WON 1610003, FY18 ERCIP P-889 ENERGY FACILITY IMPROVEMENTS, NBG. PROJECT IS TO PROVIDE MISCELLANEOUS REPAIRS AND UPGRADES TO EXISTING BUILDING SYSTEMS TO INCREASE ENERGY EFFICIENCY FOR 43 BUILDINGS/AREAS AT NAVAL BASE GUAM.
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
4 actions since 2024-03-08. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-09-19 | P00005 | Supplemental agreement (work within scope) | -$39.7K | ADDITIVE/DEDUCTIVE MODIFICATION TO DECREASE THE CONTRACT AMOUNT BY $39,745.94 FROM $5,713,582.85 TO $5,673,836.91. |
| 2024-08-10 | P00004 | Change order | $26.4K | PC05:PROVIDE NEW TRANSFORMER AND PANEL BOARD AT KILO WHARF AREA WITH AN ADDITIONAL 53 CALENDAR DAYS. |
| 2024-04-09 | P00003 | Change order | $25.8K | ADDITIVE WORK TO CORRECT CODE VIOLATION ON EXISTING ELECTRICAL CONDITION AND TO CHANGE/CORRECT PSC. |
| 2024-03-08 | P00002 | Change order | $3.5K | PC01 (-$17,430.17): ADDITIVE WORK FOR WATER HEATERS AND DEDUCTIVE WORK FOR ENERGY EFFICIENT LIGHTING REA ($20,907.18) FOR CIRCUIT BREAKERS NO-COST TIME MOD FOR 315 CALENDAR DAYS. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗