W56ZTN25FA045↗

Arctic Peak LLC received this contract from W6QK Acc-Apg Dir, Department of the Army: $1.77M obligated so far for construction of miscellaneous buildings. Its period of performance ended 2026-09-28.

Key facts · data as of Oct 23, 2026

Recipient
Arctic Peak LLC
Awarding agency
Department of the Army (Department of Defense)
Contracting office
W6QK Acc-Apg Dir (W56ZTN)
Obligated to date
$1.77M
Potential value
$1.77M
Ends
2026-09-28

Source: USAspending.gov prime award records (obligations: money committed, not outlays), data as of Oct 23, 2026.

Cite this page: SpendQuery, Award W56ZTN25FA045, data as of Oct 23, 2026, https://spendquery.com/award?id=CONT_AWD_W56ZTN25FA045_9700_W56ZTN25D0002_9700

THE WORK TO BE DONE UNDER THIS CONTRACT COMPRISES THE FURNISHING OF ALL DESIGN, LABOR, EQUIPMENT, MATERIALS AND SERVICES AND THE PERFORMANCE OF ALL WORK NECESSARY FOR AND INCIDENTAL TO REPLACING THE HEATING SYSTEM IN E4210

Delivery Order · Department of the Army · to Arctic Peak LLC (UEI PMWJHM3WMZK3) · data as of 2026-10-23

Obligated to date$1.77M3 actions
Current value$1.77Mwith options exercised
Period2025-08-15 → 2026-09-28current end date

Up for re-bid: ends 2026-09-28. Recompete brief → · The Post-wide Construction Multiple Award Task Contract (MATOC) ↗

What it is

Product or service
Construction of Miscellaneous Buildings (PSC Y1JZ)
Industry
Commercial and Institutional Building Construction (NAICS 236220)
Contracting office
W6QK Acc-Apg Dir (W56ZTN)
Competition
Not available for competition
Pricing
Firm fixed price
How it was bought
Single-award IDIQ · under W56ZTN25D0002
Where the work is
Harford, MD · district MD-01

Obligations by fiscal year

FY2025$1.77M
FY2026$0

SpendQuery holds FY2023 on; earlier years are on USAspending.gov.

Subcontractors: where the money went next

No subawards reported for this award. Primes report subawards of $30,000 or more; many awards have none.

Every action

3 actions since 2025-08-15. Each is a modification or amendment with the money it added or took back.

DateModificationKindAmountWhat the agency wrote
2026-04-16P00002Administrative change$0THE WORK TO BE DONE UNDER THIS CONTRACT COMPRISES THE FURNISHING OF ALL DESIGN, LABOR, EQUIPMENT, MATERIALS AND SERVICES AND THE PERFORMANCE OF ALL WORK NECESSARY FOR AND INCIDENTAL TO REPLACING THE HEATING SYSTEM IN E4210
2026-04-10P00001Administrative change$0THE WORK TO BE DONE UNDER THIS CONTRACT COMPRISES THE FURNISHING OF ALL DESIGN, LABOR, EQUIPMENT, MATERIALS AND SERVICES AND THE PERFORMANCE OF ALL WORK NECESSARY FOR AND INCIDENTAL TO REPLACING THE HEATING SYSTEM IN E4210
2025-08-150$1.77MTHE WORK TO BE DONE UNDER THIS CONTRACT COMPRISES THE FURNISHING OF ALL DESIGN, LABOR, EQUIPMENT, MATERIALS AND SERVICES AND THE PERFORMANCE OF ALL WORK NECESSARY FOR AND INCIDENTAL TO REPLACING THE HEATING SYSTEM IN E4210

Source: USAspending.gov prime award transactions and FSRS subaward reports, as loaded by SpendQuery (data as of 2026-10-23). Amounts are obligations (money committed), not outlays. The official record on USAspending.gov ↗