CODE 460C/ CVN ELEVATOR SUPPORT UNIT TASK ORDER
Up for re-bid: ends 2027-03-12. Recompete brief → · Preservation, Hull, Electrical/Electronic Repairs of the USS SOMERSET (LPD-25) Trailerable Boats 7MRX0816, 11MRX1002 ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
4 subawards totaling $712.7K (3.3% of what was obligated), as Hii Fleet Support Group LLC reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Colonna'S Ship Yard, Incorporated | $364.4K | 1 | VA | 2025-01-28 | 2025-01-28 |
| Delphinus Engineering, Inc. | $165.6K | 1 | PA | 2025-01-27 | 2025-01-27 |
| Epsilon Systems Solutions Inc. | $137.3K | 1 | CA | 2025-01-27 | 2025-01-27 |
| Aerotek, Inc. | $45.4K | 1 | MD | 2025-01-27 | 2025-01-27 |
| Date | To | Amount | For |
|---|---|---|---|
| 2025-01-28 | Colonna'S Ship Yard, Incorporated | $364.4K | SHIP BUILDING AND REPAIRING |
| 2025-01-27 | Delphinus Engineering, Inc. | $165.6K | SHIP BUILDING AND REPAIRING |
| 2025-01-27 | Epsilon Systems Solutions, Inc. | $137.3K | SHIP BUILDING AND REPAIRING |
| 2025-01-27 | Aerotek, Inc. | $45.4K | SHIP BUILDING AND REPAIRING |
14 actions since 2025-01-13. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-23 | P00013 | Additional work (new agreement) | $371.4K | INCORPORATE AND OBLIGATE NEW WORK |
| 2026-06-11 | P00012 | Supplemental agreement (work within scope) | $1.68M | INCORPORATE AND OBLIGATE WORK WITHIN SCOPE |
| 2026-05-06 | A00011 | Supplemental agreement (work within scope) | $7.85M | CODE 460C - MODIFICATION FOR LABOR SUPPORT FOR EXTENSION |
| 2026-02-26 | A00010 | Supplemental agreement (work within scope) | $5.6K | CODE 460C: MODIFICATION TO INCORPORATE MISSING COST |
| 2026-01-23 | A00009 | Supplemental agreement (work within scope) | $2.85M | CODE 460C: MODIFICATION TO INCORPORATE REVISED SOW |
| 2026-01-13 | A00008 | Administrative change | $0 | CODE 460C: MODIFICATION TO INCORPORATE PERIOD OF PERFORMANCE EXTENSION |
| 2025-12-31 | A00007 | Supplemental agreement (work within scope) | $0 | CODE 460C, MODIFICATION TO INCORPORATE REALIGNMENT OF FUNDING |
| 2025-11-03 | A00006 | Supplemental agreement (work within scope) | $0 | CODE 460C, MODIFICATION TO INCORPORATE WORK SCOPE TO STATEMENT OF WORK AT NO COST |
| 2025-09-18 | A00005 | Supplemental agreement (work within scope) | $90.4K | CODE 460C. TO INCORPORATE GROWTH WORK IN ALIGNMENT WITH THE STATEMENT OF WORK. |
| 2025-09-05 | A00004 | Supplemental agreement (work within scope) | $351.8K | CODE 460C. TO SUPPORT GROWTH WORK DESCRIBED IN THE STATEMENT OF WORK. |
| 2025-07-30 | A00003 | Administrative change | $0 | CODE 460C, ADMINSITRATIVE MODIFICATION TO CORRECT LINE OF ACCOUNTING |
| 2025-07-25 | A00002 | Supplemental agreement (work within scope) | $634.9K | C460C, MODIFICATION TO PROVIDE LABOR, MATERIALS, AND OTHER DIRECT COSTS TO SUPPORT GROWTH WORK |
| 2025-07-23 | A00001 | Supplemental agreement (work within scope) | $125.0K | CODE 460C, MODIFICATION TO INCORPORATE LABOR, MATERIALS, AND OTHER DIRECT COSTS |
| 2025-01-13 | 0 | $7.33M | CODE 460C/ CVN ELEVATOR SUPPORT UNIT TASK ORDER |