W52P1J19F0370↗
American Ordnance LLC received this contract from W6QK Acc-Ri, Department of the Army: $1.50M obligated so far for operation of ammunition facilities. Its period of performance ended 2025-01-31.
Key facts · data as of Oct 25, 2026
- Recipient
- American Ordnance LLC
- Awarding agency
- Department of the Army (Department of Defense)
- Contracting office
- W6QK Acc-Ri (W519TC)
- Obligated to date
- $1.50M
- Potential value
- $49.55M
- Ends
- 2025-01-31
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 25, 2026.
Cite this page: SpendQuery, Award W52P1J19F0370, data as of Oct 25, 2026, https://spendquery.com/award?id=CONT_AWD_W52P1J19F0370_9700_W52P1J09G0001_9700
American Ordnance LLC: all federal awards · Department of Defense: spending · W6QK Acc-Ri: what it buys
PHASE 1 DESIGN CHARRETTE FOR MODERNIZED MELT/POUR FACILITY AT IAAAP
What it is
- Product or service
- Operation of Ammunition Facilities (PSC M1EA)
- Industry
- Facilities Support Services (NAICS 561210)
- Contracting office
- W6QK Acc-Ri (W519TC)
- Competition
- Full and open competition
- Pricing
- Cost plus fixed fee
- How it was bought
- Single-award IDIQ · under W52P1J09G0001
- Where the work is
- Des Moines, IA · district IA-01
Obligations by fiscal year
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
Subcontractors: where the money went next
No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.
Every action
8 actions since 2022-10-12. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2024-12-03 | P00022 | Supplemental agreement (work within scope) | $839.2K | DESIGN THE FUTURE ARTILLERY COMPLEX AT IOWA ARMY AMMUNITION PLANT. |
| 2024-08-29 | P00021 | Supplemental agreement (work within scope) | $658.6K | DESIGN THE FUTURE ARTILLERY COMPLEX AT IOWA ARMY AMMUNITION PLANT. |
| 2023-10-26 | P00020 | Supplemental agreement (work within scope) | $0 | DESIGN THE FUTURE ARTILLERY COMPLEX AT IOWA ARMY AMMUNITION PLANT. |
| 2023-05-31 | P00019 | Supplemental agreement (work within scope) | $0 | TASK ORDER W52P1J19F0370 IS FOR THE CONTRACTOR TO PROVIDE THE GOVERNMENT WITH AN APPROVED DESIGN FOR THE FUTURE ARTILLERY COMPLEX AT THE IOWA ARMY AMMUNITION PLANT. MODIFICATION P00019 EXTENDS THE PERIOD OF PERFORMANCE ON 60% AND 90% DESIGN CLINS. |
| 2023-04-24 | P00018 | Funding only | $0 | ORDER W52P1J19F0370 IS FOR THE CONTRACTOR TO PROVIDE A GOVERNMENT APPROVED DESIGN FOR THE FUTURE ARTILLERY COMPLEX AT THE IOWA ARMY AMMUNITION PLANT. MODIFICATION P00018 REALIGNS FUNDING FROM THE 90% DESIGN TO THE 60% DESIGN. |
| 2023-02-01 | P00017 | Supplemental agreement (work within scope) | $0 | IAAAP - BOA W52P1J-09-G-0001, TO W52P1J19F0370 - MOD P00017 IS TO INCORPORATE THE SMALL BUSINESS SUBCONTRACTING PLANS (SBSPS) FOR CONTRACT LINE ITEM NUMBERS 0001AC, 0001AD, 0004AA, AND 0004AB. |
| 2022-11-09 | P00016 | Supplemental agreement (work within scope) | $0 | THIS TASK ORDER IS FOR DESIGN - MODERNIZED LONG-RANGE PRECISION ARTILLERY PRODUCTION FACILITY AT IOWA ARMY AMMUNITION PLANT. MODIFICATION P00016 EXTENDS THE PERIOD OF PERFORMANCE OF CLINS 0001AC AND 0001AD. |
| 2022-10-12 | P00015 | Supplemental agreement (work within scope) | $0 | MODERNIZED LONG-RANGE PRECISION ARTILLERY PRODUCTION FACILITY AT IOWA ARMY AMMUNITION PLANT (IAAAP). MODIFICATION P00015 FIXES A FUNDING ERROR ON CLIN 0001AA AND CHANGES THE ISSUED BY AND ADMIN BY DODAACS. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-25). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗