N0017823F3013↗
Hii Technical Solutions Corporation received this contract from NSWC Dahlgren, Department of the Navy: $64.13M obligated so far for support- professional: engineering/technical. It runs to 2027-04-16, or to 2028-10-17 if every option is exercised.
Key facts · data as of Oct 25, 2026
- Recipient
- Hii Technical Solutions Corporation
- Awarding agency
- Department of the Navy (Department of Defense)
- Contracting office
- NSWC Dahlgren (N00178)
- Obligated to date
- $64.13M
- Potential value
- $241.52M
- Ends
- 2027-04-16
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award N0017823F3013, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_N0017823F3013_9700_N0017819D7772_9700
Hii Technical Solutions Corporation: all federal awards · Department of Defense: spending · NSWC Dahlgren: what it buys · The follow-on: recompete brief
SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT
Up for re-bid: ends 2027-04-16. Recompete brief → · H40 BMS Industry Day Documents ↗
What it is
- Product or service
- Support- Professional: Engineering/Technical (PSC R425)
- Industry
- Engineering Services (NAICS 541330)
- Contracting office
- NSWC Dahlgren (N00178)
- Competition
- Full and open competition · 3 offers received
- Pricing
- Cost plus fixed fee
- How it was bought
- Multiple-award IDIQ · under SeaPort-NxG (N0017819D7772)
- Solicitation
- N0017822R3014
- Where the work is
- Virginia Beach City, VA · district VA-02
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
2 subawards totaling $7.76M (12.1% of what was obligated), as Hii Technical Solutions Corporation reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Chenega Analytic Business Solutions, LLC | $7.70M | 1 | VA | 2023-09-22 | 2023-09-22 |
| G. C. Micro Corporation | $67.5K | 1 | CA | 2024-08-15 | 2024-08-15 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2023-09-22 | Chenega Analytic Business Solutions, LLC | $7.70M | PROVIDE SUPPORT SERVICES FOR THE SHORE-BASED TRAINING, ENGINEERING, AND DEVELOPMENT SUPPORT SERVICES (SBEDS) EFFORT. |
| 2024-08-15 | G. C. Micro Corporation | $67.5K | PURCHASE OF UNITY INDUSTRY SOFTWARE |
Every action
61 actions since 2023-04-13. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-12 | P00060 | Funding only | $1.68M | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2026-06-03 | P00059 | Funding only | $5.34M | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2026-05-15 | P00058 | Funding only | $194.3K | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2026-05-01 | P00057 | Funding only | -$1.23M | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2026-04-14 | P00056 | Funding only | $8.11M | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2026-03-26 | P00055 | Option exercised | $753.4K | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2026-03-11 | P00054 | Administrative change | $32.3K | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2026-02-11 | P00053 | Funding only | $200.6K | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2026-01-23 | P00052 | Funding only | $1.82M | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2026-01-14 | P00051 | Administrative change | $0 | THE SCOPE OF THE CONTRACT IS TO PROCURE CONTRACTOR SUPPORT SERVICES TO ACHIEVE THE ACCEPTABLE LEVELS OF REQUIREMENTS ANALYSIS, ENGINEERING, AND TECHNICAL SUPPORT. |
| 2025-12-12 | P00050 | Administrative change | -$13.6K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-11-17 | P00049 | Administrative change | $255.0K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-11-05 | P00048 | Administrative change | $1.02M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-10-24 | P00047 | Administrative change | -$99.0K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-09-26 | P00046 | Funding only | $17.0K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-09-23 | P00045 | Administrative change | $1.62M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-08-27 | P00044 | Administrative change | $2.03M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-08-07 | P00043 | Administrative change | -$961.9K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-07-15 | P00042 | Administrative change | $1.56M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-06-12 | P00041 | Funding only | $1.93M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-05-30 | P00040 | Administrative change | $992.8K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-05-16 | P00039 | Administrative change | $832.6K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-05-08 | P00038 | Administrative change | $373.6K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-04-24 | P00037 | Funding only | $2.16M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-04-16 | P00036 | Option exercised | $11.56M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-04-01 | P00035 | Funding only | -$3.95M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-03-24 | P00034 | Funding only | -$429.2K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-02-19 | P00033 | Funding only | $204.0K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-01-30 | P00032 | Funding only | $15.3K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-01-22 | P00031 | Funding only | $267.8K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2025-01-13 | P00030 | Funding only | $982.9K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-12-13 | P00029 | Funding only | $77.7K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-11-14 | P00028 | Funding only | $336.7K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-10-25 | P00027 | Funding only | -$118.1K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-10-08 | P00026 | Funding only | $510.0K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-09-26 | P00025 | Funding only | $408.9K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-09-11 | P00024 | Funding only | $46.8K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-08-28 | P00023 | Funding only | $1.35M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-08-14 | P00022 | Funding only | $2.25M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-07-19 | P00021 | Funding only | $9.83M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-07-11 | P00020 | Funding only | -$1.25M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-07-03 | P00019 | Funding only | $1.25M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-06-21 | P00018 | Funding only | $1.45M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-05-24 | P00017 | Funding only | $331.4K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-04-29 | P00016 | Funding only | $942.8K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-04-12 | P00015 | Option exercised | $632.2K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-04-04 | P00014 | Funding only | $17.0K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-03-22 | P00013 | Funding only | $696.7K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-02-15 | P00012 | Funding only | $35.2K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2024-02-02 | P00011 | Funding only | $140.5K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-12-21 | P00010 | Funding only | $32.4K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-12-04 | P00009 | Funding only | $525.2K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-11-15 | P00008 | Funding only | $40.0K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-10-11 | P00007 | Funding only | $332.7K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-09-27 | P00006 | Funding only | $3.07M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-09-07 | P00005 | Funding only | $335.1K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-08-18 | P00004 | Funding only | $1.38M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-08-11 | P00003 | Funding only | $1.06M | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-07-28 | P00002 | Funding only | $366.3K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-07-24 | P00001 | Funding only | $718.0K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |
| 2023-04-13 | 0 | $50.0K | SHORE BASED TRAINING SYSTEM ENGINEERING AND DEVELOPMENT SUPPORT |