W519TC23F0017↗

Bae Systems Ordnance Systems Inc received this contract from W6QK Acc-Ri, Department of the Army: $94.17M obligated so far for operation of ammunition facilities. It runs to 2026-10-31.

Key facts · data as of Oct 28, 2026

Recipient
Bae Systems Ordnance Systems Inc
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W6QK Acc-Ri (W519TC)
Obligated to date
$94.17M
Potential value
$94.17M
Ends
2026-10-31

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 28, 2026.

Cite this page: SpendQuery, Award W519TC23F0017, data as of Oct 28, 2026, https://spendquery.com/award?id=CONT_AWD_W519TC23F0017_9700_W52P1J11G0002_9700

TASK ORDER W519TC23F0017 IS ISSUED FOR AWARD OF AN UCA FOR CONSTRUCTION OF A NEW CHEMICAL GRIND FACILITY AT RADFORD ARMY AMMUNITION PLANT.

Delivery Order · Department of the Army · to Bae Systems Ordnance Systems Inc (UEI PFGVR4NPLNB2) · data as of 2026-10-28

Obligated to date$94.17M8 actions
Current value$94.17Mwith options exercised
Period2022-11-30 → 2026-10-31current end date

Up for re-bid: ends 2026-10-31. Recompete brief → · Telecommunications Fiber Optic Upgrades at Iowa Army Ammunition Plant ↗

What it is

Product or service
Operation of Ammunition Facilities (PSC M1EA)
Industry
Facilities Support Services (NAICS 561210)
Contracting office
W6QK Acc-Ri (W519TC)
Competition
Full and open competition · 1 offer received
Pricing
Firm fixed price
How it was bought
Basic ordering agreement (BOA) · under W52P1J11G0002
Where the work is
Radford (City), VA · district VA-09

Obligations by fiscal year

FY2023$79.89M
FY2024$14.29M
FY2026$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

8 actions since 2022-11-30. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2025-11-25P00007Administrative change$0ADMIN MOD TO USE SEVERABLE OPTIONS WHICH HAVE PREVIOUSLY BEEN FUNDED ON A PRIOR MOD, BUT REQUIRE THE CONTRACTOR REQUEST USG PERMISSION TO ACTIVATE.
2024-09-25PZ0006Letter contract definitized$4.29MTASK ORDER W519TC23F0017 IS FOR CONSTRUCTION OF A NEW CHEMICAL GRIND FACILITY AT RADFORD ARMY AMMUNITION PLANT. MODIFICATION P00006 IS TO DEFINITIZE THE UNDEFINITIZED CONTRACT ACTION (UCA) AND OBLIGATE ADDITIONAL FUNDING.
2024-02-29P00005Supplemental agreement (work within scope)$10.00MTASK ORDER W519TC-23-F-0017 IS FOR CONSTRUCTION OF A NEW CHEMICAL GRIND FACILITY AT RADFORD ARMY AMMUNITION PLANT. MODIFICATION P00005 IS TO UPDATE THE UNDEFINITIZED CONTRACT ACTION NOT TO EXCEED CEILING AND INCREASE FUNDING.
2024-01-29P00004Supplemental agreement (work within scope)$0THE PURPOSE OF MODIFICATION P00004 TO TASK ORDER W519TC23F0017 IS TO CORRECT THE PERFORMANCE BASED PAYMENT MILESTONE SCHEDULE TO SEPARATE THE REQUIREMENTS WITHIN MILESTONE #4 AND #5 FOR INVOICING PURPOSES.
2023-09-29P00003Supplemental agreement (work within scope)$932.3KTHIS MODIFICATION IS TO ADD REVISED ECONOMIC ASSUMPTION DUE TO MATERIAL COST ESCALATION THAT WILL INCREASE THE NTE CEILING VALUE IN SUPPORT OF THE CHEMICAL GRIND CONSTRUCTION EFFORT AT RFAAP.
2023-07-28P00002Supplemental agreement (work within scope)$0THIS MODIFICATION IS TO UPDATE THE SOW, CDRLS, AND PBP MILESTONE PAYMENTS TO THE MOST RECENT VERSIONS. NONE ARE FINALIZED UNTIL DEFINITIZATION IS COMPLETE, BUT THESE ARE THE MOST ACCURATE AND UP TO DATE VERSION OF THESE DOCUMENTATIONS.
2023-06-30P00001Change order$39.48MTHIS MODIFICATION IS TO INCREASE THE FUNDING OF THE UCA TO 100% OF THE NTE CEILING VALUE, IN SUPPORT OF THE CHEMICAL GRIND FACILITY CONSTRUCTION EFFORT AT RFAAP.
2022-11-300$39.48MTASK ORDER W519TC23F0017 IS ISSUED FOR AWARD OF AN UCA FOR CONSTRUCTION OF A NEW CHEMICAL GRIND FACILITY AT RADFORD ARMY AMMUNITION PLANT.

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-28). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗