4 actions since 2023-02-28. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-08-28 | P00004 | Supplemental agreement (work within scope) | $133.7K | N4008022F4687/P00004/PC-07 AND PC-08 |
| 2024-04-30 | P00003 | Supplemental agreement (work within scope) | $0 | N4008022F4687 SANTEE P00003 PCS 03,06 |
| 2023-03-10 | P00002 | Supplemental agreement (work within scope) | $56.7K | P00002 PC1 TEN ADDITIONAL MOORING PILES |
| 2023-02-28 | P00001 | Supplemental agreement (work within scope) | $51.1K | P00001 PC02 - GANGWAY AT MERCEDES WHARF |