W50UW820F0042↗

Southwest Valley Constructors Co received this contract from W075 Endist TF Barrier, Department of the Army: $31.44M obligated so far for construction of highways, roads, streets, bridges, and railways. It runs to 2027-03-29.

Key facts · data as of Oct 23, 2026

Recipient
Southwest Valley Constructors Co
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W075 Endist TF Barrier (W50UW8)
Obligated to date
$31.44M
Potential value
$68.28M
Ends
2027-03-29

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award W50UW820F0042, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_W50UW820F0042_9700_W9126G19D0017_9700

CONSTRUCTION OF PROJECT FEATURES TIJUANA

Delivery Order · Department of the Army · to Southwest Valley Constructors Co (UEI W31DQKBPJCD3) · data as of 2026-10-23

Obligated to date$31.44M23 actions
Current value$66.54Mwith options exercised
Potential value$68.28Mif every option is used
Period2020-09-24 → 2027-03-29current end date
Passed on$15.48Mto 16 subcontractors

Up for re-bid: ends 2027-03-29. Recompete brief →

What it is

Product or service
Construction of Highways, Roads, Streets, Bridges, and Railways (PSC Y1LB)
Industry
Highway, Street, and Bridge Construction (NAICS 237310)
Contracting office
W075 Endist TF Barrier (W50UW8)
Competition
Full and open competition · 3 offers received
Pricing
Firm fixed price
How it was bought
Multiple-award IDIQ · under W9126G19D0017
Where the work is
San Diego, CA · district CA-52

Obligations by fiscal year

FY2023$10.79M
FY2024$2.02M
FY2025$4.36M
FY2026$14.28M

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

16 subawards totaling $15.48M (49.2% of what was obligated), as Southwest Valley Constructors Co reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.

SubcontractorAmountSubawardsWhereFirstLast
Peter Kiewit Sons Inc$7.02M1TX2023-03-232023-03-23
Fhe USA LLC$1.85M1CO2023-03-092023-03-09
L.B. Foster Company$1.43M1PA2022-12-302022-12-30
Keller North America, Inc.$975.8K1NC2023-03-202023-03-20
Allied Power Products, Inc.$824.5K1OR2023-01-112023-01-11
Nucor Rebar Fabrication Southwest Inc.$620.0K1AZ2023-02-042023-02-04
Spencer Construction LLC$616.6K1AZ2023-10-202023-10-20
Bay Tank & Boiler Works$590.0K1CA2023-01-312023-01-31
Gryphon Investors, Inc.$532.3K1TX2023-01-032023-01-03
Anbessaw Consulting Inc$422.0K1CA2022-10-212022-10-21
G.T.E. Metal Erectors, Inc.$217.8K1OR2022-12-282022-12-28
D III Transport Corporation$170.0K1CA2023-03-282023-03-28
Surveillance Security, Inc$145.5K1AZ2023-04-042023-04-04
Romero General Construction Corp.$32.9K1CA2024-06-072024-06-07
(Dnu) Brundage-Bone Concrete Pumping, Inc.$30.0K1CO2023-04-142023-04-14
Badger Daylighting LTD$10.0K1IN2023-03-152023-03-15
The largest single subawards
DateToAmountFor
2023-03-23Kiewit Offshore Services, LTD.$7.02MSTEEL GIRDER & GATE FRAME FABRICATION AND PAINTING
2023-03-09Fhe USA LLC$1.85MPROVIDE GATES, BOLLARD FENCE, AND BOLLARD WALL FOR THE PROJECT
2022-12-30L.B. Foster Company$1.43MGRID DECKING AND GUARDRAIL
2023-03-20Keller North America, Inc.$975.8KDRILLED SHAFT COMPLETION
2023-01-11Allied Power Products, Inc.$824.5KSUPPLY WINCHES AND WIRE ROPE
2023-02-04Nucor Rebar Fabrication Southwest Inc.$620.0KREBAR FABRICATION AND INSTALLATION
2023-10-20Spencer Construction LLC$616.6KTEMPORARY FENCE SUPPLY AND INSTALL
2023-01-31Bay Tank & Boiler Works$590.0KSUPPLY WIRE MESH AND GATE FRAME STEEL
2023-01-03Shermco Systems Integration, LLC$532.3KELECTRICAL COMPONENTS
2022-10-21Anbessaw Consulting Inc$422.0KQUALITY CONTROL
2022-12-28G.T.E. Metal Erectors, Inc.$217.8KABUTMENT EMBEDS AND HAND RAIL
2023-03-28D III Transport Corporation$170.0KONSITE AND OFFSITE TRUCKING
2023-04-04Surveillance Security, Inc$145.5KSECURITY SERVICES
2024-06-07Romero General Construction Corp.$32.9KFURNISH AND INSTALL ASPHALT PAVING
2023-04-14(Dnu) Brundage-Bone Concrete Pumping, Inc.$30.0KPUMPING CONCRETE
2023-03-15Badger Daylighting Corp$10.0KVAC TRUCK

Every action

23 actions since 2023-05-18. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-06-22P00021Change order$51.2KTHE PURPOSE OF THIS MODIFICATION IS TO: ADDITIONAL VANDALISM REPAIRSSEE ATTACHED SF30 CONTINUATION PAGE.ALL OTHER TERMS AND CONDITIONS TO REMAIN THE SAME.
2026-06-17P00020Supplemental agreement (work within scope)$0THE PURPOSE OF THIS MODIFICATION IS TO: ADDITIONAL VANDALISM REPAIRSSEE ATTACHED SF30 CONTINUATION PAGE.ALL OTHER TERMS AND CONDITIONS TO REMAIN THE SAME.
2026-05-29P00019Change order$1.20MTHE PURPOSE OF THIS MODIFICATION IS TO: ADDITIONAL VANDALISM REPAIRSSEE ATTACHED SF30 CONTINUATION PAGE.ALL OTHER TERMS AND CONDITIONS TO REMAIN THE SAME.
2026-05-29P00018Change order$36.4KTHE PURPOSE OF THIS MODIFICATION IS TO: REQUEST FOR EQUITABLE ADJUSTMENT, CLEANOUT TRASH COLLECTORS AND PROVIDE STAINLESS STEEL SHEETSSEE ATTACHED SF30 CONTINUATION PAGE.ALL OTHER TERMS AND CONDITIONS TO REMAIN THE SAME.
2026-05-01P00017Change order$2.09MTHE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE COMMISSIONING PERIOD REFERENCE REQUEST FOR PROPOSAL NO. R00021. THECONTRACT COMPLETION DATE IS HEREBY EXTENDED TO 2 JANUARY 2027. SEE ATTACHMENT FOR SCOPE OF WORK.
2026-01-10P00016Change order$4.35MTHE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE COMMISSIONING PERIOD REFERENCE REQUEST FOR PROPOSAL NO. R00021. THECONTRACT COMPLETION DATE IS HEREBY EXTENDED TO 2 JANUARY 2027. SEE ATTACHMENT FOR SCOPE OF WORK.
2025-11-12P00015Supplemental agreement (work within scope)$6.55MCONSTRUCTION OF PROJECT FEATURES TIJUANA RIVER CROSSING - VANDALISM REPAIR
2025-04-07A00006Supplemental agreement (work within scope)-$30.1KTIJUANA RIVER CROSSING, SAN DIEGO, CA. DELETE CCTV FIBER OPTIC CABLE
2025-03-03P00014Supplemental agreement (work within scope)$4.07MTIJUANA RIVER CROSSING - TRO AND CHANNEL CLEANUP REA
2025-02-26A00005Supplemental agreement (work within scope)$0TIJUANA RIVER CROSSING - WEATHER DELAY MOD
2025-01-22A00004Change order$318.2KTIJUANA RIVER CROSSING, SAN DIEGO, CA. DSC FOR COBBLES IN SHAFTS 2 THRU 5
2024-09-24A00003Change order$155.3KTIJUANA RIVER CROSSING, SAN DIEGO, CA. DSC FOR ELEVATED GROUNDWATER TABLE
2024-09-20P00013Change order$12.2KTIJUANA RIVER CROSSING - DSC FOR COBBLES IN DRILLED SHAFT
2024-09-19P00012Change order$111.7KTIJUANA RIVER CROSSING - REA FOR HURRICANE HILLARY PREP
2024-09-19P00011Change order$738.6KTIJUANA RIVER CROSSING - CHANNEL DIVERSION REA
2024-09-18P00010Change order$124.1KTIJUANA RIVER CROSSING - DSC REA DRILLED SHAFT SPLIT MOBILIZATION
2024-09-18P00009Supplemental agreement (work within scope)$34.3KTIJUANA RIVER CROSSING - DSC FOR METAL DEBRIS
2024-08-14A00002Supplemental agreement (work within scope)$0CONSTRUCTION OF PROJECT FEATURES TIJUANA WEATHER DELAY EXTENSION
2024-08-13A00001Administrative change$0CONSTRUCTION OF PROJECT FEATURES TIJUANA - ADMIN MOD FOR FUNDING CHANGE
2024-08-01P00008Supplemental agreement (work within scope)$10.3KTIJUANA RIVER CROSSING, SAN DIEGO, CA DIFFERING SITE CONDITION
2023-11-03P00007Supplemental agreement (work within scope)$834.4KTIJUANA RIVER CROSSING - TEMPORARY FENCE
2023-06-06P00006Change order$2.83MCONSTRUCTION OF PROJECT FEATURES TIJUANA RIVER BRIDGE BARRIER
2023-05-18P00005Change order$7.96MCONSTRUCTION OF PROJECT FEATURES TIJUANA

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗