N5523625F5044↗

Epsilon Systems Solutions Inc received this contract from Southwest Regional Maint Center, Department of the Navy: $1.15M obligated so far for non-nuclear ship repair (west). Its period of performance ended 2026-05-22.

Key facts · data as of Oct 25, 2026

Recipient
Epsilon Systems Solutions Inc
Awarding agency
Department of the Navy (Department of Defense)
Contracting office
Southwest Regional Maint Center (N55236)
Obligated to date
$1.15M
Potential value
$1.15M
Ends
2026-05-22

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.

Cite this page: SpendQuery, Award N5523625F5044, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_N5523625F5044_9700_N0002422D4454_9700

C460A: USS SPRUANCCE (DDG-111) FY25 CMAV S003_DELIVERY ORDER

Delivery Order · Department of the Navy · to Epsilon Systems Solutions Inc (UEI T1GVZ5Z6K5L4) · data as of 2026-10-25

Obligated to date$1.15M11 actions
Current value$1.15Mwith options exercised
Period2025-09-08 → 2026-05-22current end date

What it is

Product or service
Non-Nuclear Ship Repair (West) (PSC J999)
Industry
Ship Building and Repairing (NAICS 336611)
Contracting office
Southwest Regional Maint Center (N55236)
Competition
Full and open after exclusion of sources · 3 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under N0002422D4454
Solicitation
N0002421R4427
Where the work is
San Diego, CA · district CA-52

Obligations by fiscal year

FY2025$971.8K
FY2026$175.6K

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

11 actions since 2025-08-04. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-06-02A00010Supplemental agreement (work within scope)-$660C460A_ INCORPORATE THE DEOBLIGATION OF LOE FUNDS FOR THE USS SPRUANCE (DDG-111).
2026-05-05A00009Supplemental agreement (work within scope)$0C460A_INCORPORATE ADMINISTRATIVE CHANGE TO DELIVERY DATE FOR USS SPRUANCE (DDG-111)
2026-01-29A00008Supplemental agreement (work within scope)$30.0KC460A_INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN THE WORK SPECIFICATION PACKAGE FOR USS SPRUANCE (DDG-111)
2025-11-13A00007Supplemental agreement (work within scope)$0C460A_INCORPORATE ADMINISTRATIVE CHANGE TO DELIVERY DATE FOR USS SPRUANCE (DDG-111) FY25 CONTINUOUS MAINTENANCE
2025-11-05A00006Supplemental agreement (work within scope)$77.1KC460A_INCORPORATE ADMINISTRATIVE CHANGE TO DELIVERY DATE AND FULLY FUND DELAY AND DISRUPTION FOR USS SPRUANCE (DDG-111)
2025-11-04A00005Supplemental agreement (work within scope)$96.0KC460A_INCORPORATE ADDITIONAL REPAIRS TO THE WORK SPECIFICATION PACKAGE AND INCORPORATE ADMINISTRATIVE CHANGE FOR USS SPRUANCE (DDG-111)
2025-10-24A00004Supplemental agreement (work within scope)$0C460A_INCORPORATE ADMINISTRATIVE CHANGE TO DELIVERY DATE FOR USS SPRUANCE (DDG-111)
2025-10-22A00003Supplemental agreement (work within scope)-$27.0KCODE 460A_REMOVE REPAIRS FROM THE ORIGINAL WORK SPECIFICATION PACKAGE FOR USS SPRUANCE (DDG-111) FY25 S003
2025-09-30A00002Supplemental agreement (work within scope)$78.9KC460A: TO COMPENSATE CONTRACTOR FOR GOVERNMENT-CAUSED DELAY AND DISRUPTION UNDER CFR 056 & 057 FOR THE USS SPRUANCE (DDG-111)FY25 CMAV S003
2025-09-16A00001Supplemental agreement (work within scope)$294.0KC460A: INCORPORATE ADDITIONAL REPAIRS TO THE WORK SPECIFICATION PACKAGE AND INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN THE ORIGINAL WORK SPECIFICATION FOR USS SPRUANCE (DDG-111) FY25 CMAV S003
2025-08-040$598.9KC460A: USS SPRUANCCE (DDG-111) FY25 CMAV S003_DELIVERY ORDER

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗