRS 1780.13 AND 2143.00. |
| 2026-05-11 | P00050 | Supplemental agreement (work within scope) | $0 | WORKFORCE RETENTION |
| 2026-05-05 | A00116 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 EXEC PERIODIC RELEASE MOD FOR THE PERIOD JANUARY 1,2025 THROUGH JUNE 30,2025 |
| 2026-04-24 | A00115 | Supplemental agreement (work within scope) | $0 | N00024-21-C-2106 CVN 74 ADJUDICATION MOD FOR THE TIMEFRAME OF 23 FEBRUARY 2026 TO 15 APRIL 2026. |
| 2026-04-22 | P00049 | Administrative change | $0 | CLAUSE UPDATE |
| 2026-04-01 | P00048 | Funding only | $27.56M | FUNDING ACTION |
| 2026-04-01 | A00114 | Supplemental agreement (work within scope) | $166.3K | CVN 74 N00024-21-C-2106 HUNTINGTON HALL MOD FROM 23 MARCH 2026 TO 29 MAY 2026. |
| 2026-03-27 | A00113 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 ADJUDICATION MOD FROM 15 OCTOBER 2025 - 15 MARCH 2026. |
| 2026-03-26 | A00112 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 GOVERNMENT PROPERTY TRANSFER TO CVN 75 ADVANCE PLANNING N00024-24-C-2106. |
| 2026-03-13 | P00047 | Funding only | $350.00M | FUNDING ACTION |
| 2026-02-27 | A00111 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N00024-21-C-2106 ADJUDICATION MOD FOR THE TIMEFRAME OF 16 JAN 2026 - 15 FEB 2026. |
| 2026-02-23 | P00046 | Administrative change | $0 | ADMINISTRATIVE UPDATE |
| 2026-02-20 | A00110 | Supplemental agreement (work within scope) | $0 | THIS MODIFICATION IS FOR THE TRANSFER OF GOVERNMENT PROPERTY FROM CONTRACTS CVN73 AP, CVN73 EX, AND CVN75 AP TO CONTRACT CVN74 EX. |
| 2026-02-05 | A00109 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 GFP TRANSFER TO CVN 75 AP N00024-24-C-2106. |
| 2026-01-28 | A00107 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 ADJUDICATION MOD FOR THE PERIOD OF 16 NOV 2025 - 3 DEC 2025. |
| 2025-12-19 | A00106 | Supplemental agreement (work within scope) | $0 | TO TRANSFER GOVERNMENT PROPERTY FROM CONTRACT N00024-21-C-2106 (CVN74 EXECUTION) TO CONTRACT N00024-24-C-2106 (CVN75 AP) |
| 2025-12-18 | P00045 | Funding only | $12.50M | FUNDING ACTION |
| 2025-12-01 | P00044 | Funding only | $1.33M | DEWATERING CAPEX FUNDING |
| 2025-12-01 | A00105 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 ADJ MOD FOR THE PERIOD OF 16 OCT 25 - 15 NOV 25 |
| 2025-11-14 | P00043 | Funding only | $52.00M | QOS CAPEX FUNDING |
| 2025-11-14 | A00104 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 EXEC PERIODIC RELEASE MOD FOR THE PERIOD OF 1 JUL 2024 THROUGH 31 DEC 2024. |
| 2025-11-06 | A00103 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 ADJUDICATION MOD 16 SEP 2025 - 15 OCT 2025 |
| 2025-11-03 | P00042 | Administrative change | $0 | CVN 74 RCOH ACCOMPLISHMENT OTHER ADMINISTRATIVE ACTION |
| 2025-10-20 | A00102 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 ADJUDICATION MOD FOR THE PERIOD OF 9 AUG 2023 - 8 AUG 2025 |
| 2025-10-20 | A00101 | Supplemental agreement (work within scope) | $0 | CVN 74 N00024-21-C-2106 ADJUDICATION MOD 1 DEC 2021 - 8 AUG 2023 |
| 2025-09-26 | P00041 | Funding only | $11.34M | CVN 74 RCOH ACCOMPLISHMENT FUNDING ONLY ACTION |
| 2025-09-26 | A00100 | Supplemental agreement (work within scope) | $0 | CVN RCOH N00024-21-C-2106 ADJ MOD FOR THE PERIOD OF 16 AUGUST 2025 THROUGH 15 SEPTEMBER 2025. |
| 2025-09-23 | A00099 | Supplemental agreement (work within scope) | $931.8K | CVN 74 N00024-21-C-2106 HUNTINGTON HALL MOD FROM 22 SEPTEMBER 2025 - 22 MARCH 2026. |
| 2025-09-11 | P00040 | Supplemental agreement (work within scope) | $5.00M | CVN 74 RCOH ACCOMPLISHMENT E&S |
| 2025-09-05 | A00098 | Supplemental agreement (work within scope) | $0 | CVN REFUELING AND COMPLEX OVERHAUL N00024-21-C-2106 ADJUDICATION MODIFICATION FOR THE PERIOD OF 15 JUL 25 THROUGH 16 AUG 25 |
| 2025-09-05 | A00097 | Supplemental agreement (work within scope) | $0 | TO TRANSFER GOVERNMENT PROPERTY FROM CONTRACT N00024-21-C-2106 (CVN 74 EXECUTION) TO CONTRACT N00024-24-C-2106 (CVN 75 AP |
| 2025-08-29 | P00039 | Supplemental agreement (work within scope) | $27.50M | CONTRACT EXTENSION |
| 2025-08-08 | A00096 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N0002421C2106 ADJUDICATION MODIFICATION FOR THE PERIOD 16 JUNE 2025 THRU 15 JULY 2025. |
| 2025-07-31 | A00095 | Administrative change | $0 | GOVERNMENT PROPERTY TRANSFER TO THE FACILITIES USE CONTRACT |
| 2025-07-28 | P00037 | Funding only | $550.0K | FUNDING MODIFICATION AND UPDATE SECTION J ATTACHMENTS D AND Q. |
| 2025-07-01 | A00094 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N0002421C2106 ADJUDICATION MODIFICATION FOR THE PERIOD 16 MAY 2025 THRU 15 JUNE 2025. |
| 2025-06-13 | A00093 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N0002421C2106 ADJUDICATION MODIFICATION FOR THE PERIOD 16 APRIL 2025 THRU 15 MAY 2025. |
| 2025-06-02 | P00035 | Funding only | $85.00M | FUNDING MODIFICATION |
| 2025-05-28 | P00034 | Supplemental agreement (work within scope) | $5.00M | SUPPLEMENTAL WORK AND FUNDING |
| 2025-05-15 | A00092 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N0002421C2106 PERIODIC RELEASE MODIFICATION FOR THE PERIOD 01 JAN 2024 THROUGH 30 JUN 2024. |
| 2025-05-13 | A00091 | Supplemental agreement (work within scope) | $959.1K | CVN 74 N0002421C2106 HUNTINGTON HALL MOD 24 MAR 25 THROUGH 21 SEP 25 |
| 2025-04-30 | P00033 | Funding only | $28.16M | FY21 RCOH ACCOMPLISHMENT |
| 2025-04-24 | P00032 | Funding only | $70.00M | FUNDING MODIFICATION |
| 2025-04-23 | A00090 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N0002421C2106 ADJUDICATION MODIFICATION FOR THE PERIOD 16 MAR 2025 THRU 15 APR 2025. |
| 2025-04-17 | P00031 | Funding only | $21.70M | FUNDING MOD |
| 2025-04-16 | P00030 | Funding only | $3.00M | FUNDING FOR EARNED INCENTIVE |
| 2025-04-11 | A00089 | Supplemental agreement (work within scope) | $0 | N00024-21-C-2106, CVN74 EXECUTION, PERIODIC RELEASE MODIFICATION 1 JULY - 31 DECEMBER 2023. |
| 2025-04-10 | A00088 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N00024-21C2106 ADJUDICATION MODIFICATION FOR THE PERIOD 16 FEB 2025 TO 15 MAR 2025. |
| 2025-03-27 | A00087 | Supplemental agreement (work within scope) | $0 | GOVERNMENT PROPERTY TRANSFERRED TO N62793-22-C-0002. |
| 2025-03-20 | P00029 | Funding only | $85.00M | CVN 74 RCOH ACCOMPLISHMENT |
| 2025-03-14 | A00086 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N00024-21-C-2106 ADJUDICATION MODIFICATION FOR THE PERIOD 16 JAN 2025 TO 15 FEB 2025. |
| 2025-02-24 | A00085 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N00024-21-C-2106 ADJUDICATION MODIFICATION TO PROVIDE STORM PREPARATION FOR TROPICAL CYCLONE 16 FOR THE 21 SEP 2023 TO 24 SEP 2023. |
| 2025-02-19 | P00028 | Supplemental agreement (work within scope) | $0 | E&S |
| 2025-02-13 | A00084 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N00024-21-C-2106 ADJUDICATION MODIFICATION FOR THE PERIOD OF 16 DECEMBER 2024- 15 JANUARY 2025. |
| 2025-02-03 | A00083 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO TRANSFER GOVERNMENT PROPERTY FROM CONTRACT N00024-21-C-2106 (CVN74 EXECUTION) TO CONTRACT, N00024-15-C-2114 (CVN 79) AND N00024-24-C-2106 (CVN 75 ADVANCED PLANNING). |
| 2025-01-21 | A00082 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N00024-21-C-2106 ADJUDICATION MODIFICATION FOR THE PERIOD OF 16 NOV 2024-15 DEC 2024. |
| 2025-01-08 | P00027 | Administrative change | $0 | PAYABLE FEE ADJUSTMENT |
| 2024-12-23 | P00026 | Administrative change | $0 | E&S TRANSFER AND INCREASE |
| 2024-12-18 | A00081 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N00024-21-C-2106 ADJUDICATION MODIFICATION FOR THE PERIOD OF 16 OCT 2024-15 NOV 2024. |
| 2024-11-13 | A00080 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH N00024-21-C-2106 ADJUDICATION MODIFICATION FOR THE PERIOD OF 16 SEP 2024-15 OCT 2024. |
| 2024-11-01 | A00079 | Supplemental agreement (work within scope) | $1.28M | THE PURPOSE OF THIS MODIFICATION IS TO AWARD THE HUNTINGTON HALL BERTHING AND MESSING FOR 23 SEP 2024- 23 MAR 2025. |
| 2024-10-08 | P00025 | Funding only | $42.42M | FUNDING MODIFICATION |
| 2024-09-26 | A00078 | Supplemental agreement (work within scope) | $0 | ALLOCATIONS TO RCOH E&S FOR THE PERIOD OF 17 AUGUST 24 TO 15 SEPTEMBER 24. |
| 2024-09-16 | P00024 | Funding only | $25.00M | CVN 74 RCOH ACCOMPLISHMENT |
| 2024-08-30 | A00077 | Supplemental agreement (work within scope) | $0 | ALLOCATIONS TO RCOH E&S FOR THE PERIOD OF 16 JULY 2024 TO 16 AUGUST 2024. |
| 2024-08-29 | A00076 | Supplemental agreement (work within scope) | $0 | TRANSFER GOVERNMENT PROPERTY FROM N00024-21-C-2106 (CVN 74 EXECUTION) TO CONTRACT N00024-24-C-2106 (CVN 75 ADVANCE PLANNED). |
| 2024-08-08 | A00075 | Supplemental agreement (work within scope) | $0 | ALLOCATIONS TO RCOH E&S FOR THE PERIOD OF 16 JUNE 2024 THROUGH 15 JULY 2024 |
| 2024-07-26 | A00074 | Supplemental agreement (work within scope) | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ACCEPT GOVERNMENT PROPERTY TRANSFERRED FROM CONTRACT N00024-17-C-2105 (CVN 73 EX) AND N00024-14-C-2111 (CVN 73 AP) TO N00024-21-C-2106 (CVN 74 EX). |
| 2024-07-19 | A00073 | Supplemental agreement (work within scope) | $0 | ALLOCATIONS TO RCOH E AND S FOR THE PERIOD OF 16 MAY 2024 - 15 JUNE 2024 |
| 2024-07-12 | P00023 | Supplemental agreement (work within scope) | $0 | SPECIAL INCENTIVE FOR QOL/QOS |
| 2024-06-12 | A00072 | Supplemental agreement (work within scope) | $0 | ALLOCATIONS TO RCOH E&S FOR THE PERIOD OF 16 APRIL 24-15 MAY 24 |
| 2024-06-11 | P00022 | Funding only | $300.0K | FUNDING MOD |
| 2024-05-22 | A00071 | Supplemental agreement (work within scope) | $0 | CVN 74 EX GOVERNMENT PROPERTY ACCEPTANCE MOD FROM MATERIAL ON THE CVN 73 EX |
| 2024-05-10 | P00021 | Funding only | $42.42M | FY21 RCOH ACCOMPLISHMENT |
| 2024-05-06 | A00070 | Supplemental agreement (work within scope) | $0 | FY21 CVN 74 ADJUDICATION MOD PERIOD OF 16 MARCH 2024- 15 APRIL 2024 |
| 2024-05-03 | A00069 | Supplemental agreement (work within scope) | $0 | PERIODIC RELEASE MODIFICATION 1 JAN - 30 JUN 2023 |
| 2024-04-19 | A00068 | Supplemental agreement (work within scope) | $0 | CVN 74 TO FACILITY USE GOVERNMENT PROPERTY MOD |
| 2024-04-12 | P00020 | Administrative change | $0 | UPDATING ALLOTMENT OF FUNDS TABLE IN SECTION G-232-H0001 |
| 2024-04-11 | P00019 | Administrative change | $150.00M | FY21 RCOH ACCOMPLISHMENT |
| 2024-04-09 | A00067 | Supplemental agreement (work within scope) | $0 | CVN 74 ADJUDICATION MOD |
| 2024-03-29 | A00066 | Supplemental agreement (work within scope) | $1.20M | CVN 74 HUNTINGTON HALL MOD 25 MAR 2024 - 22 SEP 2024 |
| 2024-03-05 | A00065 | Supplemental agreement (work within scope) | $0 | CVN 74 ADJUDICATION MOD (13 JANUARY 2024 - 9 FEBRUARY 2024) |
| 2024-02-23 | P00018 | Supplemental agreement (work within scope) | $25.00M | E&S INCREASE |
| 2024-02-02 | A00064 | Supplemental agreement (work within scope) | $0 | GOVERNMENT PROPERTY MODIFICATION |
| 2024-01-31 | P00017 | Supplemental agreement (work within scope) | $7.45M | EMERGENT AND SUPPLEMENTAL WORK |
| 2024-01-30 | A00063 | Supplemental agreement (work within scope) | $0 | CVN 74 ADJUDICATION MOD (30DEC 2023 - 12 DEC 2024) |
| 2024-01-16 | A00062 | Supplemental agreement (work within scope) | $0 | CVN 74 ADJUDICATION MOD (18 NOV 2023 - 29 DEC 23) |
| 2023-12-04 | A00061 | Supplemental agreement (work within scope) | $0 | ADJUDICATION MODIFICATION 14 OCT 23 - 17 NOV 23 |
| 2023-11-30 | P00016 | Administrative change | $0 | FY21 RCOH ACCOMPLISHMENT |
| 2023-11-24 | A00060 | Supplemental agreement (work within scope) | $0 | GFP ACCEPTANCE MOD FROM N00024-17-C-2105 TO N00024-21-C-2106. |
| 2023-11-09 | A00059 | Supplemental agreement (work within scope) | $0 | PERIODIC RELEASE MOD 1 JUL - 31 DEC 2022 |
| 2023-11-07 | A00058 | Supplemental agreement (work within scope) | $0 | GFP ACCEPTANCE MOD FROM N00024-14-C-2111 TO N00024-21-C-2106. |
| 2023-10-31 | A00057 | Supplemental agreement (work within scope) | $0 | FY21 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2023-10-19 | P00015 | Funding only | $300.00M | FUNDING ACTION |
| 2023-10-13 | A00056 | Supplemental agreement (work within scope) | $0 | GFP MODIFICATION FROM N00024-17-C-2105 TO N00024-21-C-2106 |
| 2023-10-13 | A00055 | Supplemental agreement (work within scope) | $0 | GFP ACCEPTANCE MOD FOR N00024-21-C-2106 |
| 2023-10-06 | A00054 | Supplemental agreement (work within scope) | $980.0K | N00024-21-C-2106 HUNTINGTON HALL MOD POP SEP 2023 TO MAR 2024 |
| 2023-10-02 | A00053 | Supplemental agreement (work within scope) | $0 | FY21 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2023-10-02 | A00052 | Supplemental agreement (work within scope) | $0 | ADJUDICATION MODIFICATION 15 JULY 2023 - 18 AUGUST 2023 |
| 2023-08-31 | A00051 | Supplemental agreement (work within scope) | $0 | N00024-21-C-2106 GOVERNMENT PROPERTY MOD |
| 2023-08-16 | P00014 | Administrative change | $0 | FY21 RCOH ACCOMPLISHMENT |
| 2023-08-04 | A00050 | Supplemental agreement (work within scope) | $0 | ADJUDICATION MODIFICATION 20 JUNE 23 - 14 JULY 23 |
| 2023-07-18 | A00049 | Supplemental agreement (work within scope) | $0 | ADJUDICATION MODIFICATION 13 MAY 23- 16 JUNE 23 |
| 2023-06-06 | A00048 | Supplemental agreement (work within scope) | $0 | PERIODIC ADJUDICATION MOD 15 APR 2023 THROUGH 12 MAY 2023 |
| 2023-05-31 | A00047 | Administrative change | $0 | ADMINISTRATIVE CHANGE |
| 2023-05-25 | A00046 | Supplemental agreement (work within scope) | $0 | GOV PROP TRANSFER FROM CVN 73 TO CVN 74. |
| 2023-05-17 | A00045 | Supplemental agreement (work within scope) | $0 | PERIODIC ADJ MOD FOR 18 MARCH 23-14 APRIL 23 |
| 2023-05-12 | A00044 | Supplemental agreement (work within scope) | $0 | PRM 1 JAN - 30 JUN 2022 |
| 2023-05-02 | A00043 | Supplemental agreement (work within scope) | $0 | PERIODIC ADJUDICATION MOD 18 FEB-17 MAR 23 |
| 2023-04-28 | A00042 | Supplemental agreement (work within scope) | $0 | GOVERNMENT PROPERTY TRANSFER |
| 2023-04-14 | A40767 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2023-04-11 | P00013 | Administrative change | $0 | FY21 RCOH ACCOMPLISHMENT |
| 2023-03-30 | A00041 | Supplemental agreement (work within scope) | $0 | GOVERNMENT PROPERTY TRANSFER |
| 2023-03-29 | A00040 | Supplemental agreement (work within scope) | $1.07M | HUNTINGTON HALL POP MAR 23 - SEPT 23 |
| 2023-03-02 | A00039 | Supplemental agreement (work within scope) | $0 | CVN 74 ADJUDICATION MOD |
| 2023-02-22 | A00038 | Supplemental agreement (work within scope) | $0 | FY21 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2023-02-21 | A00037 | Supplemental agreement (work within scope) | $0 | CVN 74 GFP MOD FROM CVN 73. |
| 2023-02-21 | A00036 | Supplemental agreement (work within scope) | $0 | CVN 74 GFP MOD. |
| 2023-01-31 | A00035 | Supplemental agreement (work within scope) | $0 | CVN 74 JANUARY ADJUDICATION MOD |
| 2023-01-25 | P00012 | Funding only | $302.00M | FY21 RCOH ACCOMPLISHMENT |
| 2023-01-23 | A41127 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2023-01-19 | A00034 | Supplemental agreement (work within scope) | $0 | CVN 74 ADJUDICATION MOD. |
| 2022-12-09 | A41119 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-12-09 | A41114 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-12-08 | A41128 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-12-07 | A00033 | Supplemental agreement (work within scope) | $0 | CVN74 ADJUDICATION MOD |
| 2022-12-02 | A41102 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-12-02 | A41089 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-12-02 | A41080 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-30 | P00011 | Funding only | $1.70M | FY21 RCOH ACCOMPLISHMENT |
| 2022-11-29 | A41131 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-29 | A41130 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-29 | A41129 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-29 | A41116 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-29 | A41085 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-29 | A41073 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-28 | A00032 | Supplemental agreement (work within scope) | $0 | CVN 74 HURRICANE ELSA STORM PREP |
| 2022-11-28 | A00031 | Supplemental agreement (work within scope) | $0 | CVN 74 GP TRANSFER MOD |
| 2022-11-23 | A41121 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH ACCOMPLISHMENT |
| 2022-11-23 | A41120 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH ACCOMPLISHMENT |
| 2022-11-23 | A41118 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH ACCOMPLISHMENT |
| 2022-11-23 | A41117 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH ACCOMPLISHMENT |
| 2022-11-23 | A41115 | Supplemental agreement (work within scope) | $0 | CVN 74 RCOH ACCOMPLISHMENT |
| 2022-11-23 | A00030 | Supplemental agreement (work within scope) | $0 | FY21 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-22 | A41126 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-22 | A41125 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-22 | A41124 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-22 | A41123 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-22 | A41122 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-22 | A41111 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-21 | A41110 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-21 | A41108 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-21 | A41107 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-18 | A41113 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-17 | A41112 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-17 | A41105 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-17 | A41104 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-17 | A41103 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-17 | A41101 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-17 | A41100 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-17 | A41099 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-17 | A41098 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-16 | A41106 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-15 | A41097 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-15 | A41096 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-15 | A41095 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-15 | A41094 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-15 | A41093 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-15 | A41092 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-14 | A41086 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-10 | A41091 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-10 | A41090 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-10 | A41084 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-10 | A41083 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-10 | A41082 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-10 | A41055 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-09 | A41088 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-09 | A41075 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-08 | A41087 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-04 | A41079 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-04 | A41078 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-04 | A41077 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-04 | A41076 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-04 | A41071 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-04 | A41068 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-11-01 | A41062 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-10-31 | A41081 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-10-31 | A41074 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-10-31 | A41069 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-10-31 | A40933 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-10-28 | A41072 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-10-28 | A41070 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-10-28 | A00029 | Supplemental agreement (work within scope) | $0 | CVN74 ADJUDICATION MOD |
| 2022-10-26 | A41067 | Change order | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-10-26 | A41029 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |
| 2022-10-25 | A41065 | Supplemental agreement (work within scope) | $0 | CVN 74 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT |