ACTUATOR,HYDRAULIC-
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
3 subawards totaling $157.1K (8.2% of what was obligated), as Woodward HRT Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Superior Thread Rolling Co, LLC | $66.9K | 1 | CA | 2024-02-06 | 2024-02-06 |
| S & H Machine, Inc. | $55.3K | 1 | CA | 2024-03-18 | 2024-03-18 |
| Michlin Metals, Inc | $34.9K | 1 | IL | 2024-01-05 | 2024-01-05 |
| Date | To | Amount | For |
|---|---|---|---|
| 2024-02-06 | Superior Thread Rolling Co, LLC | $66.9K | CONTRACT BASED PER PC. |
| 2024-03-18 | S & H Machine, Inc. | $55.3K | PER PC. |
| 2024-01-05 | Michlin Metals, Inc | $34.9K | PER PC. |
6 actions since 2023-11-21. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-05-14 | P00005 | Supplemental agreement (work within scope) | $0 | ACTUATOR,HYDRAULIC- |
| 2025-10-28 | P00004 | Supplemental agreement (work within scope) | $0 | ACTUATOR,HYDRAULIC- |
| 2025-08-27 | P00003 | Administrative change | $0 | ACTUATOR,HYDRAULIC- |
| 2025-07-07 | P00002 | Supplemental agreement (work within scope) | -$500 | ACTUATOR,HYDRAULIC- |
| 2024-01-23 | P00001 | Supplemental agreement (work within scope) | $0 | ACTUATOR,HYDRAULIC- |
| 2023-11-21 | 0 | $1.92M | ACTUATOR,HYDRAULIC- |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗