T.O. UNDER IDIQ FOR A-E SERVICES FOR A DESIGN-BID-BUILD CONSTRUCTION PACKAGE FOR FY26 SPECIAL PROJECT RM19-0326 REPLACE DRY DOCK NO. 4 CAISSON, JBPHH, HI
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
6 subawards totaling $864.5K (19.4% of what was obligated), as Moffatt & Nichol - Burns & Mcdonnell Hawaii reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Heger Dry Dock Inc | $501.5K | 1 | MA | 2024-08-26 | 2024-08-26 |
| Myounghee Noh & Associates, L.L.C. | $115.4K | 1 | HI | 2024-08-29 | 2024-08-29 |
| Tourney Consulting Group LLC | $76.6K | 1 | MI | 2024-08-26 | 2024-08-26 |
| J. Uno & Associates, Inc. | $69.2K | 1 | HI | 2024-08-28 | 2024-08-28 |
| Earth Mechanics, Inc. | $59.4K | 1 | CA | 2024-08-25 | 2024-08-25 |
| Crawford Consulting Services, Inc. | $42.3K | 1 | PA | 2024-08-29 | 2024-08-29 |
| Date | To | Amount | For |
|---|---|---|---|
| 2024-08-26 | Heger Dry Dock Inc | $501.5K | NAVAL ARCHITECTURAL DESIGN AND / OR ENGINEERING SERVICES |
| 2024-08-29 | Myounghee Noh & Associates, L.L.C. | $115.4K | PROVIDE ENVIRONMENTAL, HAZMAT SAMPLING, TESTING, AND REPORTING DESIGN SERVICES |
| 2024-08-26 | Tourney Consulting Group LLC | $76.6K | PROVIDE CORROSION PROTECTION (ANODES AND COATINGS) DESIGN AND / OR ENGINEERING SERVICES |
| 2024-08-28 | J. Uno & Associates, Inc. |
2 actions since 2024-06-25. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-12-22 | P00001 | Supplemental agreement (work within scope) | $624.6K | T.O. MODIFICATION FOR SPECIAL PROJECT RM19-0326 REPLACE CAISSON DRY DOCK 4 (DD4) CAISSON, SIOP, PHNSY, JBPHH, HI |
| 2024-06-25 | 0 | $3.84M | T.O. UNDER IDIQ FOR A-E SERVICES FOR A DESIGN-BID-BUILD CONSTRUCTION PACKAGE FOR FY26 SPECIAL PROJECT RM19-0326 REPLACE DRY DOCK NO. 4 CAISSON, JBPHH, HI |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| $69.2K |
| COST ESTIMATING AND COST CONSULTATION DESIGN SERVICES |
| 2024-08-25 | Earth Mechanics, Inc. | $59.4K | GEOTECHNICAL AND SEISMIC ENGINEERING (SEISMIC DESIGN CRITERIA AND RESPONSE SPECTRA) |
| 2024-08-29 | Crawford Consulting Services, Inc. | $42.3K | CONSTRUCTION SCHEDULING; COST AND SCHEDULE RISK ANALYSIS (CSRA) DESIGN SERVICES |