The Boeing Company received this contract from Naval Air Warfare Center, Department of the Navy: $3.83M obligated so far for modification of equipment- aircraft components and accessories. It runs to 2027-04-03.
Key facts · data as of Oct 23, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.
Cite this page: SpendQuery, Award N6893623F0374, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_N6893623F0374_9700_N6893623D0001_9700
The Boeing Company: all federal awards · Department of Defense: spending · Naval Air Warfare Center: what it buys · The follow-on: recompete brief
TASK ORDER FOR FLIGHT PLAN SUPPORT UNDER CLIN 0002 OF THE BASIC IDIQ CONTRACT
Up for re-bid: ends 2027-04-03. Recompete brief → · NAWCWD California Contracting/Acquisition/Procurement (CCAP) Industry Days Expo ↗
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
12 actions since 2023-05-04. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-06-15 | P00011 | Funding only | $60.0K | FLIGHT PLAN ORDER |
| 2026-05-13 | P00010 | Administrative change | $0 | FLIGHT PLAN ORDER |
| 2026-04-01 | P00009 | Supplemental agreement (work within scope) | $999.6K | FLIGHT PLAN SUPPORT YEAR 4 |
| 2025-11-05 | P00008 | Supplemental agreement (work within scope) | -$170.5K | ORDER FOR FLIGHT PLAN SUPPORT |
| 2025-09-17 | P00007 | Supplemental agreement (work within scope) | $100.0K | SUPPORT FOR THE F/A-18E/F & EA-18G CAPABILITY DEVELOPMENT PLAN |
| 2025-07-24 | P00006 | Funding only | $463.0K | F/A-18 & EA-18G SYSTEM CONFIGURATION SET (SCS) - FLIGHT PLAN SUPPORT |
| 2025-04-04 | P00005 | Supplemental agreement (work within scope) | $500.0K | THESE EFFORTS ARE TO DEFINE THE F/A-18E/F & EA-18G CAPABILITY DEVELOPMENT PLAN, CALLED THE FLIGHT PLAN, AND DEFINE THE DEVELOPMENT PROGRAM EFFORTS NECESSARY TO TRANSITION THE FLIGHT PLAN TO THE WARFIGHTER. |
| 2025-02-25 | P00004 | Supplemental agreement (work within scope) | -$429.0K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS. |
| 2024-05-02 | P00003 | Supplemental agreement (work within scope) | $1.17M | THIS MODIFICATION INCREASE THE LEVEL OF EFFORT ON THE FLIGHT PLAN TASK ORDER. |
| 2024-01-31 | P00002 | Administrative change | $0 | THIS MODIFICATION UPDATES THE NAVAIR CLAUSE FOR ORDER FLIGHT PLAN CLIN 0002. |
| 2023-07-23 | P00001 | Administrative change | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ADD DFARS CLAUSE 252.232-7006 - WIDE AREA WORKFLOW (WAWF) PAYMENT INSTRUCTIONS TO THE TASK ORDER. |
| 2023-05-04 | 0 | $1.13M | TASK ORDER FOR FLIGHT PLAN SUPPORT UNDER CLIN 0002 OF THE BASIC IDIQ CONTRACT |