DB P-1495, 5TH BATTALION, 10TH MARINES, HIGH MOBILITY ARTILLERY ROCKET SYSTEM, MCB, CAMP LEJEUNE
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
1 subaward totaling $37.8K (45.3% of what was obligated), as RQ Construction, LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Isoft Solutions, LLC | $37.8K | 1 | VA | 2022-11-22 | 2022-11-22 |
| Date | To | Amount | For |
|---|---|---|---|
| 2022-11-22 | Isoft Solutions, LLC | $37.8K | ALL AUDIO VISUAL SYSTEMS |
8 actions since 2022-10-04. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2024-05-30 | P00012 | Supplemental agreement (work within scope) | $0 | TIME ONLY |
| 2023-08-31 | P00011 | Administrative change | $0 | BASE PRICE |
| 2023-06-29 | P00010 | Supplemental agreement (work within scope) | $0 | TIME ONLY FOR CRANE SUBMITTAL REVIEW DELAY AND WEATHER DELAYS. |
| 2023-05-08 | P00009 | Supplemental agreement (work within scope) | $60.1K | REA |
| 2023-03-21 | P00008 | Supplemental agreement (work within scope) | $23.4K | 7 TON CRANE AND 10 TON CRANE CERTIFICATIONS: 1. ANNUAL CONDITION INSPECTION(ACI)/ INITIAL CERTIFICATION PER P307 2. QUADRENNIAL LOAD TEST PER P307 COMPLETED BY A 3RD PARTY. |
| 2023-03-17 | P00007 | Supplemental agreement (work within scope) | $1.11M | REA - FFE/AV |
| 2023-03-13 | P00006 | Administrative change | -$1.11M | ADMINISTRATION MOD TO DELETE LOAS/CLINS TO CLINS 0008 AND 0009. |
| 2022-10-04 | P00005 | Supplemental agreement (work within scope) | $0 | TIME-ONLY WEATHER DAYS. EXTEND THE CONTRACT COMPLETION DATE BY 19 CALENDAR DAYS FROM 19 MARCH 2023 TO 7 APRIL 2023 DUE TO WEATHER. |