SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
1 subaward totaling $65.0K (1.7% of what was obligated), as VT Milcom Inc. reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
18 actions since 2023-02-06. Each is a modification or amendment with the money it added or took back.
Date
Modification
Kind
Amount
What the agency wrote
2026-05-28
P00017
Supplemental agreement (work within scope)
$363.0K
C4I HARDWARE SOFTWARE INSTALLATIONS AND SOVT SUPPORT FOR LISTED ALTERATIONS ONBOARD USS NORTH DAKOTA SSN-784
2025-07-18
P00016
Administrative change
$194.6K
BY MUTUAL AGREEMENT FAR 43.103(A)(3)
2025-05-08
P00015
Administrative change
$171.0K
INCREASE CEILING FUNDS AND PROVIDE FUNDING TO FINALIZE CORNS.
2025-04-15
P00014
Administrative change
$480.8K
INCREASE CEILING FUNDS AND PROVIDE FUNDING TO FINALIZE CORNS.
2025-04-02
P00013
Administrative change
$344.1K
INCREASE CEILING FUNDS AND PROVIDE FUNDING TO FINALIZE CORNS.
2025-01-27
P00012
Administrative change
$249.0K
INCREASE CEILING FUNDS AND PROVIDE FUNDING TO FINALIZE CORNS.
2024-12-06
P00011
Administrative change
$7.1K
INCREASE CEILING FUNDS AND PROVIDE FUNDING TO FINALIZE CORNS.
2024-10-08
P00010
Administrative change
$6.6K
INCREASE CEILING FUNDS AND PROVIDE FUNDING TO FINALIZE CORNS.
2024-08-22
P00009
Administrative change
$97.8K
INCREASE CEILING FUNDS AND PROVIDE FUNDING TO FINALIZE CORNS.
2024-08-07
P00008
Administrative change
$82.6K
INCREASE CEILING FUNDS AND PROVIDE FUNDING TO FINALIZE CORNS.
2024-06-10
P00007
Administrative change
$18.7K
INCREASE CEILING FUNDS AND PROVIDE FUNDING TO FINALIZE CORNS.
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
2024-05-30
P00006
Administrative change
$54.2K
INCREASE CEILING AND FUNDING TO ADJUDICATE CORNS FOR INSTALLATION OF C4I COMMUNICATION UPGRADE AND ELECTRONIC SECURITY SYSTEMS (ESS) AT VARIOUS SITES.
2024-02-27
P00005
Administrative change
$49.0K
INCREASE CEILING AND FUNDING TO ADJUDICATE CORNS FOR INSTALLATION OF C4I COMMUNICATION UPGRADE AND ELECTRONIC SECURITY SYSTEMS (ESS) AT VARIOUS SITES.
2024-02-07
P00004
Administrative change
-$321.0K
DECREASE CEILING FUNDS TO FINALIZE CORNS.
2023-11-06
P00003
Administrative change
$11.7K
INCREASE CEILING AND FUNDING TO ADJUDICATE CORNS FOR INSTALLATION OF C4I COMMUNICATION UPGRADE AND ELECTRONIC SECURITY SYSTEMS (ESS) AT VARIOUS SITES.
2023-05-01
P00002
Administrative change
$223.4K
ADMIN MODIFICATION
2023-04-20
P00001
Option exercised
$667.8K
INCREASE CEILING AND FUNDING TO ADJUDICATE CORNS FOR INSTALLATION OF C4I COMMUNICATION UPGRADE AND ELECTRONIC SECURITY SYSTEMS (ESS) AT VARIOUS SITES.