W51DQV26CA003↗

Ferrovial Construccion PR, LLC received this contract from W2SR Endist Caribbean(Provis), Department of the Army: $1.08B obligated so far for construction of canals. It runs to 2032-07-11.

Key facts · data as of Oct 21, 2026

Recipient
Ferrovial Construccion PR, LLC
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W2SR Endist Caribbean(Provis) (W51DQV)
Obligated to date
$1.08B
Potential value
$1.08B
Ends
2032-07-11

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 21, 2026.

Cite this page: SpendQuery, Award W51DQV26CA003, data as of Oct 21, 2026, https://spendquery.com/award?id=CONT_AWD_W51DQV26CA003_9700_-NONE-_-NONE-

RIO PUERTO NUEVO FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 3 CHANNEL BOTTOM AND WALL IMPROVEMENTS IN SAN JUAN, PR. INCLUDES CHANNEL WIDENING AND DEEPENING, DRILLED SHAFT WALLS, DREDGING, AND UTILITY RELOCATIONS.

Definitive Contract · Department of the Army · to Ferrovial Construccion PR, LLC (UEI KGKPT8C8SMB1) · data as of 2026-10-21

Obligated to date$1.08B2 actions
Current value$1.08Bwith options exercised
Period2026-04-30 → 2032-07-11current end date

What it is

Product or service
Construction of Canals (PSC Y1KB)
Industry
Other Heavy and Civil Engineering Construction (NAICS 237990)
Contracting office
W2SR Endist Caribbean(Provis) (W51DQV)
Competition
Full and open competition · 3 offers received
Pricing
Firm fixed price
How it was bought
Standalone contract
Where the work is
Guaynabo, PR · district PR-98

Obligations by fiscal year

FY2026$1.08B

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

2 actions since 2026-04-30. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-07-13P00001Supplemental agreement (work within scope)$0RIO PUERTO NUEVO FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 3 CHANNEL BOTTOM AND WALL IMPROVEMENTS IN SAN JUAN, PR. INCLUDES CHANNEL WIDENING AND DEEPENING, DRILLED SHAFT WALLS, DREDGING, AND UTILITY RELOCATIONS.
2026-04-300$1.08BRIO PUERTO NUEVO FLOOD CONTROL PROJECT, SUPPLEMENTAL CONTRACT 3 CHANNEL BOTTOM AND WALL IMPROVEMENTS IN SAN JUAN, PR. INCLUDES CHANNEL WIDENING AND DEEPENING, DRILLED SHAFT WALLS, DREDGING, AND UTILITY RELOCATIONS.