Pacific Rim Constructors Inc received this contract from Navfacsyscom Pacific, Department of the Navy: $88.27M obligated so far for construction of other administrative facilities and service buildings. It runs to 2026-12-30.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award N6274223C1301, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_N6274223C1301_9700_-NONE-_-NONE-
Pacific Rim Constructors Inc: all federal awards · Department of Defense: spending · Navfacsyscom Pacific: what it buys · The follow-on: recompete brief
CONTRACT N62742-23-C-1301, J-301 GOJ-CONSOLIDATED HEADQUARTERS, U.S. NAVSUPPACT, MARINE CORPS BASE GUAM
Up for re-bid: ends 2026-12-30. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
9 actions since 2022-12-19. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-03-13 | P00008 | Administrative change | -$42.0K | J-301 GOJ - CONSOLIDATED HEADQUARTERS, US NAVSUPPACT MCB GUAM IS MODIFIED TO ASSESS LIQUIDATED DAMAGES FOR LABOR VIOLATIONS. |
| 2025-12-31 | P00007 | Supplemental agreement (work within scope) | $5.80M | PC000006 SUSPENSION OF WORK DEMOBILIZATION COST PC000008 ADA COMPLIANCE CURB AND SIDEWALKPC000009 CONSTRUCTION SECURITY PLAN (CSP) IMPLEMENTATIONPC000010 DESCOPE REQUIREMENT DUE TO THE CSP IMPLEMENTATIONPC000012 REPLACE ELECTRIFIED LOCKSETS |
| 2025-04-01 | P00006 | Change order | $278.8K | PC00005 SECURITY FENCE |
| 2025-03-26 | P00005 | Change order | $428.2K | PC 000007 GATE GUARD EXTENSION TO 31DEC25 |
| 2024-09-06 | P00004 | Supplemental agreement (work within scope) | $5.09M | PC 000004 FURNITURES FIXTURES AND EQUIPMENT |
| 2024-04-30 | P00003 | Change order | $11.9K | BASE ITEM (AWARDED) |
| 2024-03-09 | P00002 | Change order | $2.19M | PC000001-ADDITIONAL MASS EXCAVATION FOR ADDITIONAL 2,775 CUBIC YARDS OF SOIL TO BE EXCAVATED DUE TO UNSUITABLE SOILS FOUND WITHIN BUILDING FOOTPRINT. ADDITIONAL SOIL WITH SUITABLE STRENGTH FOR THE BUILDING LOAD WILL BE PLACED IN THE EXCAVATED AREA. |
| 2024-03-05 | P00001 | Change order | $516.1K | PROPOSED CHANGE PC000002 OPEN BOTH GATES TO THROUGH TRAFFIC AT BOTH THE MAIN GATE AND COMMERCIAL GATES. |
| 2022-12-19 | 0 | $74.00M | CONTRACT N62742-23-C-1301, J-301 GOJ-CONSOLIDATED HEADQUARTERS, U.S. NAVSUPPACT, MARINE CORPS BASE GUAM |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗