Putting the award page together from the records…
Putting the award page together from the records…
Lockheed Martin Corporation received this contract from Navsea HQ, Department of the Navy: $76.46M obligated so far for modification of equipment- fire control equipment. It runs to 2027-12-31.
Key facts · data as of Oct 22, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.
Cite this page: SpendQuery, Award N0002425C6108, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_N0002425C6108_9700_-NONE-_-NONE-
Lockheed Martin Corporation: all federal awards · Department of Defense: spending · Navsea HQ: what it buys · The follow-on: recompete brief
ENGINEERING AND TECHNICAL SERVICES
Up for re-bid: ends 2027-12-31. Recompete brief → · AN/SPY-6(V) Production RFI/Sources Sought - Copy 1 ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
4 subawards totaling $520.8K (0.7% of what was obligated), as Lockheed Martin Corporation reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Advanced Systems Supportability Engineering Technologies and Tools, Inc | $203.4K | 1 | VA | 2025-02-26 | 2025-02-26 |
| Parsons Corporation | $187.1K | 1 | VA | 2025-02-04 | 2025-02-04 |
| Actalent Services, LLC | $76.2K | 1 | MD | 2025-02-04 | 2025-02-04 |
| Craig Technologies | $54.1K | 1 | FL | 2025-02-10 | 2025-02-10 |
| Date | To | Amount | For |
|---|---|---|---|
| 2025-02-26 | Advanced Systems Supportability Engineering Technologies and Tools, Inc | $203.4K | CLIN 0001 BASE YR COST CLIN 0002 BASE YR ODC |
| 2025-02-04 | Parsons Government Services Inc. | $187.1K | CLIN 0001 BASE YR COST |
| 2025-02-04 | Actalent Services, LLC | $76.2K | CLIN 0001 BASE YR COST |
| 2025-02-10 | Craig Technical Consulting Inc | $54.1K | CLIN 0001 BASE YR COST |
12 actions since 2024-12-18. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-02 | P00012 | Funding only | $16.06M | FUNDING |
| 2026-05-20 | P00011 | Administrative change | $0 | ADMIN |
| 2026-02-23 | P00009 | Funding only | $5.04M | ENGINEERING AND TECHNICAL SERVICES |
| 2026-01-26 | P00008 | Funding only | $979.3K | ENGINEERING SERVICES FUNDING |
| 2025-12-10 | P00007 | Funding only | $9.86M | CLIN 0101 AND 0102 FUNDING |
| 2025-11-20 | P00006 | Option exercised | $3.50M | OPTION EXERCISE CLINS 0101 AND 0201 |
| 2025-09-24 | P00005 | Funding only | $226.3K | UPDATE RENT-FREE CLAUSE AND DE-OB/RE-OB UNDER CLIN 0001 SLINS |
| 2025-07-31 | P00004 | Administrative change | $0 | INCLUSION OF SUBCONTRACTOR JENKINS |
| 2025-06-23 | P00003 | Funding only | $20.10M | ENGINEERING AND TECHNICAL SERVICES/ODC FUNDING |
| 2025-04-24 | P00002 | Funding only | $7.05M | ENGINEERING AND TECHNICAL SERVICES |
| 2025-02-13 | P00001 | Funding only | $4.19M | ENGINEERING AND TECHNICAL SERVICES |
| 2024-12-18 | 0 | $9.46M | ENGINEERING AND TECHNICAL SERVICES |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗