N4425525F0104↗
Tri Coast-Pac Tech JV LLLP received this contract from Navfacsyscom Northwest, Department of the Navy: $5.70M obligated so far for repair or alteration of ship construction and repair facilities. Its period of performance ended 2026-06-04.
Key facts · data as of Oct 28, 2026
- Recipient
- Tri Coast-Pac Tech JV LLLP
- Awarding agency
- Department of the Navy (Department of Defense)
- Contracting office
- Navfacsyscom Northwest (N44255)
- Obligated to date
- $5.70M
- Potential value
- $5.70M
- Ends
- 2026-06-04
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 28, 2026.
Cite this page: SpendQuery, Award N4425525F0104, data as of Oct 28, 2026, https://spendquery.com/award?id=CONT_AWD_N4425525F0104_9700_N4425523D1607_9700
Tri Coast-Pac Tech JV LLLP: all federal awards · Department of Defense: spending · Navfacsyscom Northwest: what it buys
THIS TASK ORDER FOR BUILDING 857 IS TO REMOVE, REPAIR, AND REPLACE THE EXISTING ROOF, ADD AN EXTERIOR STAIR ACCESS WITH RAILING AROUND THE PERIMETER OF THE BUILDING, AND RELOCATE THE NATURAL GAS LINES FROM ON TOP OF THE ROOF, TO INSIDE THE BUILDING.
What it is
- Product or service
- Repair or Alteration of Ship Construction and Repair Facilities (PSC Z2ED)
- Industry
- Commercial and Institutional Building Construction (NAICS 236220)
- Contracting office
- Navfacsyscom Northwest (N44255)
- Competition
- Full and open after exclusion of sources · 9 offers received
- Pricing
- Firm fixed price
- How it was bought
- Multiple-award IDIQ · under N4425523D1607
- Solicitation
- N4425525RB053
- Where the work is
- Kitsap, WA · district WA-06
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
1 action since 2025-06-04. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-06-04 | 0 | $5.70M | THIS TASK ORDER FOR BUILDING 857 IS TO REMOVE, REPAIR, AND REPLACE THE EXISTING ROOF, ADD AN EXTERIOR STAIR ACCESS WITH RAILING AROUND THE PERIMETER OF THE BUILDING, AND RELOCATE THE NATURAL GAS LINES FROM ON TOP OF THE ROOF, TO INSIDE THE BUILDING. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-28). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗