SP060014C8292↗

American Water Operations and Maintenance, LLC received this contract from Dla Energy, Defense Logistics Agency: $35.47M obligated so far for utilities- water. It runs to 2064-11-25.

Key facts · data as of Oct 22, 2026

Recipient
American Water Operations and Maintenance, LLC
Awarding agency
Defense Logistics Agency (Department of Defense)
Contracting office
Dla Energy (SP0600)
Obligated to date
$35.47M
Potential value
$418.95M
Ends
2064-11-25

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 22, 2026.

Cite this page: SpendQuery, Award SP060014C8292, data as of Oct 22, 2026, https://spendquery.com/award?id=CONT_AWD_SP060014C8292_9700_-NONE-_-NONE-

IGF::OT::IGF CONTRACT AWARD FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION SYSTEMS LOCATED ON PICATINNY ARSENAL, NJ.

Definitive Contract · Defense Logistics Agency · to American Water Operations and Maintenance, LLC (UEI HQ4FB19HK6N8) · data as of 2026-10-22

Obligated to date$35.47M61 actions
Current value$418.95Mwith options exercised
Period2015-01-01 → 2064-11-25current end date

What it is

Product or service
Utilities- Water (PSC S114)
Industry
Water Supply and Irrigation Systems (NAICS 221310)
Contracting office
Dla Energy (SP0600)
Competition
Full and open competition · 2 offers received
Pricing
Fixed price with economic price adjustment
How it was bought
Standalone contract
Solicitation
SPE60012R0812
Where the work is
Camden, NJ · district NJ-01

Obligations by fiscal year

FY2023$7.96M
FY2024$9.16M
FY2025$7.97M
FY2026$10.38M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

61 actions since 2023-01-03. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-15P00162Administrative change$0TO INCORPORATE FAR CLAUSE 52.222-90, ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS- APRIL 2026, INTO SECTION I.6, OTHER CLAUSES, BY FULL TEXT. THIS INCORPORATION IS MADE IN ACCORDANCE WITH EXECUTIVE ORDER 14398.
2026-06-03P00161Supplemental agreement (work within scope)$37.5KAUTHORIZE AN EQUITABLE ADJUSTMENT IN THE AMOUNT OF $37,484.00 IN ACCORDANCE WITH H.12 DIFFERING SITE CONDITIONS FOR UNKNOWN CONDITIONS ENCOUNTERED DURING THE PERFORMANCE OF LEAD SERVICE LINE REPLACEMENT FOR FACILITIES ON PICATINNY ARSENAL, AS PREVIOUSLY…
2026-05-19P00160Funding only$4.07MTO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITIES SERVICES CHARGE FOR THE PERIOD OF APRIL 26, 2026 - OCTOBER 25, 2026.
2026-04-14P00159Supplemental agreement (work within scope)$2.22MTO AUTHORIZE AMERICAN WATER OPERATIONS AND MAINTENANCE TO INSTALL THE PHASE 1 WATER EXTENSION TO SERVICE A PROPOSED REDEVELOPMENT SITE AT PICATINNY ARSENAL AMMUNITION SUPPLY POINT.
2026-03-26P00158Administrative change$0CORRECT ADMINISTRATIVE ERRORS IN THE STATED CONTRACT OBLIGATION TOTALS FOR MODIFICATIONS P00136 THROUGH P00157.
2026-03-19P00157Funding only$678.4KTO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF MARCH 26, 2026 THROUGH APRIL 25, 2026.
2026-03-17P00156Change order$7.3KAUTHORIZE AN EQUITABLE ADJUSTMENT IN THE AMOUNT OF $7,279.63 IN ACCORDANCE WITH H.12 DIFFERING SITE CONDITIONS FOR ADDITIONAL COSTS INCURRED FOR THE RELOCATION OF THE SERVICE MAIN FOR BUILDING 30 AS PREVIOUSLY AWARDED ON CONTRACT MODIFICATION P00141
2026-01-26P00155Funding only$678.4KTHE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDING FOR THE PERFORMANCE PERIOD OF FEBRUARY 26, 2026 TO MARCH 25, 2026.
2025-11-26P00154Administrative change$0TO REVISE SECTION J, LIST OF ATTACHMENTS, TO REPLACE ATTACHMENT JA4 WAGE DETERMINATION IN ITS ENTIRETY FOR THE CONTRACT PERIOD EXTENDING FROM NOVEMBER 26, 2025 THROUGH NOVEMBER 25, 2026.
2025-11-25P00153Supplemental agreement (work within scope)$2.04MAPPLY ECONOMIC PRICE ADJUSTMENT (EPA) TO CONTRACT YEAR 12 AND FUND THE PERIOD OF NOVEMBER 26, 2025 TO FEBRUARY 25, 2026.
2025-11-17P00152Funding only$655.7KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICE CHARGE FOR THE PERIOD OF OCTOBER 26, 2025 THROUGH NOVEMBER 25, 2025.
2025-11-10P00151Administrative change$0THE PURPOSE OF THIS MODIFICATION IS TO UPDATE LANGUAGE IN SECTION G.2 AND G.4 OF THE CONTRACT.
2025-09-24P00150Administrative change$0THE PURPOSE OF THIS MODIFICATION IS AUTHORIZE A NO-COST EXTENSION TO THREE PROJECTS FOR REPLACEMENT OF GALVANIZED SERVICE LINES PREVIOUSLY FUNDED ON CLINS 1006, 1007, AND 1008.
2025-09-15P00149Administrative change$0TO REVISE SECTION J, LIST OF ATTACHMENTS, TO INCORPORATE THE 2025 WAGE DETERMINATION AT ATTACHEMENT JA4 WAGE DETERMINATION.
2025-08-11P00148Administrative change$0THIS MODIFICATION UPDATES SECTION I, CONTRACT CLAUSES IN ACCORDANCE WITH EXECUTIVE ORDER 14173 AND 14168.
2025-07-02P00147Funding only$1.31MTO PROVIDE TWO MONTHS OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF AUGUST 26, 2025 THROUGH OCTOBER 25, 2025.
2025-06-16P00146Administrative change$0AUTHORIZE A NO-COST EXTENSION TO THE PROJECT COMPLETION DATE AAL GALVANIZED SERVICE LINE REPLACEMENT VARIOUS BLDGS, INSIDE & OUTSIDE GALVANIZED LINE REPLACEMENT AND GALVANIZED SERVICE LINE REPLACEMENT PROJECTS PREVIOUSLY EXECUTED ON MOD P00135.
2025-05-07P00145Supplemental agreement (work within scope)$2.11MAPPLY ECONOMIC PRICE ADJUSTMENT TO THE UTILITY SERVICE CHARGE FOR CONTRACT YEAR 11 AND TO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF MAY 26, 2025 TO AUGUST 25, 2025.
2025-04-14P00144Funding only$631.8KTO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF APRIL 26, 2025 THROUGH MAY 25, 2025.
2025-02-06P00143Change order$17.5KTO AUTHORIZE AN EQUITABLE ADJUSTMENT IN ACCORDANCE WITH H.12 DIFFERENT SITE CONDITIONS FOR ADDITIONAL COSTS INCURRED FOR THE RELOCATION OF THE SERVICE MAIN FOR BUILDING 717.
2025-01-07P00142Funding only$1.90MTO PROVIDE THREE MONTHS OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF JAN 26, 2025 TO APRIL 25, 2025.
2024-12-10P00141Supplemental agreement (work within scope)$104.0KESTABLISHES CLIN 1101 FOR NEW SERVICES AT B30.
2024-12-10P00140Administrative change$0UPDATES CLIN 1006, CLIN 1007, AND CLIN 1008 AND CORRECTS ADMINISTRATIVE ERRORS FROM MODIFICATIONS P00137, P00138, AND P00139.
2024-11-13P00139Funding only$1.26MTO PROVIDE TWO MONTHS OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF NOV. 26, 2024 TO JAN. 25, 2025.
2024-10-10P00138Administrative change$0UPDATES DFARS 252.204-7012 AND DFARS 252.204-7020.
2024-10-10P00137Funding only$631.8KFUNDS THE PERFORMANCE PERIOD OF OCTOBER 26, 2024 - NOVEMBER 25, 2024.
2024-08-28P00136Supplemental agreement (work within scope)$284.3KAUTHORIZES RELOCATION OF WATER MAIN SERVICING BUILDING 717.
2024-08-16P00135Funding only$569.0KTO ESTABLISH AND FUND CLIN 1006, CLIN 1007 AND CLIN 1008 TO ADDRESSED REQUIRED CORRECTIONS FOR REGULATORY COMPLIANCE WITH THE US EPA'S LEAD AND COPPER RULE AND THE NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION'S LEAD SERVICE LINE REPLACEMENT BILL.
2024-08-08P00134Change order$1.8KAUTHORIZE AN EQUITABLE ADJUSTMENT DUE TO DIFFERING SITE CONNECTIONS DURING THE INSTALLATION OF A NEW SANITARY SEWER SERVICE FOR BUILDING 65.
2024-07-31P00133Supplemental agreement (work within scope)$233.3KTHE PURPOSE OF THIS MODIFICATION IS AUTHORIZE COMPLETION OF SYSTEM DEFICIENCY CORRECTIONS OF ASSETS AT BUILDINGS 636G 636F, 636E, 636 AND 643.
2024-05-21P00132Funding only$1.90MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE THREE MONTHS OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICE CHARGE FOR THE PERIOD OF PERFORMANCE JULY 26, 2024 TO OCT 25, 2024.
2024-05-07P00131Funding only$1.26MTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE TWO MONTHS OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICE CHARGE FOR THE PERIOD OF PERFORMANCE MAY 26, 2024 TO JULY 25, 2024.
2024-04-18P00130Administrative change$0THE PURPOSE OF THIS MODIFICATION IS TO CORRECT ADMINISTRATIVE ERRORS FROM MODIFICATION P000129.
2024-04-17P00129Funding only$631.8KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICE CHARGE FOR THE PERIOD OF PERFORMANCE APRIL 26, 2024 TO MAY 25, 2024.
2024-04-11P00128Funding only$631.8KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICE CHARGE FOR THE PERIOD OF PERFORMANCE MARCH 26, 2024 TO APRIL 25, 2024.
2024-03-04P00127Supplemental agreement (work within scope)$51.7KTHE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE AW TO FURNISH AND INSTALL A NEW SANITARY SEWER SERVICE NEAR BUILDING 65.
2024-02-26P00126Supplemental agreement (work within scope)$7.2KTHE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE AW TO FURNISH AND INSTALL A NEW 1-INCH REDUCED PRESSURE ZONE (RPZ) BACKFLOW PREVENTER AT BUILDING 232F.
2024-02-22P00125Funding only$631.8KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF FEB. 26, 2024 - MARCH. 25, 2024.
2024-02-09P00124Funding only$631.8KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF JAN. 26, 2024 - FEB. 25, 2024.
2024-02-08P00123Supplemental agreement (work within scope)$465.2KTHE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE AW TO COMPLETE NEW SERVICE CONNECTIONS TO BUILDING 424.
2024-02-05P00122Funding only$631.8KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF DEC. 26, 2023 - JAN 25, 2024.
2024-01-30P00121Supplemental agreement (work within scope)$37.7KESTABLISHES AND FUNDS CONTRACT YEAR 10 (CY10) ECONOMIC PRICE ADJUSTMENT (EPA)
2023-12-11P00120Administrative change$0TO REVISE SECTION J, LIST OF ATTACHMENTS, TO INCORPORATE THE CURRENT WAGE DETERMINATION AT ATTACHMENT JA4 WAGE DETERMINATION.
2023-12-05P00119Funding only$594.1KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF NOV 26, 2023 - DEC 25, 2023.
2023-11-09P00118Funding only$594.1KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE ONE MONTH OF FUNDING EACH FOR THE WATER AND WASTEWATER UTILITY SERVICES CHARGE FOR THE PERIOD OF NOV 26, 2023 - NOV 25, 2024.
2023-09-25P00117Supplemental agreement (work within scope)$290.3KFUNDS THE INSTALLATION OF WELL 302D EMERGENCY BACK-UP GENERATOR
2023-09-25P00116Supplemental agreement (work within scope)$19.3KFUNDS THE REMOVAL OF CARBON WASTE FROM REPLACEMENT WELL.
2023-08-11P00115Supplemental agreement (work within scope)$11.0KCONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-07-06P00114Administrative change$0CONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-06-30P00113Supplemental agreement (work within scope)$507.5KCONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-06-26P00112Change order$0CONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-05-22P00111Administrative change$1.78MCONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-04-21P00110Funding only$1.78MCONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-03-21P00109Supplemental agreement (work within scope)$33.4KCONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-03-20P00108Administrative change$0CONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-03-03P00107Administrative change$0CONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ.
2023-03-02P00106Funding only$1.78MCONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ.
2023-01-31P00105Supplemental agreement (work within scope)$1.19MCONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL NJ
2023-01-24P00104Supplemental agreement (work within scope)$0CONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-01-13P00103Funding only$564.2KCONTRACT FOR PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ
2023-01-03P00102Administrative change$0CONTRACT FOR THE PRIVATIZATION OF POTABLE AND SERVICE WATER DISTRIBUTION AND WASTEWATER COLLECTION LOCATED ON PICATINNY ARSENAL, NJ

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-22). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗