DRS Sustainment Systems, Inc received this contract from W6QK Acc- Dta, Department of the Army: $251.90M obligated so far for bridges, fixed and floating. It runs to 2028-09-30.
Key facts · data as of Oct 21, 2026
Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 21, 2026.
Cite this page: SpendQuery, Award W56HZV16C0028, data as of Oct 21, 2026, https://spendquery.com/award?id=CONT_AWD_W56HZV16C0028_9700_-NONE-_-NONE-
DRS Sustainment Systems, Inc: all federal awards · Department of Defense: spending · W6QK Acc- Dta: what it buys · The follow-on: recompete brief
LOW RATE INITIAL PRODUCTION/FULL RATE PRODUCTION FOR THE JOINT ASSAULT BRIDGE.
Up for re-bid: ends 2028-09-30. Recompete brief →
SpendQuery holds FY2023 on; earlier years are on USAspending.gov.
242 subawards totaling $51.61M (20.5% of what was obligated), as DRS Sustainment Systems, Inc reported them. Primes report subawards of $30,000 or more; smaller ones and unreported ones aren't here.
| Subcontractor | Amount | Subawards | Where | First | Last |
|---|---|---|---|---|---|
| Elite Tool LLC | $8.14M | 36 | MO | 2022-12-22 | 2025-04-17 |
| Leonardo S.P.A. | $7.42M | 9 | FL | 2023-08-11 | 2024-12-11 |
| Jarp Industries, Inc. | $5.94M | 4 | WI | 2022-11-22 | 2025-02-24 |
| Charles E. Gillman Company | $4.85M | 4 | AZ | 2022-12-20 | 2024-12-17 |
| Purolator Facet, Inc. | $2.59M | 19 | IA, IL, OH | 2023-05-12 | 2024-11-18 |
| Loc Performance Products LLC | $1.89M | 8 | MI | 2022-11-22 | 2025-04-21 |
| Hyspeco, Inc. | $1.55M | 20 | MO | 2023-02-23 | 2024-12-17 |
| Sanmar Holdings LTD. | $1.46M | 4 | IA | 2023-05-12 | 2025-02-11 |
| Planet Tool & Gear Inc | $1.21M | 15 | MO | 2023-03-17 | 2025-05-02 |
| Deutz Corporation | $1.14M | 2 | GA | 2023-08-08 | 2024-09-05 |
| Kidde Technologies Inc | $1.09M | 4 | NC | 2023-08-01 | 2024-11-18 |
| L. E. F., Inc. | $996.0K | 8 | OK | 2023-03-13 | 2025-03-17 |
| Custom Manufacturing & Engineering, Inc | $988.2K | 4 | FL | 2023-08-03 | 2024-12-09 |
| Ultra Electronics Holdings PLC | $910.3K | 3 | CT | 2023-08-31 | 2025-05-02 |
| Digital Systems Engineering Inc | $902.0K | 3 | AZ | 2023-07-19 | 2024-10-15 |
| Arch City Steel and Alloy, Inc. | $830.8K | 7 | MO | 2023-03-09 | 2025-05-17 |
| Cadco Program and Machine, Inc. | $790.0K | 5 | MO | 2023-04-18 | 2024-10-31 |
| Ravelin Defense, Inc. | $747.2K | 2 | AZ | 2024-07-01 | 2024-12-19 |
| Integral Components, Inc. | $734.3K | 1 | MD | 2024-12-04 | 2024-12-04 |
| Q & C International Inc | $635.9K | 8 | MO | 2023-03-16 | 2025-04-22 |
| Magna Machine Co. | $625.1K | 4 | OH | 2023-08-02 | 2024-12-18 |
| Bearings and Industrial Supply Co., Inc. | $528.8K | 4 | IL | 2023-12-06 | 2025-02-26 |
| Heizer Aerospace, Inc. | $456.8K | 4 | MO | 2023-07-18 | 2024-05-13 |
| Onodi Tool & Engineering Co | $444.7K | 7 | MI | 2022-12-19 | 2024-05-29 |
| Armorworks Holdings Inc. | $390.1K | 1 | AZ | 2022-10-27 | 2022-10-27 |
The 25 largest of 50; the rest are on USAspending.gov.
| Date | To | Amount | For |
|---|---|---|---|
| 2023-08-11 | DRS Systems, Inc | $3.93M | CAMERAS |
| 2025-02-24 | Jarp Industries, Inc. | $2.74M | HYDRAULIC CYLINDERS |
| 2023-09-25 | Jarp Industries, Inc. | $2.60M | HYDRAULIC CYLINDERS |
| 2024-09-11 | DRS Systems, Inc | $2.49M | CAMERAS |
| 2023-04-18 | Elite Tool LLC | $1.96M | METAL FABRICATED PARTS |
| 2022-12-20 | Charles E. Gillman Company | $1.81M | ELECTRICAL CABLE HARNESSES |
| 2023-08-31 | Charles E. Gillman Company | $1.47M | CABLE HARNESS ASSEMBLIES |
| 2023-05-28 | Elite Tool LLC | $1.37M | METAL FABRICATED PARTS |
| 2024-12-17 | Charles E. Gillman Company | $1.37M | CABLE HARNESSES |
| 2023-08-08 | Deutz Corporation | $968.2K | DIESEL ENGINES |
| 2024-12-04 | Integral Components, Inc. | $734.3K | CABLE HARNESS ASSEMBLIES |
| 2023-08-01 | Kidde Technologies Inc | $730.4K | FIRE SUPPRESION COMPONENTS |
| 2023-03-30 | Loc Performance Products LLC | $715.3K | METAL FABRICATED PARTS |
| 2024-12-19 | Ravelin Defense, Inc. | $609.5K | CUSTOM SEAT |
| 2024-12-17 | Elite Tool LLC | $605.9K | METAL FABRICATED PARTS |
| 2025-02-11 | Keokuk Mills, LLC | $599.4K | ARMOR STEEL CASTINGS |
| 2023-08-31 | Measurement Systems Inc | $562.7K | HAND CONTROLLERS |
| 2024-11-18 | Elite Tool LLC | $557.5K | METAL FABRICATED PARTS |
| 2022-11-22 | Jarp Industries, Inc. | $515.3K | HYDRAULIC CYLINDERS |
| 2025-02-23 | Elite Tool LLC | $468.7K | METAL FABRICATED PARTS |
| 2023-08-15 | Keokuk Mills, LLC | $446.5K | CASTINGS |
| 2023-04-17 | Elite Tool LLC | $432.6K | METAL FABRICATED PARTS |
| 2023-08-03 | Custom Manufacturing & Engineering, Inc | $423.9K | CONTROL PANELS |
| 2024-12-11 | DRS Systems, Inc | $420.2K | SOFTWARE DESIGN SERVICES |
| 2023-07-19 | Digital Systems Engineering Inc | $413.5K | DISPLAYS |
69 actions since 2022-10-25. Each is a modification or amendment with the money it added or took back.
| Date | Modification | Kind | Amount | What the agency wrote |
|---|---|---|---|---|
| 2026-07-20 | P00178 | Funding only | $0 | JAB HYBRID CONTRACT, PRODUCTION AND SERVICES, FOREIGN AND DOMESTIC |
| 2026-06-17 | P00177 | Supplemental agreement (work within scope) | $0 | JOINT ASSAULT BRIDGE SCHEDULE UPDATE. |
| 2026-06-01 | P00175 | Supplemental agreement (work within scope) | $0 | ADMIN MOD TO UPDATE SECTION C AND CDRLS. |
| 2026-05-29 | P00176 | Supplemental agreement (work within scope) | $0 | DELIVERY SCHEDULE UPDATE |
| 2026-05-08 | P00173 | Supplemental agreement (work within scope) | $544.7K | CONTRACTOR LOGISTIC SUPPORT (CLS) OPTION EXERCISE FOR CONUS AND OCONUS SUPPORT. |
| 2026-05-07 | P00174 | Supplemental agreement (work within scope) | -$223.6K | JAB PRODUCTION AND SERVICES |
| 2026-03-31 | P00172 | Supplemental agreement (work within scope) | $0 | JAB PRODUCTION CONTRACT |
| 2026-03-31 | P00171 | Option exercised | $44.98M | OPTION CALL UP FOR 20 JOINT ASSAULT BRIDGE (JAB) SYSTEMS AND SPARES UNDER OPTION YEAR 9 UNDER CONTRACT W56HZV-16-C-0028. |
| 2026-03-23 | P00170 | Funding only | $0 | DE-OB |
| 2026-02-25 | P00169 | Supplemental agreement (work within scope) | $300.8K | CLS SUPPORT FOR THE 370TH BRIGADE |
| 2026-01-30 | P00168 | Supplemental agreement (work within scope) | $0 | DELIVERY SCHEDULE UPDATE FOR W56HZV-16-C-0028. |
| 2026-01-29 | P00167 | Change order | $0 | JOINT ASSAULT BRIDGE MFOCS PHASE II ECP |
| 2026-01-12 | P00166 | Supplemental agreement (work within scope) | $4.46M | JOINT ASSAULT BRIDGE MFOCS PHASE II ECP |
| 2025-09-23 | P00165 | Option exercised | $1.47M | OPTION EXERCISE FOR ASL KITS UNDER OPTION YEAR 9 |
| 2025-08-20 | P00164 | Supplemental agreement (work within scope) | -$206.1K | ADMINISTRATION MODIFICATION FOR JOINT ASSAULT BRIDGE (JAB) CONTRACT W56HZV-16-C-0095 |
| 2025-08-07 | P00163 | Supplemental agreement (work within scope) | $666.3K | JOINT ASSAULT BRIDGE OPTION YEAR 9 FSR OPTION EXERCISE |
| 2025-07-21 | P00162 | Administrative change | $0 | EXECUTIVE ORDER 14173 |
| 2025-06-26 | P00161 | Option exercised | $3.99M | JAB OPTION FOR 2 JAB SYSTEMS. |
| 2025-06-24 | P00159 | Supplemental agreement (work within scope) | $7.18M | CONTRACT FOR THE AWARD OF JOINT ASSAULT BRIDGE SYSTEMS (JAB) TECHNICAL MANUAL UPDATES TO VARIOUS ENGINEERING CHANGE PROPOSALS. |
| 2025-06-02 | P00160 | Supplemental agreement (work within scope) | $1.69M | FIELD SERVICE REPRESENTATIVE SUPPORT AND SPARES SUPPORTING FMS CASE FOR AUSTRALIA JOINT ASSAULT BRIDGES. |
| 2025-05-09 | P00158 | Option exercised | $53.90M | OPTION BUY OF 27 JOINT ASSAULT BRIDGE SYSTEMS UNDER OPTION YEAR 8 OF CONTACT W56HZV-16-C-0028. |
| 2025-04-30 | P00157 | Supplemental agreement (work within scope) | $0 | SCHEDULE UPDATE FOR THE JOINT ASSAULT BRIDGE. |
| 2025-03-27 | P00156 | Supplemental agreement (work within scope) | $247.5K | THIS CONTRACT IS TO PURCHASE JOINT ASSAULT BRIDGE (JAB) SYSTEMS. THIS MODIFICATION IS TO INCORPORATE INCREASED COSTS FROM VARIOUS ECP UPDATES AS WELL AS THE INCREASED COSTS SINCE THE CLIN WAS INITIALLY PRICED AND AWARDED IN 2016. |
| 2025-02-28 | P00155 | Supplemental agreement (work within scope) | $0 | JOINT ASSAULT BRIDGE (JAB) IS A SUPPLIES AND SERVICES CONTRACT. MODIFICATION P00155 CLIN 8051 IS BEING REVISED TO EXTEND THE POP FROM 01 MARCH 2025 TO 01 MARCH 2026 AT NO ADDITIONAL COST TO FMS CASE PL-B-UDT. |
| 2024-12-23 | P00154 | Supplemental agreement (work within scope) | $0 | JOINT ASSAULT BRIDGE (JAB) IS A SUPPLIES AND SERVICES CONTRACT. MODIFICATION P00154 INCORPORATES SIGNED ECPS AND RFVS AS WELL AS DECREASES THE QUANTITY ON ONE RESET CLIN. |
| 2024-11-26 | P00153 | Supplemental agreement (work within scope) | $1.75M | THE JOINT ASSAULT BRIDGE (JAB) IS A HARDWARE AND SERVICES CONTRACT. MOD P00153 FUNDS THE NRE FOR THE MATERIAL WORK ORDERS (MWOS) FOR THE BLM ADD ON ARMOR AND PARKING BRAKE UPGRADE ECPS AND UPDATES THE DELIVERY SCHEDULE ON MULTIPLE JABS. |
| 2024-11-18 | P00152 | Funding only | $0 | THIS IS A HARDWARE AND SERVICES CONTRACT. THIS ACTION IS TO COMPLETE A FUNDS SWAP FOR THE CURRENT PERIOD'S BLM ASL AND STTE CLINS IN ADDITION TO AN HOURS AND FUNDS SWAP ON MULTIPLE FMS SUPPORT CLINS. THE ASL AND STTE ACTION DE-OBLIGATED PROGRAM OF RECORD… |
| 2024-10-01 | ARZ993 | Administrative change | $0 | LOW RATE INITIAL PRODUCTION/FULL RATE PRODUCTION FOR THE JOINT ASSAULT BRIDGE. |
| 2024-09-20 | P00151 | Change order | $635.1K | THIS IS A HARDWARE AND SERVICES ACTION. MODIFICATION P00151 ESTABLISHES AND FUNDS CLIN 8063AA FOR THE EMBEDDED DIAGNOSTICS UPDATE TO UPDATE THE SOFTWARE FROM V1.3 TO V1.4. |
| 2024-09-18 | P00150 | Administrative change | $0 | THIS IS A HARDWARE AND SERVICES CONTRACT. MODIFICATION P00150 DEFINITIZED AN UNPRICED CHANGE ORDER (UCO) THAT WAS ISSUED UNDER THE CONTRACT ON MODIFICATION P00144. THE UCO DEFINITIZES ENGINEERING CHANGES AGAINST 43 JOINT ASSAULT BRIDGE (JAB) SYSTEMS IN… |
| 2024-09-17 | P00149 | Supplemental agreement (work within scope) | $569.4K | THIS IS A HARDWARE AND SERVICES REQUIREMENT. THIS ACTION IS TO RE-ESTABLISH THE BATTLE DAMAGE ASSESSMENT AND REPAIR (BDAR) MANUAL CLIN, CLIN A013 AND OBLIGATE FISCAL YEAR(FY)22 FUNDS. |
| 2024-09-11 | P00148 | Supplemental agreement (work within scope) | -$569.4K | THIS IS A HARDWARE AND SERVICES CONTRACT. MODIFICATION P00148 INCORPORATES TWO REQUESTS FOR VARIANCE (RFVS) AND DE-OBLIGATES FUNDING AGAINST A013 BATTLE DAMAGE ASSESSMENT REPAIR (BDAR) CDRL AS CANCELLED FUNDS ARE AGAINST THE CLIN. |
| 2024-08-15 | P00147 | Funding only | -$801.0K | THIS CONTRACT IS FOR HARDWARE AND SERVICES. THIS MODIFICATION IS TO DE-OBLIGATE MULTIPLE ILCS AND RESET CLINS. THIS ACTION OBLIGATES ONE RESET CLIN. TOTAL DE-OBLIGATION IS (1,912,963.08). TOTAL OBLIGATION IS $1,112,013.00. NET VALUE IS $(800,950.08). |
| 2024-08-12 | P00146 | Supplemental agreement (work within scope) | $4.0K | THIS CONTRACT IS FOR HARDWARE AND SERVICES. THIS MODIFICATION EXERCISES THE FIELD SERVICE REPRESENTATIVE (FSR) CLIN AND ADMINISTRATIVELY CORRECT A CLIN VALUE. |
| 2024-06-28 | P00145 | Supplemental agreement (work within scope) | $0 | MODIFICATION P00145 IS FOR A DELIVERY SCHEDULE CHANGE TO SEVERAL USG AND FMS JABS ON CONTRACT. |
| 2024-06-28 | P00144 | Change order | $5.74M | THIS CONTRACT IS FOR BOTH HARDWARE AND SERVICES. THIS ACTION IS TO ISSUE AN UNPRICED CHANGE ORDER (UCO) TO INCORPORATE ENGINEERING CHANGES AGAINST JOINT ASSAULT BRIDGE (JAB) SYSTEMS THAT ARE IN SUPPORT OF FMS AUSTRALIA, POLAND, AND UKRAINE. |
| 2024-06-12 | P00143 | Option exercised | $41.41M | THIS CONTRACT IS FOR BOTH HARDWARE AND SERVICES. THIS ACTION IS TO EXERCISE 25 JABS (19 USG, 2 EDI, 4 ROMANIA) UNDER OPTION PERIOD EIGHT (11 MAY 2024 THROUGH 11 MAY 2025). |
| 2024-05-21 | P00142 | Supplemental agreement (work within scope) | $3.59M | JOINT ASSAULT BRIDGE CONTRACT. MODIFICATION TO REALIGN FUNDS, EXERCISE THE MFOCS OPTION AND ADD FUNDS TO ADD THE BLM TO LRIP 4. |
| 2024-05-10 | P00141 | Additional work (new agreement) | $1.59M | JAB CONTRACT. MODIFICATION TO FUND ASL AND STTE KITS, PRICED TDP CDRL AND PROPOSAL COSTS. |
| 2024-04-22 | P00140 | Supplemental agreement (work within scope) | $308.3K | THIS CONTRACT IS FOR THE JOINT ASSAULT BRIDGE. THIS ACTION IS FOR ADDING HYDRAULIC POWER UNIT ENGINEER CHANGE PROPOSAL TO THE CONTRACT AS A NON-RECURRING EXPENSE. A PER UNIT CUT-IN WILL FOLLOW. |
| 2024-03-28 | P00139 | Option exercised | $0 | THIS ACTION IS FOR ADDING HOURS TO FMS. |
| 2024-03-12 | P00138 | Supplemental agreement (work within scope) | $0 | THE JOINT ASSAULT BRIDGE IS FOR BOTH HARDWARE AND SERVICES. THIS ACTION IS FOR CHANGING THE SCHEDULE FOR MULTIPLE CLINS. |
| 2024-02-29 | P00137 | Supplemental agreement (work within scope) | $2.43M | THIS CONTRACT HAS BOTH HARDWARE AND SERVICES. THIS ACTION IS FOR THE AWARD OF PHASE II OF THE BRIDGE LAUNCHER MECHANISM (BLM) ARMOR KIT. |
| 2024-02-21 | P00136 | Administrative change | $0 | THIS CONTRACT IS FOR HARDWARE AND SERVICES FOR THE JOINT ASSAULT BRIDGE. THIS ACTION IS TO CHANGE PERIOD OF PERFORMANCES FOR MULTIPLE CONTRACT LINE ITEM NUMBERS. |
| 2024-02-14 | P00134 | Funding only | $453.9K | THE JOINT ASSAULT BRIDGE CONTRACT IS FOR BOTH HARDWARE AND SERVICES. THIS ACTION IS TO INCORPORATE AN ENGINEER CHANGE PROPOSAL FOR THE MOUNTED FAMILY OF COMPUTER SYSTEMS. |
| 2024-02-08 | P00135 | Funding only | -$615.7K | THIS CONTRACT IS FOR BOTH HARDWARE AND SERVICES. THIS ACTION IS TO DEOBLIGATE FUNDS. |
| 2023-11-20 | P00131 | Option exercised | $1.67M | THIS CONTRACT IS FOR BOTH HARDWARE AND SERVICES. THIS ACTION IS TO INCREASE MULTIPLE CONTRACT LINE ITEM NUMBERS FOR THE JOINT ASSAULT BRIDGE RESET EFFORT. |
| 2023-11-03 | P00133 | Option exercised | $2.50M | THIS CONTRACT IS FOR BOTH HARDWARE AND SERVICES FOR THE JOINT ASSAULT BRIDGE (JAB). THIS MODIFICATION IS TO EXERCISE 2 SYSTEMS WITHIN THE 7TH ORDERING YEAR. |
| 2023-11-01 | P00132 | Option exercised | $6.25M | THIS CONTRACT IS FOR BOTH HARDWARE AND SERVICES. THIS MODIFICATION IS FOR THE PROCUREMENT OF 5 JOINT ASSAULT BRIDGES (JABS) IN ORDERING YEAR 7. |
| 2023-09-13 | P00130 | Administrative change | $0 | THE JOINT ASSAULT BRIDGE CONTRACT HAS BOTH HARDWARE AND SERVICES. THIS ACTION IS STRICTLY TO EXTEND PERIOD OF PERFORMANCE. |
| 2023-09-11 | P00129 | Supplemental agreement (work within scope) | $70.0K | THIS CONTRACT HAS BOTH HARDWARE AND SERVICES ASSOCIATED WITH THE JOINT ASSAULT BRIDGE. THIS MODIFICATION IS TO INCORPORATE AN APPROVED REQUEST FOR VARIANCE, ADJUST INSPECTION AND ACCEPTANCE, EXTEND PERIOD OF PERFORMANCE AND TO ADD PAINT COLOR TO FOREIGN… |
| 2023-08-14 | P00128 | Administrative change | $660.3K | THE JOINT ASSAULT BRIDGE (JAB) CONTRACT IS FOR BOTH HARDWARE AND SERVICES. THIS MODIFICATION IS TO ADD A MAN YEAR OF FIELD SERVICE REPRESENTATIVE SUPPORT AND A ENGINEER CHANGE PROPOSAL (ECP) FOR THE LAUNCHER CABLE UNIT. |
| 2023-08-02 | P00127 | Change order | $279.8K | THIS ACTION IS FOR A MAN-YEAR OF FIELD SERVICE REPRESENTATIVE AT FORT CAVAZOS. |
| 2023-07-18 | P00126 | Option exercised | $0 | THIS CONTRACT IS FOR THE PURCHASE OF JOINT ASSAULT BRIDGE SYSTEMS. |
| 2023-06-29 | P00125 | Option exercised | $232.5K | THIS CONTRACT IS FOR THE PURCHASE OF JOINT ASSAULT BRIDGE SYSTEMS. |
| 2023-06-26 | P00124 | Administrative change | $0 | THIS CONTRACT IS FOR THE PURCHASE OF JOINT ASSAULT BRIDGE SYSTEMS. |
| 2023-06-01 | P00123 | Administrative change | $0 | THIS ACTION IS TO ADD CAMP HUMPHREYS AS A LOCATION AND TO UPDATE THE DD254 ATTACHMENT |
| 2023-05-31 | P00122 | Option exercised | $0 | THIS ACTION IS TO ADD THE ABILITY TO SPEAK TO THE CONTRACTOR REGARDING FOREIGN MILITARY SALES. EXERCISING 300 HOURS. |
| 2023-05-16 | P00118 | Option exercised | $29.02M | THIS ACTION IS FOR THE PROCUREMENT OF 25 JOINT ASSAULT BRIDGE (JAB) |
| 2023-05-11 | P00121 | Option exercised | $179.7K | THIS ACTION FOR TO ADD THE PAINT COLOR CHANGE FOR THE JOINT ASSAULT BRIDGE. |
| 2023-04-12 | P00120 | Option exercised | $419.7K | THIS ACTION IS TO INCREASE CONTRACT LINE ITEMS FOR OPERATOR NEW EQUIPMENT TRAINING, FIELD LEVEL NEW EQUIPMENT TRAINING AND TOTAL PACKAGE FIELDING. ALSO TO ADD APPROVED REQUEST FOR VARIANCE AND ATTACHMENTS. |
| 2023-03-20 | P00119 | Supplemental agreement (work within scope) | $3.49M | JOINT ASSAULT BRIDGE (JAB): CONTRACT TO PROCURE JAB SYSTEMS, MOD TO ADD ICLS SUPPORT. |
| 2023-03-07 | P00117 | Administrative change | $0 | CONTRACT TO PROCURE THE JOINT ASSAULT BRIDGE (JAB). MOD TO UPDATE QUANTITY ON CLIN 6002AC AND UPDATE ATTACHMENT 0030 GFP. |
| 2023-02-07 | P00116 | Supplemental agreement (work within scope) | $299.3K | THIS ACTION IS TO ADD OPNET/FLMNET/TPF AS WELL AS TO ADD ECP FOR THE JAB BRAKE AND REIMBURSEMENT FOR KOREA DETENTION. |
| 2022-12-16 | P00115 | Supplemental agreement (work within scope) | $1.30M | JOINT ASSAULT BRIDGE (JAB) CONTRACT TO PROCURE JAB SYSTEMS. MOD TO EXERCISE OPTIONS FOR FLNET/OPNET, TPF, CSR OT AND STORAGE. |
| 2022-11-29 | P00114 | Administrative change | $2.30M | JOINT ASSAULT BRIDGE (JAB) CONTRACT TO PROCURE JAB SYSTEMS. ADMIN MOD TO ADD COR, EXTEND DATES, UPDATE SECTION G & H AND PERIOD OF PERFORMANCE DATES. |
| 2022-11-04 | P00113 | Supplemental agreement (work within scope) | $20.27M | THIS JAB REQUIREMENT IS TO ORDER 17 JABS. |
| 2022-10-27 | P00112 | Supplemental agreement (work within scope) | $7.15M | CONTRACT TO PROCURE JOINT ASSAULT BRIDGE (JAB). PROCURE 5 JAB SYSTEMS UNDER CLIN 6001. |
| 2022-10-25 | P00111 | Funding only | $324.7K | JOINT ASSAULT BRIDGE (JAB) CONTRACT TO PROCURE JAB SYSTEMS: RE-FUND CLIN 8020AC WITH FY22 FUNDS. |
Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-21). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗