N4425524F4392↗
Absher Construction Co received this contract from Navfacsyscom Northwest, Department of the Navy: $147.15M obligated so far for construction of miscellaneous buildings. It runs to 2029-04-22.
Key facts · data as of Oct 23, 2026
- Recipient
- Absher Construction Co
- Awarding agency
- Department of the Navy (Department of Defense)
- Contracting office
- Navfacsyscom Northwest (N44255)
- Obligated to date
- $147.15M
- Potential value
- $149.38M
- Ends
- 2029-04-22
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award N4425524F4392, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_N4425524F4392_9700_N4425523D1700_9700
Absher Construction Co: all federal awards · Department of Defense: spending · Navfacsyscom Northwest: what it buys
P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA.
What it is
- Product or service
- Construction of Miscellaneous Buildings (PSC Y1JZ)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Navfacsyscom Northwest (N44255)
- Competition
- Full and open competition · 2 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under N4425523D1700
- Solicitation
- N4425521R4000
- Where the work is
- Kitsap, WA · district WA-06
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
8 subawards totaling $88.10M (59.9% of what was obligated), as Absher Construction Co reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Quanta Services, Inc. | $46.98M | 1 | WA | 2025-01-23 | 2025-01-23 |
| Pivetta Brothers Construction Inc | $19.47M | 1 | WA | 2025-01-28 | 2025-01-28 |
| Nuuco Electric Co | $17.29M | 1 | WA | 2025-01-14 | 2025-01-14 |
| Donald B. Murphy Contractors, Inc. | $2.59M | 1 | WA | 2025-01-10 | 2025-01-10 |
| Keystone Masonry, Inc | $822.3K | 1 | WA | 2025-02-10 | 2025-02-10 |
| Miller Sheetmetal Inc | $600.6K | 1 | WA | 2025-02-12 | 2025-02-12 |
| Queen City Sheet Metal and Roofing, Inc | $249.3K | 1 | WA | 2025-02-19 | 2025-02-19 |
| Architectural Sheet Metal Inc | $93.7K | 1 | WA | 2025-02-12 | 2025-02-12 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2025-01-23 | Potelco Inc | $46.98M | HIGH VOLTAGE: COMPLETE, MED VOLTAGE: SUPPLY |
| 2025-01-28 | Pivetta Brothers Construction Inc | $19.47M | CIVIL (COMPLETE) |
| 2025-01-14 | Nuuco Electric Co | $17.29M | DUCTBACK/GEAR SET |
| 2025-01-10 | Donald B. Murphy Contractors, Inc. | $2.59M | SHORING (COMPLETE) |
| 2025-02-10 | Keystone Masonry, Inc | $822.3K | MASONRY (COMPLETE) |
| 2025-02-12 | Miller Sheetmetal Inc | $600.6K | HVAC AND CONTROLS |
| 2025-02-19 | Queen City Sheet Metal and Roofing, Inc | $249.3K | ROOFING (COMPLETE) |
| 2025-02-12 | Architectural Sheet Metal Inc | $93.7K | FLASHING AND SHEETMETAL |
Every action
17 actions since 2024-09-16. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-22 | P00016 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FAR CLAUSE 52.222-90 INTO THE TASK ORDER |
| 2026-06-25 | P00015 | Supplemental agreement (work within scope) | $840.2K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 28 DESIGN DEFICIENCY CHANGES INTO THE SCOPE OF WORK. |
| 2026-05-12 | P00014 | Supplemental agreement (work within scope) | $333.8K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 24, PC-26, PC-27 DESIGN DEFICIENCY AND PC-25 UNFORESEEN CONDITION CHANGES INTO THE SCOPE OF WORK. |
| 2026-04-21 | P00013 | Supplemental agreement (work within scope) | $209.6K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 20 DESIGN DEFICIENCY AND PC-23 UNFORESEEN CONDITION CHANGES INTO THE SCOPE OF WORK. |
| 2026-03-20 | P00012 | Change order | $546.1K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 15, 18, 19, AND 21 DESIGN DEFICIENCY CHANGES INTO THE SCOPE OF WORK. |
| 2025-12-12 | P00011 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE DFARS 252.225-7013 DUTY-FREE ENTRY (AUG 2025) CLAUSE INTO TASK ORDER N4425524F4392. |
| 2025-12-10 | P00010 | Change order | $43.7K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 14 DESIGN DEFICIENCY, INTO THE SCOPE OF WORK. |
| 2025-11-06 | P00009 | Supplemental agreement (work within scope) | $174.9K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 12 DESIGN DEFICIENCY, INTO THE SCOPE OF WORK. |
| 2025-10-17 | P00008 | Change order | $80.7K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 13 UNFORESEEN CONDITIONS, INTO THE SCOPE OF WORK. |
| 2025-09-22 | P00007 | Change order | -$1.08M | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 03 DESIGN DEFICIENCY CHANGES, PC 04, PC 05, AND PC 06 VALUE ENGINEERING CHANGES, AND PC 11 UNFORESEEN CONDITIONS INTO THE SCOPE OF WORK. |
| 2025-09-10 | P00006 | Change order | $189.2K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 10 DESIGN DEFICIENCY CHANGES INTO THE SCOPE OF WORK. |
| 2025-08-28 | P00005 | Change order | $141.6K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 09 UNFORESEEN CONDITION CHANGES INTO THE SCOPE OF WORK. |
| 2025-06-25 | P00004 | Change order | $133.3K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 08 UNFORESEEN CONDITION CHANGES INTO THE SCOPE OF WORK. |
| 2025-06-18 | P00003 | Change order | $52.9K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 07 DESIGN DEFICIENCY CHANGES INTO THE SCOPE OF WORK. |
| 2025-06-12 | P00002 | Change order | $220.3K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE PROPOSED CHANGE (PC) 02 DESIGN DEFICIENCY CHANGES INTO THE SCOPE OF WORK. |
| 2024-10-16 | P00001 | Administrative change | $0 | EXTEND PERIOD OF PERFORMANCE FROM 04 APRIL 2029 TO 13 APRIL 2029 |
| 2024-09-16 | 0 | $145.27M | P891 SIOP SHIPYARD ELECTRICAL BACKBONE, PUGET SOUND NAVAL SHIPYARD (PSNS), BREMERTON, WA. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗