SSP ADDITION
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
33 actions since 2022-12-30. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-01-23 | P00032 | Administrative change | $0 | THE PURPOSE OF THIS UNILATERAL MODIFICATION IS TO INCORPORATE NEGOTIATED MUTUALLY UNDERSTOOD CHANGES RELATED TO PC 078 FOR THE AMOUNT OF $30,375.00 AND ZERO DAYS. THE CCD HAS NOT CHANGED. |
| 2025-12-23 | P00031 | Change order | $30.4K | THE PURPOSE OF THIS UNILATERAL MODIFICATION IS TO INCORPORATE NEGOTIATED MUTUALLY UNDERSTOOD CHANGES RELATED TO PC 078 FOR THE AMOUNT OF $30,375.00 AND ZERO DAYS. THE CCD HAS NOT CHANGED. |
| 2025-12-05 | P00030 | Change order | $26.6K | THE PURPOSE OF THIS UNILATERAL MODIFICATION IS TO INCORPORATE NEGOTIATED CHANGES RELATED TO PC 065 AND PC 084 FOR THE AMOUNT OF $26,644.00 AND ZERO DAYS. THE CCD HAS NOT CHANGED. NOTICE TO PROCEED WAS GIVEN VERBALLY ON 05 NOVEMBER 2025. |
| 2025-10-16 | P00029 | Change order | $605.7K | THE PURPOSE OF THIS UNILATERAL MODIFICATION IS TO INCORPORATE NEGOTIATED CHANGES RELATED TO PCS 082 FOR THE AMOUNT OF $605,705.00 AND 124 ADDITIONAL DAYS TO THE NAVSEA CCD. THE CCD IS HEREBY CHANGED FROM 19 AUGUST 2025 TO 22 DECEMBER 2025. |
| 2025-09-29 | P00028 | Supplemental agreement (work within scope) | $7.4K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE NEGOTIATED CHANGES RELATED TO PCS 085 FOR THE NEGOTIATED MUTUALLY AGREED AMOUNT OF $7,355.00 AND ZERO ADDITIONAL DAYS TO THE BOD OF SSP OR THE CCD. |
| 2025-09-03 | P00027 | Supplemental agreement (work within scope) | $28.8K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE NEGOTIATED CHANGES RELATED TO PCS 077, 079 AND 080 FOR THE NEGOTIATED MUTUALLY AGREED AMOUNT OF $28,755.00 AND ZERO ADDITIONAL DAYS TO THE BOD OF SSP OR THE CCD. |
| 2025-08-04 | P00026 | Change order | $1.73M | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE NEGOTIATED CHANGES RELATED TO PCS 038, 046, 047, 056, 067, 069, 070, 074, AND 075 FOR THE NEGOTIATED MUTUALLY AGREED AMOUNT OF $1,733,661.00 AND ZERO ADDITIONAL DAYS TO THE BOD OF SSP OR THE CCD. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-09-30). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗
| 2025-06-11 | P00025 | Supplemental agreement (work within scope) | $1.63M | SSP ADDITION - TO INCORPORATE CHANGES AS RELATED TO PC 050, G1 GIRDERS AND PC 064, MC2 CHECKERED PLATE, FOR ADDITIONS AT SSP AND NAVSEA, NSB, KINGS BAY, GA |
| 2025-03-27 | P00024 | Supplemental agreement (work within scope) | $269.7K | SSP ADDITION - WORK RELATED TO PCS 57,66,68,71,72,73. |
| 2025-03-26 | P00023 | Supplemental agreement (work within scope) | $2.47M | TO INCORPORATE CHANGES AS RELATED TO PC053A (ACQR 6068514) AND PC053B (ACQR 6077607) AS THEY RELATE TO THE FIRE WALL CHANGES FOR THE ADDITIONS AT SSP AND NAVSEA, NSB, KINGS BAY, GA |
| 2024-09-12 | P00022 | Change order | $429.2K | SSP ADDITION - INCORPORATE PC 034, CABLE TRAY REVISION, AND PC055 CONSTRUCT SHAFT WALL. |
| 2024-09-06 | P00021 | Supplemental agreement (work within scope) | $130.2K | SSP ADDITION - AWARD OF THE PLANNED MODIFICATION FOR CLIN 003 (FF&E) FOR SSP PORTION OF TASK ORDER (CLIN 001) AND CLIN 004 (FF&E) NAVSEA PORTION OF TASK ORDER (CLIN002). |
| 2024-08-22 | P00020 | Supplemental agreement (work within scope) | $237.8K | SSP ADDITION - INCORPORATE PC 044, STC TYPE D WALL BRACING AND PC 61 SPRAY FOAM APPLIED INSULATION. |
| 2024-07-24 | P00019 | Change order | $318.0K | SSP ADDITION - TO INCORPORATE ACQRS 6002315 FOR SSP AIR AND HYDRAULIC SYSTEMS, 6031092 FOR SAFETY GATE, 6060800 FOR HPU 3 AND 4 INTERFACE CONTROLS, 6060873 FOR CLOSED LOOP DEIONIZED SYSTEM, AND 6060810 STRUCTURAL STEEL AND CHECKERED PLATE |
| 2024-05-30 | P00018 | Change order | $30.3K | SSP ADDITION - TO INCORPORATE ACQR 6053442, FOR PC 041, NITROGEN PRE-CHARGE CAPABILITY AND ACQR 6031090, FOR PC 045, DUCTLESS MINI SPLIT. |
| 2024-04-12 | P00017 | Change order | $715.4K | SSP ADDITION - TO INCORPORATE ACQR 6038940, BASED ON NEGOTIATIONS HELD 20 AND 21 FEBRUARY 2024 FOR A MUTUALLY AGREED AMOUNT OF $715,434.24. |
| 2024-03-21 | P00016 | Change order | $80.3K | SSP ADDITION - INCORPORATE PC 033 AND PC 052, FOR P676 PROJECT, KINGS BAY, GA. |
| 2024-02-07 | P00015 | Supplemental agreement (work within scope) | $130.5K | SSP ADDITION - INCORPORATION OF PC 027 DELETE LAB ACOUSTICAL CEILING, PC 036 THE ADDITION OF FIRE DAMPERS, PC 037 NAVSEA BRIDGE CRANE REQUIREMENTS AND PC 049 WATERPROOFING AT NAVSEA WHSTT TRAINER PIT. |
| 2023-12-22 | P00014 | Change order | $112.6K | SSP ADDITION - INCORPORATE PC 040, FOR P676 PROJECT, KINGS BAY, GA |
| 2023-12-19 | P00013 | Supplemental agreement (work within scope) | $31.0K | SSP ADDITION - INCORPORATE PC 032 HPU 3 & 4 |
| 2023-12-13 | P00012 | Supplemental agreement (work within scope) | $31.0K | SSP ADDITION - INCORPORATE PC 018 FIRE-STOPPING FOR PROJECT P676, KINGS BAY GA. |
| 2023-12-06 | P00011 | Supplemental agreement (work within scope) | $61.7K | SSP ADDITION -INCORPORATE PC'S 014,016, 023, 025, AND 030, FOR PROJECT P676, KINGS BAY GA. |
| 2023-11-30 | P00010 | Administrative change | $27.4K | SSP ADDITION - INCORPORATE PC 026, FOR P676 PROJECT, KINGS BAY, GA. |
| 2023-10-30 | P00009 | Supplemental agreement (work within scope) | $214.3K | SSP ADDITION - PC'S 006, 019, 020, 022, AND 024, FOR P676 PROJECT, KINGS BAY, GA |
| 2023-10-19 | P00008 | Supplemental agreement (work within scope) | $72.0K | SSP ADDITION- ADD PC 10, A5, 29 AND 31 |
| 2023-09-27 | P00007 | Supplemental agreement (work within scope) | $51.7K | SSP ADDITION - INCORPORATE PC021 AND PC028 |
| 2023-08-24 | P00006 | Supplemental agreement (work within scope) | $21.6K | SSP ADDITION - INCORPORATE PC 07, PC 013, AND PC 017 |
| 2023-07-21 | P00005 | Supplemental agreement (work within scope) | $22.3K | SSP ADDITION - PC04, PC05, PC09, AND PC012 |
| 2023-07-07 | P00004 | Supplemental agreement (work within scope) | $11.0K | SSP ADDITION INCORPORATE PC001 DRAWINGS CONTAINED IN TTF P676 REVISION B FOR MC2 LEVEL 3 FOR TRAINING EQUIPMENT PC002 THE REMOVAL OF EXISTING TREE AND PC011 FUEL OIL VAULT CLEANING |
| 2023-06-13 | P00003 | Administrative change | $0 | SSP ADDITION - ADMINISTRATIVE MODIFICATION TO INCLUDE UPDATED ATTACHMENTS (SPEC SECTIONS AND REVISE SF85 TO SF86). |
| 2023-02-03 | P00002 | Supplemental agreement (work within scope) | $0 | SSP ADDITION - INCORPORATING THE CONFORMED SPECIFICATIONS AND DRAWINGS |
| 2023-01-03 | P00001 | Administrative change | $0 | SSP ADDITION |
| 2022-12-30 | 0 | $37.62M | SSP ADDITION |