MILCON - CONSTRUCT C-130 FLIGHT SIMULATOR TRAINING FACILITY
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
8 actions since 2022-12-23. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2025-10-16 | P00007 | Supplemental agreement (work within scope) | $0 | C-130 FLIGHT SIMULATOR FACILITY PROJECT NUMBER VBDZ179043PROJECT DESCRIPTIONTHE CONTRACTOR SHALL PROVIDE ALL MATERIAL, LABOR, EQUIPMENT, AND SUPERVISION TO CONSTRUCT A NEW C-130 FLIGHT SIMULATOR FACILITY. |
| 2025-09-24 | P00006 | Supplemental agreement (work within scope) | $86.3K | C-130 FLIGHT SIMULATOR FACILITY PROJECT NUMBER VBDZ179043PROJECT DESCRIPTIONTHE CONTRACTOR SHALL PROVIDE ALL MATERIAL, LABOR, EQUIPMENT, AND SUPERVISION TO CONSTRUCT A NEW C-130 FLIGHT SIMULATOR FACILITY. |
| 2025-04-22 | P00005 | Supplemental agreement (work within scope) | $233.6K | MODIFICATION TO CORRECT OVERHEAD DOOR SIZE AND COMMUNICATIONS FIBER RUN DUE TO INCORRECT BASIS OF DESIGN. |
| 2024-08-29 | P00004 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO EXTEND THE PERIOD OF PERFORMANCE DUE TO UNANTICIPATED POTENTIAL DESIGN CHANGES BY AIR MOBILITY COMMAND (AMC) |
| 2024-05-31 | P00003 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO EXTEND CONTRACT IN ORDER TO ALLOW ADEQUATE TIME FOR FINAL REPORTING, SWPPP CLOSE-OUT, TURF ESTABLISHMENT, PUNCH LIST, FINAL START-UP AND COMMISSIONING. THIS IS A NO-COST EXTENSION. |
| 2024-02-29 | P00002 | Supplemental agreement (work within scope) | $89.3K | MODIFICATION TO ADDRESS THE COST IMPACT OF IN-SCOPE CHANGES TO THE CONTRACT. |
| 2024-02-14 | P00001 | Supplemental agreement (work within scope) | $0 | MODIFICATION TO EXTEND THE COMPLETION DATE UNTIL 31 MAY 2024 DUE TO UNFORESEEN CONDITIONS ENCOUNTERED DURING SITE PREPARATION. |
| 2022-12-23 | 0 | $10.55M | MILCON - CONSTRUCT C-130 FLIGHT SIMULATOR TRAINING FACILITY |