N6274221F0302↗
Mndpi Pacific JV received this contract from Navfacsyscom Pacific, Department of the Navy: $1.20M obligated so far for architect and engineering- construction: ship construction and repair facilities. It runs to 2027-07-01.
Key facts · data as of Oct 26, 2026
- Recipient
- Mndpi Pacific JV
- Awarding agency
- Department of the Navy (Department of Defense)
- Contracting office
- Navfacsyscom Pacific (N62742)
- Obligated to date
- $1.20M
- Potential value
- $120.18M
- Ends
- 2027-07-01
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 26, 2026.
Cite this page: SpendQuery, Award N6274221F0302, data as of Oct 26, 2026, https://spendquery.com/award?id=CONT_AWD_N6274221F0302_9700_N6274220D0004_9700
Mndpi Pacific JV: all federal awards · Department of Defense: spending · Navfacsyscom Pacific: what it buys · The follow-on: recompete brief
X004 P-209 DRY DOCK #3 REPLACEMENT - PHASE 1 DESIGN AWARD. AE TASK ORDER.
Up for re-bid: ends 2027-07-01. Recompete brief →
What it is
- Product or service
- Architect and Engineering- Construction: Ship Construction and Repair Facilities (PSC C1ED)
- Industry
- Engineering Services (NAICS 541330)
- Contracting office
- Navfacsyscom Pacific (N62742)
- Competition
- Full and open competition
- Pricing
- Firm fixed price
- How it was bought
- Single-award IDIQ · under N6274220D0004
- Where the work is
- Honolulu, HI · district HI-01
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
10 subawards totaling $996.2K (82.7% of what was obligated), as Mndpi Pacific JV reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Controlpoint Surveying Inc | $219.7K | 1 | HI | 2023-02-14 | 2023-02-14 |
| Manson / Sea Engineering JV | $211.2K | 1 | HI | 2022-10-19 | 2022-10-19 |
| Burns & Mcdonnell, Inc. | $149.3K | 1 | VA | 2023-03-24 | 2023-03-24 |
| MK Engineers, LTD. | $139.7K | 2 | HI | 2022-10-17 | 2023-03-21 |
| Mustang Acquisition Holdings Inc. | $106.5K | 1 | HI | 2023-03-21 | 2023-03-21 |
| Pacific Cost Engineering LLC | $60.5K | 1 | HI | 2023-01-23 | 2023-01-23 |
| Insynergy Engineering Inc | $41.6K | 1 | HI | 2023-03-21 | 2023-03-21 |
| Wilson Okamoto Corporation | $37.4K | 1 | HI | 2023-03-20 | 2023-03-20 |
| Geolabs Inc | $30.4K | 1 | HI | 2022-12-19 | 2022-12-19 |
The largest single subawards
| Date | To | Amount | For |
|---|---|---|---|
| 2023-02-14 | Controlpoint Surveying Inc | $219.7K | SURVEY SERVICES |
| 2022-10-19 | Sea Engineering Inc | $211.2K | SUPPORT SEDIMENT SAMPLING WITHIN PEARL HARBOR€„¢S FUTURE DRY DOCK 5 PROJECT AREA |
| 2023-03-24 | Burns & Mcdonnell Engineering Company, Inc. | $149.3K | DESIGN AND / OR ENGINEERING SERVICES TO MODIFY DESIGN OF THE EAST SUBSTATION AND CHILLED WATER SYSTEM |
| 2023-03-21 | Stantec Consulting Services Inc. | $106.5K | DESIGN AND / OR ENGINEERING SERVICES TO MODIFY DESIGN OF THE CHILLED WATER SYSTEM |
| 2023-03-21 | MK Engineers, LTD. | $94.8K | ELECTRICAL SCOPE OF WORK-ADDITIONAL SERVICES FOR EAST SUBSTATION Z2 OPTION |
| 2023-01-23 | Pacific Cost Engineering LLC | $60.5K | PROJECT COST CONSULTANT; DETAILED ESTIMATES FOR STRUCTURAL, ARCHITECTURAL AND CIVIL WORK |
| 2022-10-17 | MK Engineers, LTD. | $44.9K | CONDUCT PRELIMINARY FIELD INVESTIGATION OF STATIONS B AND D AND THE MANHOLES |
| 2023-03-21 | Insynergy Engineering Inc | $41.6K | FIRE PROTECTION AND COMMUNICATION DESIGN AND / OR ENGINEERING SERVICES TO MODIFY DESIGN OF THE EAST SUBSTATION |
| 2023-03-20 | Wilson Okamoto Corporation | $37.4K | DESIGN AND / OR ENGINEERING SERVICES TO MODIFY DESIGN OF THE EAST SUBSTATION Z2 OPTION |
| 2022-12-19 | Geolabs Inc | $30.4K | GEOTECHNICAL ENGINEERING SERVICES |
Every action
4 actions since 2022-11-10. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-12-10 | P00011 | Supplemental agreement (work within scope) | $0 | CONTRACT NO. N62742-20-D-0004; TASK ORDER NO. N6274221F0302; MODIFICATION NO. P00011; EXTEND CCD TO 01 JULY 2027 |
| 2024-09-04 | P00010 | Supplemental agreement (work within scope) | $0 | NO-COST MODIFICATION TO EXTEND PERIOD OF PERFORMANCE TO 31 DECEMBER 2025 FOR TASK ORDER N6274221F0302 UNDER CONTRACT N62742-20-D-0004 |
| 2023-02-28 | P00009 | Supplemental agreement (work within scope) | $1.20M | FY23 MCON PROJECT P-209 DRY DOCK 3 REPLACEMENT, JOINT BASE PEARL HARBOR-HICKAM, HAWAII. |
| 2022-11-10 | P00008 | Supplemental agreement (work within scope) | $0 | N62742-20-D-0004-N6274221F0302 FY23 MCON PROJECT P-209 DRY DOCK 3 REPLACEMENT, JOINT BASE PEARL HARBOR-HICKAM, HAWAII. MODIFICATION P00008 NO COST TIME EXTENSION TO 31 DEC 2023. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-26). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗