SERVICES FOR THE PURSUIT OF DEPLOYING PROJECT BLUE AS AN UNCOMPROMISED INFORMATION SYSTEM (IS) AND USING A MODEL-BASED SYSTEMS ENGINEERING APPROACH TO IDENTIFY THE MOST APPROPRIATE IS DESIGN FOR THE PROGRAM
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
6 actions since 2023-05-10. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-06-11 | P00005 | Funding only | -$13.5K | THE CONTRACTOR SHALL APPLY GENERALLY ACCEPTED PRACTICES FROM SYSTEMS ENGINEERING AND SOFTWARE ENGINEERING TO DOCUMENT THERESEARCH PRODUCTS AND SOLUTIONS PRODUCED DURING THIS PROJECT. |
| 2024-04-26 | P00004 | Funding only | $1.44M | THE CONTRACTOR SHALL APPLY GENERALLY ACCEPTED PRACTICES FROM SYSTEMS ENGINEERING AND SOFTWARE ENGINEERING TO DOCUMENT THE RESEARCH PRODUCTS AND SOLUTIONS PRODUCED DURING THIS PROJECT. |
| 2024-04-10 | P00003 | Funding only | -$1.44M | THE CONTRACTOR SHALL APPLY GENERALLY ACCEPTED PRACTICES FROM SYSTEMS ENGINEERING AND SOFTWARE ENGINEERING TO DOCUMENT THE RESEARCH PRODUCTS AND SOLUTIONS PRODUCED DURING THIS PROJECT. |
| 2023-08-07 | P00002 | Administrative change | $0 | THE CONTRACTOR SHALL SUPPORT PMS397S PURSUIT OF DEPLOYING PROJECT BLUE AS AN UNCOMPROMISABLE BY APPLYING A SOCIOTECHNICAL MODEL BASED SYSTEMS ENGINEERING APPROACH TO DETERMINE THE MOST APPROPRIATE IS DESIGN FOR THE PROGRAM. |
| 2023-05-25 | P00001 | Administrative change | $0 | SERVICES FOR THE PURSUIT OF DEPLOYING PROJECT BLUE AS AN UNCOMPROMISED INFORMATION SYSTEM (IS) AND USING A MODEL-BASED SYSTEMS ENGINEERING APPROACH TO IDENTIFY THE MOST APPROPRIATE IS DESIGN FOR THE PROGRAM |
| 2023-05-10 | 0 | $4.20M | SERVICES FOR THE PURSUIT OF DEPLOYING PROJECT BLUE AS AN UNCOMPROMISED INFORMATION SYSTEM (IS) AND USING A MODEL-BASED SYSTEMS ENGINEERING APPROACH TO IDENTIFY THE MOST APPROPRIATE IS DESIGN FOR THE PROGRAM |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗